3.1. Production Process Modeling of the Studied Manufacturing Architecture Using WITNESS Horizon
Figure 22 shows the preliminary manufacturing architecture modeled and simulated in WITNESS. The explanation of equipment in
Figure 22 is presented in
Table 1.
Within the manufacturing architecture, work points were created for each operation required to manufacture the rear axle.
To evaluate the production capacity in a work week with three shifts per day of eight hours each, and a production gap of eight hours, a simulation was performed for a total duration of 6960 min for the manufacturing architecture. This architecture can produce 2618 rear axles per week and approximately 68 scraps, which can be recoverable or non-recoverable, depending on the degree of defect.
Robotic cell 1:
Figure 23.
Robotic cell 1.
Figure 23.
Robotic cell 1.
“Robot welding cell operation 1” performs the welding operation between the Link Element (EDL), the anti-roll bar, the supports for the anti-roll bar, and the gussets.
The elements that are welded within this work point are placed and picked up manually by a human operator, named in the manufacturing architecture “Operator 3”.
This first subassembly obtained after the welding operation in robotic cell 1 is transported with the help of conveyor C1 to work point two, i.e., “Robot cell welding operation 2”.
Robotic cell 3:
Figure 24.
Robotic cell 3.
Figure 24.
Robotic cell 3.
In this work point, “Robot welding cell operation 3”, the second subassembly is obtained, comprising an arm, bushing, and damper shaft. With the help of this cell, this subassembly is obtained for both the left and right sides of the bridge at the same time.
After obtaining each subassembly, “Operator 1” places it in the specific container for the left or right, and after filling them, they are picked up by a forklift and transported to robotic cell 2.
Robotic cell 2:
Figure 25.
Robotic cell 2.
Figure 25.
Robotic cell 2.
In the second robotic cell, the first subassembly is obtained at the first working point, and the second subassembly consisting of an arm, bushing, and damper is obtained with the help of robotic cell 3, and the spring plate is welded.
After welding them, “Operator 3” takes this obtained assembly and places it on the C2 conveyor that transports it to the “preparation station”, where it is taken over by “Operator 4”.
Rear-axle preparation post:
Figure 26.
Rear-axle preparation post.
Figure 26.
Rear-axle preparation post.
In the “preparation station”, “Operator 4” mounts the following parts on the subassembly obtained in the previous stages: one support for the brake pipe; two supports for the handbrake cable; and on the left and right sides of it, two ABS brackets, two fairing brackets protecting the spring plate, and two fairing brackets protecting the EDL.
After fitting the parts listed above, the operator places the assembly on conveyor C3, which transports the assembly to the “Robot welding cell operation 4”.
Robotic cell 5:
Figure 27.
Robotic cell 5.
Figure 27.
Robotic cell 5.
Within this cell, Subassembly 3 is obtained, which consists of the following parts: left and right axle head, left and right axle head reinforcement, left and right axle head reinforcement, left axle head reinforcement, and right and lower axle head brace for left and right.
This obtained subassembly fits in both ends of the rear axle.
Within the robotic cell, two subassemblies can be welded at the same time. The parts are placed manually by “Operator 7” and are also picked up after welding by the operator and placed in the container for storage. After the container is filled, it is transported to robotic cell 4 with the help of a forklift.
Robotic cell 4:
Figure 28.
Robotic cell 4.
Figure 28.
Robotic cell 4.
With the help of robotic cell 4, the final assembly consisting of the axle-head subassembly 3 and the assembly prepared in the previous stages is made.
The assembly previously prepared in the preparation station and transported by the conveyor C3 is taken by Operator 5 and placed inside robotic cell 4, after which two subassemblies made within robotic cell 5 are placed: one on the left side and one on the right side.
Within cell 4, the last welding operation on the deck is carried out. After its completion, Operator 5 takes the bridge and places it on conveyor C4, which transports it to the quality control point.
Post quality control:
Figure 29.
Post quality control.
Figure 29.
Post quality control.
In this position, a visual control is carried out by Operator 6 on the welds, and the engraving of the bridge series is carried out with the help of a milling cutter in order to have traceability on the production.
After carrying out the quality control and engraving, the operator takes the deck and stores it on a scale suitable for the decks considered OK or NOK, where they are stored and picked up for the next stages of processing.
The mean time between failures as well as the mean time to repair all equipment were defined in the preliminary system according to their technical data sheets but also based on statistics of the real system.
Following the simulation of the manufacturing architecture, the results were obtained, which can be found in the reports below.
In
Figure 30, one can see the operating percentage of each work point, but also the waiting percentage of the parts.
Report for working points:
Figure 30.
