Next Article in Journal
Quantitative Analysis of Ferrate(VI) and Its Degradation Products in Electrochemically Produced Potassium Ferrate for Waste Water Treatment
Previous Article in Journal
Knowledge-Based Perturbation LaF-CMA-ES for Multimodal Optimization
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

The Effect of Railway Projects Increasing Safety on the Frequency of Occurrences

Faculty of Civil Engineering, Brno University of Technology, 602 00 Brno, Czech Republic
*
Author to whom correspondence should be addressed.
Appl. Sci. 2024, 14(19), 9143; https://doi.org/10.3390/app14199143
Submission received: 3 September 2024 / Revised: 26 September 2024 / Accepted: 27 September 2024 / Published: 9 October 2024
(This article belongs to the Section Transportation and Future Mobility)

Abstract

:

Featured Application

The presented results are intended for inclusion in the national methodology for the economic evaluation of railway infrastructure projects.

Abstract

This contribution is focused on the presentation of individual research results aimed at evaluating the socio-economic impacts associated with increasing the safety and reliability of the railway transport route. The goal of the research is to propose and subsequently verify an original approach for assessing the impact of the implementation of investment projects, including measures aimed at increasing the safety and reliability of railway transport routes, on the resulting number of occurrences that happen on the railway in the Czech Republic. The proposed procedure is based on several key documents. In addition to already existing national methodologies, these are mainly the database of occurrences managed by the Railway Administration of the Czech Republic, including approximately 1000 occurrences for each year of the evaluated period (2009–2018), and information on 33 projects on the railway transport route, where the effects of their implementation on the overall frequency of occurrences are examined events in the subject location. The output of the research is a methodical approach for assessing the impact of the implementation of projects aimed at increasing the safety and reliability of the railway transport route. We perceive the impact on the occurrences from the point of view of the frequency of their occurrence and from the point of view of the socio-economic impacts that are achieved as a result of the implementation of the projects. From the point of view of the frequency of occurrence, a reduction in its value of 4.63% was found. As part of the research, the impact on the occurrence of extraordinary events is also assessed in the context of the scope of the railway transport route, both with regard to the length of the reconstructed track and also with regard to traffic performance.