The degree of operation of the work points.
Figure 30.
The degree of operation of the work points.
In
Figure 31, one can graphically observe the values from
Figure 31. Green means the degree of operation of each work point, and yellow means their waiting time.
Figure 32 shows the operating percentage of the conveyors used to transport parts between work points.
Conveyor report:
Figure 32.
The degree of operation of the conveyors.
Figure 32.
The degree of operation of the conveyors.
In the graphic report in
Figure 33, the degree of the operation, waiting, queue or blockage of the conveyors in the manufacturing architecture can be observed in percentage, where green represents the operation, yellow indicates waiting for parts, blue indicates the queue of parts on the conveyor, and pink indicates the degree of blockage.
Figure 34 shows the graphic report of the percentage of work of the operators.
In the report in
Figure 35, one can see the operating percentage of the two machines used to transport parts between work points.
Report for forklifts:
Figure 35.
Operating percentage of forklifts.
Figure 35.
Operating percentage of forklifts.
Figure 36 shows the graphic ratio of the utilization of the two forklifts, where green means the percentage in which the forklift is loaded, blue means the transfer, and yellow means the waiting degree.
After simulating the non-optimized manufacturing architecture, it was found that this architecture could produce 2618 rear axles per week. This reflects a robust production capability, but there is room for improvement to reduce scrap and optimize cycle times.
The analysis of the degree of operation of the work points (
Figure 31 and
Figure 32) shows that there are significant variations in the use of different work points. Some workstations have high waiting times, indicating possible inefficiencies in the production flow.
Weekly production generates approximately 68 scraps, which may be salvageable or non-salvageable depending on the degree of defect. This suggests the need to implement more rigorous quality control measures and process optimization to reduce the scrap rate.
Each robotic cell has different specifications and cycle times. Variability in cell performance indicates the need to adjust and synchronize them to ensure a continuous and balanced flow of production.
The quality control station (
Figure 30) plays a crucial role in ensuring product conformity. Improving quality control techniques and implementing standardized procedures can reduce the number of non-conforming parts and improve production traceability.
The conveyor and forklift utilization report (
Figure 33,
Figure 34,
Figure 35 and
Figure 36) shows a variable degree of utilization with waiting periods and bottlenecks. Optimizing the use of this equipment can contribute to a better flow of production.
Possible solutions for optimization:
Reducing waiting times: implementation of production flow synchronization measures to minimize waiting times at work points and conveyors;
Improving quality control: adoption of advanced quality control techniques to reduce the scrap rate and ensure better product traceability;
Optimizing resource utilization: redistributing tasks and adjusting the work schedule of operators and equipment to maximize efficiency and productivity, and to prevent worker fatigue and errors, the operators work in 8 h shifts with 3 breaks (one half-hour lunch break and two 15 min breaks);
Robotic cell synchronization: adjusting cycle times and robot scheduling to ensure better harmonization between different stages of the manufacturing process;
Analysis and implementation of improvements: continuous use of simulations to test and evaluate the impact of various proposed improvements on the entire production system.
3.2. Optimization of the Production Process in WITNESS Horizon
Figure 37 shows the manufacturing architecture after optimization made in WITNESS. The explanation of equipment in
Figure 37 is presented in
Table 2.
Following the optimization of the manufacturing architecture, production capacity increased from 2618 decks to 3980 parts per week. Both functional and technological optimization procedures were performed on the manufacturing architecture.
Table 3.
Parameter values used in the manufacturing architecture before optimization and after optimization.
Table 3.
Parameter values used in the manufacturing architecture before optimization and after optimization.
Component Elements—Manufacturing Architecture | Parameter Values Used Before Optimization | Parameter Values Used After Optimization |
---|
Cell Robot Sud OP1 | 1.425 | 1.425 |
Cell Robot Sud OP2 | 1.425 | 1.1 |
Cell Robot Sud OP3 | 1.425 | 1.2 |
Cell Robot Sud OP4 | 1.425 | 1 |
Cell Robot Sud OP5 | 1.425 | 1.425 |
Post Preparation | 1.5 | 1.5 |
Post Quality Control | 1 | 1 |
C1 | 0.5 | 0.5 |
C2 | 0.5 | 0.5 |
C3 | 0.2 | 0.2 |
C4 | 0.2 | 0.2 |
C5 | - | 0.5 |
C6 | - | 0.5 |
Forklift1 (T1 + T2 + T3) | 1 | - |
Forklift2 (T4 + T5 + T6) | 10 | - |
Following the preliminary simulation, blockages related to the handling of materials generated by forklifts were identified. These blockages were reduced by replacing forklifts with conveyors, which facilitated the reduction in transport time between different workstations. Following the optimization, all the changes made to the flow, including the replacement of forklifts, led to an increase in productivity.