1. Introduction

The presented results were processed as part of the research work that took place within the research project “Evaluation of increased safety and reliability of railway infrastructure after its modernization or reconstruction”, which was supported by a grant from the Technology Agency of the Czech Republic.
The economic evaluation of transport constructions is currently generally methodologically enshrined in the Guide to CBA [1], within the framework of the Czech Republic. The detailed evaluation procedure is described in the so-called Departmental Methodology, which was published in 2017 by the Ministry of Transport of the Czech Republic, and which is still continuously updated (the last update took place in 2023) [2,3,4,5]. Various statistical reports on rail transport are also important sources of information. One of the most important documents in this area is, for example, the Transport Yearbook of the Czech Republic, which is published annually by the Ministry of Transport [6]. The basic components of economic evaluation are financial and economic analysis and risk analysis, while the presented research mainly focuses on financial and economic analysis.
The essence of the economic evaluation is to quantify the benefit of the construction implementation for its investor and, in the case of economic analysis, its societal benefits. The issue of evaluating the efficiency of projects implemented on the railway infrastructure is addressed by a number of authors of scientific articles. The key topics in the field of analyzing the efficiency of railway structures are the subject of a background paper [7]. In their work [8], Niu et al. carry out a comparative analysis of systems for evaluating the efficiency of transport construction projects on a sample of 16 countries. The methodological aspects of evaluating the efficiency of projects implemented on the railways are addressed by the authors of the publication [9]. They bring an ecological dimension to the evaluation of the life cycle of complex railway projects. Strelkov et al. in their article [10]. The authors of the paper [11] deal with an interesting analysis of the interaction between technical and economic indicators in an effort to increase the efficiency of operational activities on railways. The subject of the paper [12] is the assessment of the efficiency of control systems with diagnostic functions in railway transport. A very topical topic on which the authors of scientific articles are currently focusing is the issue of high-speed lines. The efficiency of operation of high-speed lines is addressed in the paper [13]. The authors Zhang et al. focus on the impact of high-speed lines on regions and their performance and on their impact on the environment in the center of municipalities [14]. The economy of high-speed lines is also addressed by the authors of the paper [15], in which they address the complex urban-environmental efficiency of these projects in the territory of China. Also interesting is the comparison which is presented by the authors Yang et al. in their contribution [16]. They compare railway and road projects in their work, especially in terms of economic efficiency and emissions of harmful gases. The issue of the influence of the choice of material used for the realization of the railway top on the efficiency of railway constructions, including the impact on greenhouse gas emissions, is the subject of the contribution [17].
However, a substantial part of the research is devoted to the issue of increased safety and reliability of the railway infrastructure after its modernization or reconstruction. At the moment, higher reliability or safety after the implementation of investments is not considered in any way, with the exception of an increase in the level of security of railway crossings. Investments in increasing infrastructure reliability are an integral part of every reconstruction or modernization of a track or station. They consist of investments in modern security equipment, communication equipment or, for example, in electric heating of switches or other technical measures.
In the paper [18], Edkins and Pollock analyze the typical causes of railway incidents on Australian railways with a sample of 112 incidents from 1990 to 1994. The contribution is mainly devoted to the human factor and influences that have the highest share in causing human error, the consequence of which is an occurrence. In their 2007 paper [19], Baysari and colleagues analyze the causes of accidents on Australian railways by analyzing 40 investigation reports using the Human Factors Analysis and Classification System (HFACS) tool, concluding that the root cause of 43% of accidents is a defect on the equipment of the railway route due to insufficient supervision or testing. In the case of emergencies caused by the human factor, the main cause is the loss of attention of the driver of the vehicle associated with reduced vigilance and fatigue. Circumstances influencing the human factor in occurrences are further addressed in the contribution by Read et al. [20]. The reliability of the railway and the way to increase it through digitization are subsequently the subjects of the contribution [21].
The article [22], published by Evans, which statistically summarizes the development of occurrences within the EU, Norway, and Switzerland, deals with emergencies on the European railways in the years 1980–2009. In the article [23], Evans addresses the approach to assessing the benefits of some measures to increase railway safety within the EU, the USA, and partly also in Japan, while documenting the low economic profitability of some solutions expressed through the B/C indicator. The reason is the high acquisition costs of automatic train security systems and at the same time the relatively small number of accidents they can prevent. At the same time, however, it points to the fact that each of the accidents that happens on the railway and has human victims is perceived very negatively, which creates pressure for the introduction of safety measures that are not defensible by the standard CBA method. The analysis of 407 railway accidents and their causes is dealt with by Zhou in the article [24], where connections between latent and active faults leading to railway accidents are investigated. Tabaia, in article [25], examines the relationship between education, length of experience, and age in relation to the probability of occurrence of emergency, revealing that there is no directly demonstrable relationship between these factors and the probability of occurrence of an accident; however, he found a connection between level of maintenance and demographic data.
Safety on the railway in the context of its growing importance in the field of suburban transport systems is addressed in the publication [26] by Kim et al. In the publication, they analyze the locations of the most common causes and locations of passenger accidents and at the same time analyze the accident from a demographic point of view. The result is a recommendation to introduce a system of security and transport companies focused especially on critical infrastructure locations and the riskiest parts of the population.
The methodology of the economic evaluation of railway constructions is addressed by Matrai in the article [27], where he examines the difference in the results of the financial and economic analysis carried out ex ante and ex post. In the article, Matrai presents the effects of changes in the assessment methodology of railway constructions in the above-mentioned two cases and, separately, the effects of considering actual costs, transport performance, and macroeconomic indicators instead of the inputs assumed at the time of processing the ex ante assessment. Last but not least, in the case of the modernization of the Sopron–Szombathely–Szentgotthárd line, the economic impact of traffic restrictions during construction is declared, as well as the benefit in the form of higher reliability of rail traffic after the completion of the line modernization. The results show that the increased reliability of rail transport (lower number of train delays) has a non-negligible economic benefit, here specifically EUR 30.9 million, which in the case of this construction is about 15% of the investment costs. It should be considered here that these are non-discounted values and therefore that the overall impact on economic efficiency will not be so significant. At the same time, the results of this research are burdened with a certain amount of uncertainty, because they do not have a sufficient volume of data available, e.g., the data on the average delay of trains after the construction is completed are drawn from only one year, namely, 2011.
Wemakor et al. investigate, in [28], the relationship between rail traffic safety and rail network performance in the context of the UK rail network, using statistical data from 17 transport companies from 2006 to 2016.
Tseng et al., in the study [29], investigate the effects of increased reliability on the results of economic efficiency of railway constructions, while examining these effects on the example of an intercity direct rail connection. According to the conclusions of this study, the increased reliability of rail transport can be a relatively significant benefit of the economic CBA, while it should be emphasized that this is a simplified model of a direct (without transfer) intercity connection.
The background [30] also deals with general contexts associated with the economic analysis of railway projects using the CBA method. In their treatise, Klockner and Toft [31] subsequently declare the necessity of a comprehensive approach including the technical, social, and safety dimensions of modeling the impacts of extraordinary events on a railway transport route.
As part of the research work on the project “Evaluation of increased safety and reliability of the railway infrastructure after its modernization or reconstruction”, the influence of the implementation of specific buildings on the severity and number of occurrences of extraordinary events on the railway transport route is investigated.
The objective of this contribution is to determine the real benefit of the implementation of railway projects involving investments in increasing the safety and reliability of the railway transport route to reduce the occurrence of extraordinary events on the railway transport route and their socio-economic impacts.
Within the presented part of the research, the following research question was formulated:
RQ1: To what extent can the frequency and impact of extraordinary events be reduced through the modernization of the railway infrastructure?