The mean time between failures as well as the mean time to repair were defined for the new proposed equipment from the proposed optimized system architecture. The proposed solutions for the replacement of the different equipment within the flow were made based on the performance described in their technical data sheet. The initial simulation results led to an additional analysis of the technical equipment used in order to be able to identify solutions for configuring the flow, taking into account the performance of some equipment that can perform similar tasks in the logistics processes. The performance of the technical systems used to handle the products plays an important role in the performance of the material flow, and therefore using a dedicated software application, one can obtain predictable data for the better functioning of the material flow in relation to the performance of the equipment.
In the reports below, the results obtained from the previously mentioned optimizations are presented.
Figure 38 shows the operating and waiting percentages of the work points in the manufacturing flow.
Report working points:
Figure 38.
The degree of operation of the work points after optimization.
Figure 38.
The degree of operation of the work points after optimization.
For example, the welding robotic cell OP2 had a waiting percentage of 35.77% after optimization, compared to 44.822% before optimization, and an uptime of 64.23% compared to 55.178%. To be able to compare the results obtained before optimization and after optimization, the presented reports can be compared (
Figure 31 and
Figure 39).
Figure 39 graphically shows the degree of operation and waiting of the work points shown in
Figure 38, where green signifies the degree of operation, and yellow indicates the degree of waiting.
Figure 40 shows the degree of functionality of the conveyors within the manufacturing flow. Five of the six conveyors had a movement percentage of over 90%. The only conveyor on which there were blockages was the C6 conveyor.
Conveyor report:
Figure 40.
Conveyor efficiency report after optimization.
Figure 40.
Conveyor efficiency report after optimization.
Figure 41 shows the graphical report of conveyor operation, showing the values in
Figure 40. To see the differences in operation before and after optimization,
Figure 33 and
Figure 41 can be compared.
After optimizing the manufacturing architecture, we can draw several important conclusions based on the data and reports obtained, which are as follows:
Increase in production capacity:
Production capacity increased significantly, from 2618 decks per week to 3980 decks. This represents an improvement of approximately 52%, demonstrating the effectiveness of the implemented optimizations.
Reduction in cycle times:
Elimination of logistical blockages:
Improving the degree of operation of robotic cells:
Streamlining the input flow of parts:
Decreasing the time of entry of parts into the flow allowed for an increase in the number of processed components. For example, for the bushing part, the input time was reduced from one minute to 0.7 min, increasing the number of parts processed from 6961 to 9943.
Reduction in waste:
Technological and functional optimizations also contributed to reducing the number of scraps. This aspect, although not detailed in the reports, is implicit in increasing production efficiency and quality.
Efficiency of workstations:
Reducing blockages in conveyors:
The optimizations performed in the manufacturing architecture resulted in a significant increase in production capacity and operational efficiency. These improvements demonstrate the effectiveness of the optimization approach, both functionally and technologically. Detailed reports provide a solid basis for continuous monitoring and improvement in manufacturing processes in the future.
3.3. Mathematical Calculation for Maximizing the Profit by Optimizing the Logistic Flow Using the Simplex Method Mathematical
3.3.1. Simplex Method Description
The Simplex method is an approach to solving linear programming models by hand using slack variables, tableaus, and pivot variables as a means to finding the optimal solution to an optimization problem. A linear program is a method of achieving the best outcome given a maximum or minimum equation with linear constraints [
18].
The optimization problem is a choice problem that involves a correction of entities called solutions/scenarios/variants. These solutions are compared and classified by a performance criterion.
There is the problem of finding the most appreciated solution called the optimal solution.
The general study method of operational research can be schematized as follows:
3.3.2. Example of an Optimization Problem Solved with the Simplex Method
Three models of non-motor rear axle are proposed for manufacture: rigid non-motor axle, semi-rigid non-motor axle, and articulated non-motor axle. Taking into account that the automobile market is a developing one, it is desired that the diversity of a vehicle’s features ensure the satisfaction of the majority of customers. The prices of the three types of bridges that will be manufactured are rigid non-motorized bridge—RON 850 (EUR 170), semi-rigid non-motorized bridge—RON 1000 lei (EUR 200), and articulated non-motorized bridge—RON 1720 (EUR 344).
The problem facing the manufacturing process is the supply sector, which is limited due to suppliers having capacity issues. Four of the component elements required for the production of the three types of axle have a limited monthly stock: link element (EDL), anti-roll bar, springs, and McPherson suspension.
To make a non-motorized rigid rear axle, we need the following:
An EDL;
An anti-roll bar;
Two springs.
To make a non-motorized semi-rigid rear axle, we need the following:
An EDL;
An anti-roll bar;
Two springs.
To make an articulated non-motorized rear axle, we need the following:
The monthly stock that suppliers can provide includes the following:
Thus, to maximize turnover, we need to determine how many decks should be made of each type, taking into account the constraints of available monthly inventory.
Answer:
We denote x1—the number of rigid non-motorized axles, x2—the number of semi-rigid non-motorized axles, x3—the number of articulated non-motorized axles, and z—the turnover.
With the restrictions
we convert the model to standard form as follows:
Now, all variables are positive:
In
Table 4, in the column highlighted in red, the basic variables are written. The coefficients of the objective function are written on the lines highlighted in green. In the column highlighted in blue, the free terms of the restrictions are written.
The initial solution is not optimal because there is at least one negative value. From the three negative solutions, we choose the one with the highest absolute value (i.e., 1720). The yellow column divides at the pivot (green column), i.e., 10,400:1 = 10,400, 10,800:1 = 10,800, 19,900:2 = 9950, and 8000:2 = 4000 (
Table 5).
The smallest of these terms was chosen (i.e., 8000:2 = 4000). The row (purple) containing the smallest element is the pivot row (
Table 6).
The initial pivot line (y4) leaves the table.
Notably, y4 has left the table and x3 has entered (
Table 7). With the input of x3, instead of 0 in the objective function, the coefficient of x3 will appear, i.e., 1720 (colored in pink).
The elements of the purple line are divided at the pivot, i.e., at 2.
In
Table 8, the results after dividing the elements of the purple line at pivot 2 are shown.
The calculations in Equations (16)—(19) are the results of the arrows in
Table 8 and are listed in
Table 9 with each color corresponding to the arrow.
Additionally, the same calculation method was used for the other cells (the number 2 below the fraction being the pivot).
In
Table 9, in the pivot column, i.e., the column of x3, apart from element 1, which is the pivot, the rest of the column is padded with zeros.
Only the cells in the columns that are not colored are calculated.
If there are only numbers ≥ 0 in the last line, the calculation stops. If not, the previous calculation steps are repeated until there are only positive results.
Since there are still negative values, the procedure is repeated. From the two negative values, the column with the highest absolute value, i.e., 1000, is chosen.
The yellow column is divided by the pivot column (green column) (6400:1 = 6400, 6800:1 = 6800, 11900:2 = 5950, and 4000:0 cannot be divided. The positive minimum is chosen). In this situation, y3 leaves the column (since it is the minimum positive), and x2 appears with a coefficient of 1000.
The purple row divides at the pivot, i.e., at 2, which is circled in
Table 10 and passes the values in
Table 11. After that, the calculations are performed for the other cells in the columns that are not colored, and they are also passed in
Table 11. The calculations are performed as in
Table 8, to which Equations (16) and (20) belong.
Because there are no more negative values on the last row of
Table 11, the calculation stops, and this solution is the optimal one.
From the calculation, it follows that in order to maximize the turnover, which is z = RON 12,830,000 (EUR 2,566,00), we must produce the following quantities:
x1 = 0 (pieces)—Number of non-motorized rigid rear axles manufactured;
x2 = 5950 (pieces)—Number of non-motorized semi-rigid rear axles manufactured;
x3 = 4000 (pieces)—Number of articulated non-motorized rear axles manufactured;
y1 = 450 (pieces)—The number of connecting elements (EDL) remaining after making the rear axles influenced by the stock constraints of the other components;
y2 = 850 (pieces)—The number of anti-roll bars remaining after making the decks influenced by the stock constraints of the other components;
y3 = 0—The remaining number of springs;
y4 = 0—The remaining number of suspensions.
It is important to recognize that market conditions and component inventory availability may fluctuate. Thus, inventory management strategies and production planning should be flexible to respond to changes in demand and available resources.
The continuous monitoring of performance and adjustment of plans according to updated data and market feedback will ensure maintaining competitiveness and adaptability to changes in the business environment.
Market variables and fluctuations in the supply chain are a real risk in production because the market includes suppliers who cannot deal entirely with order variations. To avoid manufacturing risks, a minimum quantity is negotiated with the supplier, and a plan is made to recover the outstanding quantity. Due to the inability to comply with the orders, additional transport costs will be involved, as special transport will have to be organized to pick up the goods that are covered by the budget of the logistics department.
Another strategy to avoid risks in production is to schedule daily or weekly meetings in which the parts produced by the supplier are distributed so that none of his customers would be confronted with supply risks, and the production plan can be kept under observation until a solution to improve production is identified.