2. Materials and Methods

To evaluate the impact of projects, a database of extraordinary events (MU) on the railway network managed by the Railway Administration (SŽ, s. o.) is available. The database contains data for the entire railway network for 10 years in the period 2009–2018, while each year contains approximately 1100 extraordinary events, which are specified according to various criteria and supplemented with a description containing, among other things, the following:
  • Place and time of creation,
  • Description of MU,
  • Cause of MU,
  • Material damage caused by MU,
  • Damage to life or health, and
  • Train delay.
The mentioned criteria were chosen with regard to the research goal of the project being addressed, i.e., the evaluation of the socio-economic impacts associated with increasing the safety and reliability of the railway transport route. The mentioned criteria sufficiently describe the impacts of occurrences and thus possibly the benefits associated with their reduction.
The total number of data reported for each occurrence varies from year to year. The more recent the data, the more descriptive information they contain. In 2018, the table describing occurrences contains over 100 columns describing occurrences. For each of the years, it is therefore necessary to analyze tens of thousands of cells defining the occurrences.
In order to assess the impact of projects aimed at modernizing the railway transport route on reducing the number and impact of extraordinary events that occur on the railway route, information on the state of extraordinary events in the period before the implementation of the project was used, which was subsequently compared with information on the state of extraordinary events in the period after implementation of the project. For these purposes, a total of 33 projects implemented on the Czech railway were analyzed, and data from the above database of extraordinary events were used to assess the impact of the projects on the number and impact of extraordinary events. An overview of the projects is presented in more detail in the following chapter.
Data on occurrences were analyzed on the lines that were reconstructed as part of the above-mentioned projects. Occurrences appearing at railway crossings were not considered in the aforementioned analysis. In addition, only those occurrences that may arise in connection with insufficient security of the railway transport route in the area of the station or the railway line between stations and at the same time those occurrences that arose as a result of human error were identified as events that can be influenced by the implementation of the new security device. Therefore, the following categories of extraordinary events were considered for the research [32,33]:
A1: collision of railway vehicles resulting in death, injury to the health of at least 5 persons, or extensive damage,
A2: derailment of a railway vehicle resulting in death, injury to the health of at least 5 persons, or extensive damage,
A3: collision of a railway vehicle with an obstacle in the cross-section resulting in death, injury to the health of at least 5 persons, or extensive damage,
B1: collision of railway vehicles with consequences less than a serious accident,
B2: derailment of a railway vehicle with consequences less than a serious accident,
B3: collision of a railway vehicle with an obstacle in the cross-section with consequences less than a serious accident,
C1: collision of railway vehicles with consequences less than a serious accident and an accident,
C2: derailment of a railway vehicle with consequences less than a serious accident and an accident,
C3: collision of a railway vehicle with an obstacle in the cross-section with consequences less than those of a serious accident and an accident,
C6: illegal driving of a railway vehicle behind a sign prohibiting driving with consequences less than those of an accident,
C12: unsecured driving of a railway vehicle with consequences less than an accident,
C16: failure of signaling (security) systems with consequences less than in an accident,
C19: unspecified MU, arising in connection with the movement of a railway vehicle with consequences less than those of an accident.
As part of the presented research, the relationship between the implementation of selected railway projects and the change in the occurrence of extraordinary events was investigated, with the aim of determining the change in the frequency of the occurrence of extraordinary events and their impact on society as a whole—the costs resulting from the loss of human life, injury to health, delays, and last but not least also material damage.

3. Results

The key outputs of the project are the demonstration of the positive effect of projects involving measures to increase the safety and reliability of the railway transport route on reducing the number of extraordinary events occurring on the railway. The outputs are presented in three steps:
  • presentation of a sample of projects for impact assessment (see Table 1),
  • the effect of the evaluated measures on extraordinary events,
  • evaluation of MU within the railway transport route.
The presented results are one of the key outputs of a long-time project entitled “Evaluation of increased safety and reliability of the railway infrastructure after its modernization or reconstruction” financed by the Technological Agency of the Czech Republic. This project was started in 2019. It was formally completed at the end of 2021. However, the implementation of the results and expert discussion are still ongoing. The realization of the research is based on the database of extraordinary events [33]. Due to the start date of work on the project (beginning of 2019), a database from 2011 to 2018 was used to estimate partial outputs. Data from these years were used to determine and calculate a whole range of outputs, which gradually led, among other things, to the evaluation of the average socio-economic impacts of occurrences, which are used, for example, in Table 2 and Table 4. For this reason, the calculations and results presented in this contribution were carried out within the periods defined by the used part of the database of occurrences, i.e., for the period 2011–2018, which was very well mapped and described as part of the research activity. Considering the scope of the evaluated period and the possibility of generalization of the presented conclusions resulting from the analysis, the use of these data does not have a negative impact on the interpretation of the results.

3.1. Presentation of a Sample of Projects for Impact Assessment

Given that the initial statistical data are from 2011 to 2018, projects implemented approximately in the middle of this period were selected for this analysis. The website of the Transport Operational Program served as a source of information about these projects, where 33 projects were selected that reconstructed more than 600 km of tracks.
An overview of the projects that were evaluated is shown below in Table 1 and contains the date of implementation of the individual projects, the total investment costs of the construction including VAT, and the type and number of the track. A more detailed description of the individual projects is not part of this article, but is available on request from the authors. All projects included the reconstruction of security devices.
Table 1. Overview of analyzed projects.
Table 1. Overview of analyzed projects.
NumberProjectStartFinishInvestment Costs Incl. VATKind of the TrackNumber of the Track
1Project 11 October 201531 August 2016173,136,542Regional175
2Project 228 May 201530 June 2016762,536,398National280
3Project 315 June 201531 January 2016596,407,370National030
4Project 41 June 201530 June 20161,202,408,201Regional323
5Project 57 February 201531 August 2015920,773,676Regional173
6Project 63 July 201429 July 2016894,985,703Regional183
7Project 71 September 20152 January 2016715,977,853National230
8Project 810 September 201511 December 2015464,213,974National340
9Project 915 October 201512 December 2015663,232,990Regional022
10Project 1020 April 201513 August 2015798,625,215National280
11Project 111 July 201510 December 2015560,440,328National030
12Project 1219 October 201130 November 2015281,996,745Regional148
13Project 1319 October 201531 December 201520,455,604National120
14Project 141 November 2015 1 June 2016614,288,644National024
15Project 1520 August 201529 July 2016520,197,091National073
16Project 161 July 201530 November 2015690,537,162National030
17Project 174 February 20154 December 2015293,624,996National251
18Project 181 July 201531 August 201549,361,529Regional281
19Project 1916 May 201430 November 20151,197,333,682National030
20Project 201 April 201530 November 20151,204,890,775National238
21Project 211 August 20141 July 2015639,700,109National179
22Project 2215 March 201431 May 2015898,093,690Regional036
23Project 231 March 201431 December 20151,831,222,723Regional194
24Project 241 April 201431 December 20151,206,483,115National220
25Project 2517 October 201331 December 20152,087,008,938National011
26Project 2630 November 201228 February 20151,208,429,612National090
27Project 2726 February 201430 October 20151,253,063,156National220
28Project 281 April 201331 December 20152,333,583,115National220
29Project 2912 October 201230 October 2013515,032,795Regional325
30Project 301 July 201215 August 20153,150,052,805National170
31Project 3115 April 201331 December 20151,946,428,004National220
32Project 325 February 201619 June 20171,203,211,371National292
33Project 3325 June 201531 May 20171,202,365,089National310
Typical actions that increase the safety and reliability of railway traffic were within the framework of individual projects, for example, the modernization of track and station security equipment to the category of the third level, including equipment with remote traffic control, the installation of axle computers to determine the clearance of tracks and switches, or the construction of information, communication, or camera systems.

3.2. The Impact of Evaluated Measures on Occurrences

The initial data included in the analysis contain data limited by the period 1 January 2011 to 31 December 2018, excluding the construction period of the buildings in question. The data are spatially limited to the beginning and end of reconstructed track sections.

3.2.1. Average Annual Incidence of Occurrences

As part of the analysis, the above-mentioned 33 projects with total construction costs of CZK 32.1 billion were monitored, the length of the track sections was a total of 552 km. Construction was carried out mainly in 2014–2015.
The average length of the monitored period was 3.72 years prior to the implementation of the construction, with the maximum length slightly over five years (Project 32) and the shortest interval less than a year (Project 12). For detailed information about lengths of periods before the projects’ realization, see Figure 1.
The average length of the monitored period was 3.00 years after construction, with a maximum length of just over five years (Project 29) and the shortest interval of one and a half years (Project 32). For detailed information about lengths of periods after the projects’ realization, see Figure 2.

3.2.2. Determination of an Average Occurrence

In the article Economic impact of occurrences on railways [30], the average societal impacts of individual types of extraordinary events caused by the human factor were determined. The calculation and total amount for individual categories of extraordinary events are shown in Table 2.
In order to assess the total societal costs associated with the occurrence of an extraordinary event, it is necessary to assess the economic impacts associated with the death and injury of residents and at the same time express the costs of train delays, for both passengers and cargo.
Society-wide costs (according to the Department’s methodology [2]) expressed at the 2021 price level associated with the following impacts are listed below:
  • death amounts to 24,280,219 CZK/person,
  • severe injuries amount to 5,878,639 CZK/person,
  • minor injuries amount to 758,888 CZK/person.
In order to calculate the cost of delay, it is necessary to know the price of one ton-hour and one person-hour, as well as the average load weight of one freight train and the average occupancy of passenger trains. Data on occupancy and cargo weight are calculated from the Statistical Yearbook of the Czech Railways Group from 2018 [34] and are shown in Table 3.
The data show that the average occupancy of a passenger train between 2016 and 2019 was 65.35 persons/train, and the average weight of transported cargo was 442.13 tons/train.
The value of 1 person-hour with equal distribution of trips and 10% representation of working time amounts to 321.00 CZK/hour at the price level of 2021 [3].
The value of 1 ton-hour is 40.38 CZK /ton-hour at the price level of 202 [3].
The sum of society-wide costs associated with emergencies of selected categories, which were caused by the human factor on the railway network of the Czech Republic in the years 2011–2018, amounts to CZK 899,953,468 at the price level of 2021. The average society-wide cost of one emergency event is CZK 510,467, while it is true that the average costs associated with extraordinary events differ significantly within categories A, B, and C.
The average societal cost of one emergency within categories is as follows:
  • A—CZK 27,505,865
  • B—CZK 2,433,778
  • C—CZK 105,670
An overview of the partial impacts of extraordinary events by category is presented in Table 4.

3.2.3. Evaluation of the Impact of Building Construction on the Incidence of Occurrences

Within the monitored 33 projects, there were an average of 17.84 occurrences per year before the implementation of the project and 17.01 occurrences per year after the implementation of the project. In both cases, these are only occurrences of selected categories and caused by the human factor. It is therefore possible to state that due to the implementation of measures to increase the safety and reliability of the railway transport route (see Section 3.1), the number of occurrences decreased in the period after the implementation of the project by 4.63% on average.
The annual societal costs associated with these occurrences amounted to an average of 9.11 million CZK/year before the implementation of the constructions. After construction, this value dropped to 8.68 million CZK/year.
After the implementation of most constructions, there is an increase in track speed and, in some cases, an increase in the traffic load. Transport performance within the entire network increased between 2011 and 2018 by 9.08% for passenger transport and by 3.33% for freight transport (Figure 3). The relationship between traffic performance and the frequency of occurrence of emergencies is analyzed in the following part of the article.

3.3. Evaluation of an Occurrence within the Railway Transport Route

The evaluation of occurrences within the railway transport route is carried out from two points of view. First, the occurrence is related to the length of the reconstructed line, and in the second case, the occurrence is related to traffic performance.

3.3.1. Assessment of the Occurrence in Relation to the Length of the Reconstructed Line

The length of the tracked tracks was 552 km, and thus 0.0323 occurrences were accounted for per 1 km of track before the implementation of the project (1 occurrence for every 30,966 km). After the implementation of the project, it was 0.0308 (1 occurrence for every 32,470 km). The costs associated with the occurrence amounted to an average of 15,179 CZK/km of track before the implementation of the construction; after the implementation of the project, a decrease to 14,476 CZK/km of track can be expected.
The length of the reconstructed or modernized line was between 0.6 and 79.72 km within the assessed projects. With an average length of the reconstructed section of 16.74 km per monitored project, the average saving per project is 11,765 CZK/year, with average costs before implementation of 254,066 CZK/year and 242,301 CZK/year after construction.

3.3.2. Assessment of the Occurrence in Relation to Traffic Performance

Traffic performance is a factor significantly affecting the probability of the occurrence. With its increase, the probability of the occurrence should logically increase.
In this part of the contribution, the relationship between the occurrences before and after the completion of the projects is assessed, considering the average increase in traffic performance on the entire railway network of the Czech Republic.
Between 2011 and 2018, transport performance on Czech railways increased from 161 to 173 million train kilometers (see Figure 3), with just under 23% of freight transport performance and the rest passenger transport. In the years 2011–2014, which is the period before the implementation of the project, the average annual traffic performance was 160.8 million train kilometers. In the years 2016–2018, i.e., after the implementation of most of the projects, the average annual transport performance was 168 million train kilometers. The increase between the two monitored periods is therefore 4.52%.
In Section 3.2.3, an average decrease in monitored occurrences by 4.63% was calculated depending on the completion of the track or station reconstruction including the modernization of security equipment. Respecting the idea that there is a direct correlation between traffic performance and the probability of the occurrence on the track while maintaining its traffic technical condition, the decrease caused by the implementation of the monitored projects would be the sum of the increase in traffic performance and the average decrease in the number of occurrences.
When considering the increase in traffic performance within the monitored periods before and after the implementation of the projects, the decrease in the probability of occurrence is as follows: 4.63% + 4.52% = 9.15%.

4. Discussion

From the analyzed data, it can be seen that the implementation of constructions resulted in a decrease in the number of occurrences by 4.63% on average, and when considering the average increase in traffic performance in the monitored period, it is a total of 9.15%. The average societal cost of one occurrence amounts to CZK 511,564 (expressed at the 2021 price level), with the fact that this value will increase over time as a result of GDP growth and thus also the standard of living of the population of the Czech Republic.
The incidence of the occurrence was evaluated based on statistics in relation to the length of the line or its traffic load. The results show that one occurrence occurred every 30,966 km of track, and after track reconstruction there was one occurrence for every 32,470 km of track.
Within the monitored projects, the average length of the reconstructed section was 16.74 km per monitored project. The average savings resulting from the reduction in the probability of the occurrence amounted to an average of 12,804 CZK/year per project, with average socio-economic costs before implementation of CZK 276,509 and CZK 263,705 after construction.
In relation to traffic performance, the average of one occurrence for every 693,725.56 km per year was calculated. After the modernization or reconstruction of the line, one occurrence should occur on average at 726,548.4 km per year.
A suitable topic for the discussion would be a comparison of the achieved results of the presented research with the situation abroad. Scientific publications deal with the issue of occurrences on railways quite widely; however, in most cases, the research is focused on specific aspects causing occurrences, such as unauthorized access to a railway crossing or the influence of the load on selected railway equipment on the occurrence of failures. However, as part of the search, data in the same or similar structure were not found in scientific publications. The presented results can serve as a starting point for further research and a possible international comparison.
As part of the research, an answer was sought to a research question related to investments into rail transport and its safety. To answer the question, current valid methodologies for evaluating of the effectiveness of transport investments [2], the database of extraordinary events [33], and many other sources were used as sources. The research question was formulated as follows:
RQ1: To what extent can the frequency and impact of occurrences be reduced through the modernization of the railway infrastructure?
The evaluation of the research question was carried out on the basis of a comparison of the development of the number of extraordinary events on 33 monitored projects involving the reconstruction of 552 km of railway tracks.
From the analyzed data, it can be seen that the implementation of constructions resulted in a decrease in the number of occurrences by 4.63% on average, and even by 9.15% when considering the average increase in traffic performance in the monitored period.

5. Conclusions

The research and scientific contribution of this paper is the analysis of the methodology for performing the economic evaluation of railway constructions and the definition of essential benefits in terms of societal benefits of railway projects.
Part of the presented results is also an analysis of statistical data related to occurrences on the railway provided by the Railway Administration for the needs of the presented research. The statistical data contain data on occurrences on the railway network from 2009 to 2018, including details describing the date and place of occurrence, the cause of the extraordinary event and, last but not least, the damage caused by each extraordinary event.
The presented research examines the influence of the implementation of selected railway projects on the change in the occurrence of extraordinary events in connection with the length of the reconstructed section and the traffic performance realized on the affected infrastructure. The key problem that the presented research solves and at the same time the key research gap that the authors try to fill with the help of the research results consists of the lack of current methodological procedures that do not allow considering, in the economic evaluation of railway investment projects, the effect of the implementation of specific measures to reduce the number of occurrences in the addressed section. Together with the previously defined average impacts of extraordinary events (510,467 CZK/occurrence) and the average annual reduction in the number of extraordinary events (by an average of 4.63%), it is possible to determine the expected benefit associated with the implementation of a project including measures leading to an increase in railway safety and reliability.
The principles of the defined methodological approach are also applicable in an environment outside the Czech Republic, but there are two conditions for the possibility of application. The first condition is that for the alternative country, the documents for determining the average impact of the occurrence will be available (similar to the Departmental Methodology and database of occurrences that are available in the Czech Republic). The second condition is the existence of an adequate number of projects involving measures leading to an increase in railway safety and reliability.

Author Contributions

Conceptualization, V.H. and T.F.; methodology, V.H. and T.F.; software, T.F.; validation, V.H. and T.F.; formal analysis, V.H. and T.F.; resources, V.H. and T.F.; data curation, T.F.; writing—original draft preparation, V.H.; writing—review and editing, V.H. and T.F.; visualization, V.H.; supervision, V.H.; project administration, V.H.; funding acquisition, V.H. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by Brno University of Technology, grant number FAST-S-24-8524. The APC was funded by Brno University of Technology.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data for the processing of the article and its outputs are not publicly available, but will be provided by the authors of the article upon request.

Acknowledgments

The contribution was prepared with the support of a specific research project at Brno University of Technology FAST-S-24-8524 “Management of selected economic processes in the construction industry”.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Sartori, D. Guide to Cost-Benefit Analysis of Investment Projects, Economic Appraisal Tool for Cohesion Policy 2014–2020; European Commission, Directorate-General for Regional and Urban Policy: Etterbeek, Belgium, 2014; ISBN 978-92-79-34796-2. [Google Scholar]
  2. Ministry of Transport of the Czech Republic (MoT CZ). Departmental Guideline for the Evaluation of Economic Effectiveness of Transport Construction Projects. 2017. Available online: http://www.sfdi.cz/pravidla-metodiky-a-ceniky/metodiky/ (accessed on 1 July 2022).
  3. Actualization of Ministry of Transport of the Czech Republic (MoT CZ). Departmental Guideline for the Evaluation of Economic Effectiveness of Transport Construction Projects. 2022. Available online: http://www.sfdi.cz/pravidla-metodiky-a-ceniky/metodiky/ (accessed on 1 July 2022).
  4. Actualization of Appendixes of Ministry of Transport of the Czech Republic (MoT CZ). Departmental Guideline for the Evaluation of Economic Effectiveness of Transport Construction Projects. 2023. Available online: http://www.sfdi.cz/pravidla-metodiky-a-ceniky/metodiky/ (accessed on 1 July 2022).
  5. Actualization of Ministry of Transport of the Czech Republic (MoT CZ). Departmental Guideline for the Evaluation of Economic Effectiveness of Transport Construction Projects. 2023. Available online: http://www.sfdi.cz/pravidla-metodiky-a-ceniky/metodiky/ (accessed on 1 July 2022).
  6. Ministry of Transport of the Czech Republic. Transport Yearbook of the Czech Republic; Ministry of Transport of the Czech Republic: Prague, Czech Republic, 2019.
  7. Holvad, T. Efficiency analyses for the railway sector: An overview of key issues. Online. Res. Transp. Econ. 2020, 82, 100877. [Google Scholar] [CrossRef]
  8. Niu, Y.; Li, X.; Zhang, J.; Deng, X.; Chang, Y. Efficiency of railway transport: A comparative analysis for 16 countries. Online. Transp. Policy 2023, 141, 42–53. [Google Scholar] [CrossRef]
  9. Mężyk, A. Railway efficiency. Methodological aspects. Cent. Eur. Rev. Econ. Financ. 2021, 32, 21–41. [Google Scholar] [CrossRef]
  10. Strelkov, A.K.; Teplykh, S.Y. Ecological and economic efficiency of the life cycle of railway territorial-industrial complexes. Online. IOP Conf. Ser. Mater. Sci. Eng. 2020, 775, 12035. [Google Scholar] [CrossRef]
  11. Gulamov, A.; Egamberdieva, K. Analysis of the Interaction of Technical and Economic Indicators in Improving the Efficiency of Operational Activities of Railway Transport. E3S Web Conf. 2023, 449, 8002. [Google Scholar] [CrossRef]
  12. Ikonnikov, S.; Loktev, A.; Korolev, V.; Shishkina, I. Method for Assessing the Economic Efficiency of a Dispatch Control System with Diagnostic Functions in Railway Transport. Transp. Res. Procedia 2022, 63, 2636–2644. [Google Scholar] [CrossRef]
  13. Yang, X.; Zhang, H.; Li, Y. High-speed railway, factor flow and enterprise innovation efficiency: An empirical analysis on micro data. Socio-Econ. Plan. Sci. 2022, 82, 101305. [Google Scholar] [CrossRef]
  14. Zhang, B.; Dong, W.; Yao, J. The Opening of High-Speed Railways, the Improvement of Factor Allocation Efficiency between Regions, and the City’s Environmental Quality Improvement. Int. J. Environ. Res. Public Health 2023, 20, 4648. [Google Scholar] [CrossRef]
  15. Sun, X.; Yan, S.; Liu, T.; Wu, J. High-speed rail development and urban environmental efficiency in China: A city-level examination. Transp. Res. Part D Transp. Environ. 2020, 86, 102456. [Google Scholar] [CrossRef]
  16. Yang, Q.; Hu, X.; Wang, Y.; Liu, Y.; Liu, J.; Ma, J.; Wang, X.; Wan, Y.; Hu, J.; Zhang, Z.; et al. Comparison of the impact of China’s railway investment and road investment on the economy and air pollution emissions. J. Clean. Prod. 2021, 293, 126100. [Google Scholar] [CrossRef]
  17. Jeong, W.; Park, H. Economic and environmental assessment of the Korea urban railway and its greenhouse gas mitigation potential. Environ. Res. Commun. 2024, 6, 95009. [Google Scholar] [CrossRef]
  18. Edkins, G.D.; Pollock, C.M. The influence of sustained attention on Railway accidents. Accid. Anal. Prev. 1997, 29, 533–539. [Google Scholar] [CrossRef]
  19. Baysari, M.T.; McIntosh, A.S.; Wilson, J.R. Understanding the human factors contribution to railway accidents and incidents in Australia. Accid. Anal. Prev. 2008, 40, 1750–1757. [Google Scholar] [CrossRef]
  20. Read, G.J.M.; Lenné, M.G.; Moss, S.A. Associations between task, training and social environmental factors and error types involved in rail incidents and accidents. Accid. Anal. Prev. 2012, 48, 416–422. [Google Scholar] [CrossRef]
  21. Maierhofer, J.; Gänser, H.-P.; Daves, W.; Eck, S. Digitalization and Reliability of Railway Vehicles and Tracks—Condition Monitoring and Condition-based Maintenance. Online. BHM Berg Hüttenmänn. Monatsh. 2024, 169, 264–268. [Google Scholar] [CrossRef]
  22. Evans, A.W. Fatal train accidents on Europe’s railways: 1980–2009. Accid. Anal. Prev. 2011, 43, 391–401. [Google Scholar] [CrossRef]
  23. Evans, A.W. The economics of railway safety. Res. Transp. Econ. 2013, 43, 137–147. [Google Scholar] [CrossRef]
  24. Zhou, J.-L.; Lei, Y. Paths between latent and active errors: Analysis of 407 railway accidents/incidents’ causes in China. Saf. Sci. 2018, 110 Pt B, 47–58. [Google Scholar] [CrossRef]
  25. Hani Tabai, B.; Bagheri, M.; Sadeghi-Firoozabadi, V.; Sze, N.N. Evaluating the impact of train drivers’ cognitive and demographic characteristics on railway accidents. Saf. Sci. 2018, 110, 162–167. [Google Scholar] [CrossRef]
  26. Kim, H.J.; Jeong, J.Y.; Kim, J.W.; Oh, J.K. A Factor Analysis of Urban Railway Casualty Accidents and Establishment of Preventive Response Systems. Procedia—Soc. Behav. Sci. 2016, 218, 131–140. [Google Scholar] [CrossRef]
  27. Mátrai, T. Cost benefit analysis and ex-post evaluation for railway upgrade projects. Period. Polytech. Transp. Eng. 2013, 41, 33–38. [Google Scholar] [CrossRef]
  28. Wemakor, W.D.; Anson, J.; Schmid, F. Establishing the Relationship between Railway Safety and Operational Performance, Birmingham Centre for Railway Research and Education, University of Birmingham, UK. Int. J. Transp. Dev. Integr. 2018, 2, 98–114. [Google Scholar] [CrossRef]
  29. Tseng, Y.; Rietveld, P.; Verhoef, E. Unreliable trains and induced rescheduling: Implications for cost-benefit analysis. Transportation 2012, 39, 387–407. [Google Scholar] [CrossRef]
  30. Olsson, N.; Oekland, A.; Halvorsen, S.; Olsson, N. Consequences of differences in cost-benefit methodology in railway infrastructure appraisal: A comparison between selected countries. Transp. Policy 2012, 22, 29–35. Available online: http://search.proquest.com/docview/1692388163/ (accessed on 1 March 2024). [CrossRef]
  31. Klockner, K.; Toft, Y. Railway accidents and incidents: Complex socio-technical system accident modelling comes of age. Saf. Sci. 2018, 110, 59–66. [Google Scholar] [CrossRef]
  32. Hromádka, V.; Korytárová, J.; Vítková, E.; Seelmann, H.; Funk, T. Economic Impact of Occurrences on Railways. Procedia Comput. Sci. 2021, 181, 76–83. [Google Scholar] [CrossRef]
  33. Czech Railway Infrastructure Administration (CRIA). Statistika Mimořádných Událostí, Databáze 2009–2018 (Database of Occurrences 2009–2018); Czech Railway Infrastructure Administration: Prague, Czech Republic, 2018. [Google Scholar]
  34. Czech Railway Group. Statistical Yearbook of the Czech; Czech Railway Group: Prague, Czech Republic, 2018. [Google Scholar]
Figure 1. Graph of the length of the evaluated period before the implementation of the project in years (source: https://opd3.opd.cz/projekty (accessed on 1 July 2023)).
Figure 1. Graph of the length of the evaluated period before the implementation of the project in years (source: https://opd3.opd.cz/projekty (accessed on 1 July 2023)).
Applsci 14 09143 g001
Figure 2. Graph of the length of the evaluated period after the implementation of the project in years (source: https://opd3.opd.cz/projekty (accessed on 1 July 2023)).
Figure 2. Graph of the length of the evaluated period after the implementation of the project in years (source: https://opd3.opd.cz/projekty (accessed on 1 July 2023)).
Applsci 14 09143 g002
Figure 3. Development of transport performance on the Czech railway transport route (own elaboration based on [34]).
Figure 3. Development of transport performance on the Czech railway transport route (own elaboration based on [34]).
Applsci 14 09143 g003
Table 2. Total impacts of extraordinary events by category for the period 2011–2018 (cause—human factor).
Table 2. Total impacts of extraordinary events by category for the period 2011–2018 (cause—human factor).
CategoryNumber
of Occurrences
Consequences on the Health of People in TotalTrain Delays (min)Financial Impact in Total
Total DeathsTotal Serious InjuriesTotal Minor InjuriesPassenger Train DelaysFreight Train Delays(CZK, CÚ 2021)
A111214310,360,00913116,541,074
A220020045,666,786
A320319250125,833,889
B14205203,549,002,251,0080,788,498
B27000516,559,003,971,00138,979,460
B31803103,248,002,106,0012,389,192
C19200000692,969
C245000017,915,006,390,0046,648,040
C328200035,351,0011,209,0022,545,910
C657200076,713,0028,441,0012,585,865
C1210500019,912,007,159,002,554,216
C1911700014,571,008,166,0010,188,512
Source: Economic impact of occurrences on railways [32].
Table 3. Transport performance of ČD, a.s.
Table 3. Transport performance of ČD, a.s.
Item2016201720182019Average
PT *FT **PTFTPTFTPTFTPTFT
Train km (mil. train km)120.321.8122.822.6123.624.3124.022.6122.722.8
Gross train km (1000 mil. ton km)19.422.719.523.319.825.720.323.019.823.7
Goods transport (mil. tons)X54.6X55.2X57.2X53.9X55.7
Transport performance (mil. ton km)X9521X10,057X11,086X9740X10,221
Number of passengers (mil. persons)171.5X174.7X179.2X182.1X176.9X
Transport performance (mil. pass. km)7380X7778X8225X8685X8017X
Source: Statistical Yearbook of the Czech Railways Group from 2018 [34]. * Passenger Trains. ** Freight Trains.
Table 4. Society-wide costs of extraordinary events in CZK, price level 2021.
Table 4. Society-wide costs of extraordinary events in CZK, price level 2021.
CategoryNumber
of Occurrences
Consequences on the Health of People (CZK)Train Delays (CZK)Financial Impact (CZK)Total Costs (CZK)
A11187,071,2733,893,642116,541,074207,505,989
A221,517,776045,666,78647,184,563
A3232,054,7958740125,833,889157,897,424
B14244,570,9621,910,63380,788,498127,270,093
B2703,794,4416,970,892138,979,460149,744,794
B31825,224,8011,762,25112,389,19239,376,244
C19200692,969692,969
C245008,164,82946,648,04054,812,868
C3282015,694,68322,545,91038,240,593
C6572035,283,24012,585,86547,869,105
C1210509,091,8432,554,21611,646,058
C1911707,524,25610,188,51217,712,768
Total1763194,234,04890,305,009615,414,411899,953,468
Average occurrence110,17251,222349,072510,467
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Hromádka, V.; Funk, T. The Effect of Railway Projects Increasing Safety on the Frequency of Occurrences. Appl. Sci. 2024, 14, 9143. https://doi.org/10.3390/app14199143

AMA Style

Hromádka V, Funk T. The Effect of Railway Projects Increasing Safety on the Frequency of Occurrences. Applied Sciences. 2024; 14(19):9143. https://doi.org/10.3390/app14199143

Chicago/Turabian Style

Hromádka, Vít, and Tomáš Funk. 2024. "The Effect of Railway Projects Increasing Safety on the Frequency of Occurrences" Applied Sciences 14, no. 19: 9143. https://doi.org/10.3390/app14199143

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop