Next Article in Journal
A Fast Sparse Coding Method for Image Classification
Next Article in Special Issue
A Web Service for Evaluating the Level of Speech in Korean
Previous Article in Journal
A New Approach for Economical Pretreatment of Corncobs
Previous Article in Special Issue
Effects of Connection Type between Surface Vessel and Submersible Propeller on Motion Performance of Wave Glider
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Investigation of an Explosion at a Styrene Plant with Alkylation Reactor Feed Furnace

1
Graduate School of Engineering Science and Technology, National Yunlin University of Science and Technology, Yunlin 64002, Taiwan
2
Center for Process Safety and Industrial Disaster Prevention, School of Engineering, National Yunlin University of Science and Technology, Yunlin 64002, Taiwan
*
Author to whom correspondence should be addressed.
Appl. Sci. 2019, 9(3), 503; https://doi.org/10.3390/app9030503
Submission received: 9 December 2018 / Revised: 23 January 2019 / Accepted: 28 January 2019 / Published: 1 February 2019
(This article belongs to the Special Issue Selected Papers from IMETI 2018)

Abstract

:
To prevent and mitigate chemical risks in the petrochemical industry, such as fires and spillage, process safety management (PSM), is essential, especially where flammable, corrosive, explosive, toxic, or otherwise dangerous chemicals are used. We investigated process safety (PS) between man–machine (material equipment) and environmental interfaces by using process hazard analysis (PHA) and fault tree analysis (FTA). By analyzing the data obtained through machinery and mechanical integrity (MI), pre-startup safety review (PSSR), current operating modes, and areal locations of hazardous atmospheres (ALOHA) simulations of the disaster’s aftermath, the cause of the styrene plant accident was found to be the fuel furnace (F101) switching process. Although the furnace had been extinguished, fuel continued to enter the furnace, and it was exposed to a high-temperature surface, resulting in the flashing ignition of the C4 fuel. The plan-do-check-act (PDCA) management model can be used to forestall the system from accident, and it is used to improve the proposal and develop countermeasures that would increase PSM performance and substantially lessen the impact of the thermal hazard. Disasters are often attributable to the unsafe state of machinery, equipment, or the environment, dangerous behaviors of the operator, and the lack of a thorough management system. It is anticipated that the investigation and analysis of the accident would not only find the real cause of the disaster but also lead to the establishment of better effective solutions for common safety problems.

1. Introduction

Although the petrochemical industry has brought convenience to modern life, some accidents sporadically occur during the production process. In general, the process of raw materials poses enormous threats to human life. If improperly handled in preparation operation, management, transportation, or storage, these chemicals can cause fires, explosions, or leakages of toxic gas. In addition to causing loss of life and property damage, these kinds of industrial accidents could also trigger public protest over these large-scale plants. Therefore, after complex disasters happen, the social cost is often difficult to estimate. Nevertheless, the impact of a recent disaster was clear. On the morning of 6 March 2017, an explosion thundered through a styrene monomer (SM) company in Taiwan. In the aftermath of this incident, the public safety and environmental quality in the vicinity of industrial park were seriously affected. In light of the growing frequency of industrial accidents, this paper and its subject served as a relevant case study in the critical importance of process safety management (PSM). We hope to assist manufacturers in dealing with their accident investigation reports and to help experts and scholars diagnose the causes of disasters to ensure that similar accidents will not occur in the future. In this way, the lives of employees and the property of manufacturers could be protected. Taiwan’s SM plant alkylation reactor feed heating furnace explosion (equipment number: F101) accident on 6 March 2017 has been used as an example of PSM to provide analysis information to substantially lessen the risks as well as severities to the petrochemical industry [1,2].
In chemical manufacturing, the heating furnace is a process equipment that exchanges heat energy in furnace to heat the feed fluid to specific temperature range. The heating furnace is the main unit of the chemical processing system, fluid flows through the tubes into the furnace. Outside the tube is the heat generated by the combustion of fuel and air, so that the fluid is heated to a specific temperature. After the fuel is ignited by a burner, a flame is generated, and the combustion air flowing in the furnace is heated to exceptionally high temperature. Then, the combustion gas is transferred to heat the pipe by means of radiation and convection; the fluid is heated to the setpoint of the temperature for the process. Generally speaking, the gas in the heating furnace is not only extremely flammable, explosive, but also corrosive and toxic. Since the furnace is operated under high temperature conditions, the operating conditions may be poor; the gas generation period is short. If there is negligence or violation of the operating procedures, it may cause a fire or an explosion.
The heating of raw materials in chemical plants mainly depends on the heating furnace. The furnace temperature is sometimes as high as 700–800 °C (or even higher). Once the material of the furnace tube leaks, whether the temperature exceeds the self-ignition point or not, it is directly in contact with the open flame, so the hazard is extremely serious. In addition, improper ignition could also cause explosion. Once the furnace is damaged, it will directly lead to downtime and increase the loss. Therefore, it is necessary to take measures to prevent and mitigate fire and explosion accident.
Before commencing with the study and investigation, a brief literature [3] search was implemented to collect publicly available information about year’s explosion accidents in furnaces. Table 1 and Table 2 report this information. It was observed that even with detailed design, these accidents still occur; because they occurred at a high pressure within the system, they result in the loss of property and life. The accidents reported in Table 1 and Table 2 indicate that most of them are caused by human error, improper maintenance, or faulty design. Accordingly, it is recognized that the accidents of heating furnaces occur sporadically. Common accidents mainly include furnace explosion, coking in the furnace, and explosion in the flue. The furnace tube is damaged, the material in the tube leaks into the furnace, fire occurs, and the fire or explosion caused by overheating. In addition, the burner of heating furnace is damaged, the refractory insulating material in the furnace is impaired. The environment is seriously polluted, and the heating furnace has exploded. In numerous literature descriptions, furnace explosion was the most common, destructive, and extremely serious accident. In the past, there have been few literature studies on accident cases. Therefore, we used the furnace explosion accident as an example to analyze and improve the understanding of the explosion accident of the heating furnace.
We integrated the furnace explosion case and analyzed the relevant factors comprehensively that may cause fire and explosion during the operation of the furnace. The explosion factors of the heating furnace system were established by fault tree analysis method, and qualitative analysis was carried out to provide a basis for diagnosis and prevention of furnace explosion. The results of this study could provide the operators and managers with further understanding of the elements of furnace explosion and substantially diminish the chance of accidents in the future.

2. Accident Review

2.1. Accident Description

At 03:00 a.m. of 6 March 2017, one operator exchanged fuel gas for fuel oil in the alkylation reactor feed heating furnace (F101) and found poor combustion occurring at 04:28 a.m. The operator began to adjust accordingly, but at 04:31 a.m., a flash explosion occurred in the heating furnace, injuring four operators. It also damaged the surrounding property, such as the ethylbenzene process area (EB1) heating furnace (F101) being destroyed, both of which had to be shut down and repaired [4,5]. The accident scene conditions are shown in Figure 1; the location of the accident in Figure 2. The heating furnace (F101) accident’s time sequence is shown in Figure 3 [6].

2.2. Process Description

In general, the styrene monomer (SM) manufacturing method is based on the alkylation of benzene and ethylene. Ethylbenzene is formed and then dehydrogenated to produce a product–styrene, with byproducts: Toluene and hydrogen [7] (Figure 4). According to the process flow chart, before the raw materials enter the reactor, the materials (benzene) must be heated to reach the operating temperature by the heating furnace (F101). The inner structure of heating furnace (F101) is shown in Figure 5.
SM is an important intermediate material for the petrochemical industry that can be used to produce polystyrene (PS) plastic, acrylonitrile-butadiene-styrene (ABS) copolymers, styrene butadiene rubber (SBR), and unsaturated polyester (UPS). Its products are commonly used in electrical, mechanical, electronic, automotive, packaging, and other industries, all closely related to peoples’ livelihoods [8].
The accident was a section of the EB process. The raw material benzene was heated by a heating furnace (F101), and then mixed to reaction with another raw material ethylene in the alkylation reactor. The design of the heating furnace (F101) fuel operating system included fuel oil and fuel gas functions. However, the furnace flash explosion occurred when fuel oil and fuel gas were switched [9].

3. Accident Investigation Analysis

3.1. Analysis Procedures

This section identifies and describes the accident which caused with current risk management methods and principles. According to the risk assessment process, including risk analysis, control, and four decision making steps [10], the implementation steps are as follows (Figure 6).
The accident analysis follows a four-step sequence:
  • Hazard identification: First, identify all process activity and find the accident hazard causes and consequences, then confirm existing protective measures.
  • Assessment: Use qualitative or quantitative analysis method to implement risk assessment.
  • Risk control: According to the risk assessment results compare with the critical risk value, then take control measures for risk reduction.
  • Decision making: According to the risk reduction control measures and principles, consider the cost-effectiveness to formulate improvement strategies, and regularly implement supervision and assessment to determine the risk reduction performance [11,12,13,14].

3.2. Fault Tree Analysis (FTA)

3.2.1. What is FTA

FTA is one of the most widely used methods in system reliability, maintainability, and safety analysis. FTA was developed by Watson, at Bell Telephone Laboratories, in 1962 to apply the analytical method of studying the causes of undesired event failures. As a false logic diagram, the graphical structure of the model could be used as qualitative analysis and quantitative analysis [15].
The main purpose of the FTA is to identify potential causes of system failures before the failures actually occur. It also can be used to evaluate the probability of the top event using analytical or statistical methods. These calculations involve system quantitative reliability and maintainability information, such as failure probability, failure rate, and repair rate. After completing an FTA, the focus is on efforts for improving system safety and reliability. An FTA begins by defining the “undesirable” top event, such as fire disaster, explosion, leakage, and out of control. Then, FTA can analyze the top event to basic events through intermediate events. Once the FTA has been constructed, it can be qualified and quantified [16,17].

3.2.2. FTA Effects

Effects of FTA are illustrated as follows:
  • Applies deduction methods to figure out the possible cause of the system failure.
  • Provides a clear graphical method, various easy ways to understand, and to count system failure.
  • Points out the weaker links of the operating system.
  • Renders system tools to evaluate system improvement strategies.

3.2.3. Fault Tree Establishment

In this study, the disaster investigation team summarized the accident investigation report for the company and analyzed the causes of the accident by FTA to find numerous points of the accident. The establishment of FTA is shown in Figure 7. The top event was a heating furnace (F101) explosion. The heating furnace (F101) exploded and the fuel continued to enter and accumulate in the furnace. Then, the fuel and air formed a mixed flammable substance (here, concentration was already within the boundaries of the explosion) that was exposed to the furnace surface caused by high temperature flashover (with enough energy) [18,19].
Factors of the heating furnace explosion by FTA are as shown in Table 3. We discussed the causes of heating furnace explosion disasters from the principle of burning triangles, including three elements, fuel (flammable substances), oxygen (air), and heat (temperature). Then, we applied the FTA method to find the reasons for the explosion accident; the meanings of the symbols are as follows:
T Heating furnace explosion: The result of the furnace accident
X1
Heating source: One of the possible causes of the furnace accident
X2
Air: One of the possible causes of the furnace accident
X3
Excessive combustibles: One of the possible causes of the furnace accident
X4
Furnace temperature: One of the possible causes of heating source
X5
Heated surface: One of the possible causes of heating source
X6
Heating furnace flame: One of the possible causes of heating source
X7
Electrical spark: One of the possible causes of heating source
X8
Abnormal fuel flow into the furnace: Excessive combustibles (oil) in the furnace
X9
Abnormal gas flow into the furnace: Excessive combustibles (gas) in the furnace
X10
Human-error: Did not operate emergency shutoff valve.
Indirect possible reasons are as the following:
  • After the heating furnace (F101) explosion, the operator did not shut down the F101 according to the standard operating procedure (SOP); then the atomization of fuel and gas continued into the furnace, resulting in flash over under the high temperature.
  • In the fuel adjusting period, the furnace produced black smoke. At this point, on-site staff discovered the flame extinguished and performed the adjustment, then determined the fuel gasification and caused the ignition, resulting in other burners flame extinguishing instantly.
  • The on-site staff response time during the abnormal situation was too short. The staff lacked awareness of the safety of the heating furnace operation and was unwilling to shut down the heating furnace (F101), nor did the staff perform the emergency stop procedure.
  • Another reason might be that the staff was unfamiliar with the operating environment and equipment.

3.3. Qualitative Analysis

The goal of fault tree analysis was to find the basic cause of the accident. That is, the basic events were found by Boolean algebra simplified calculation to obtain the minimal path sets, minimal cut sets (MCSs) of fault tree and the structure importance coefficient of each basic event. To reduce the probability of an accident, we could apply the consequence of analysis to take more preventive and control measures [20,21,22,23].
The fault tree totally included top event equations illustrated as below:
T = X1·X2·X3
T = (X4 + X5 + X6 + X7)··X2·(X8 + X9)
T = X2·(X4 + X5 + X6 + X7)··(X10 + X11 + X10 + X12)
T = X2·(X4 + X5 + X6 + X7)··(X10 + X11 + X12)
T = X2·X4·X10 + X2·X4·X11 + X2·X4·X12 + X2·X5·X10 + X2·X5·X11 + X2·X5·X12 + X2·X6·X10 + X2·X6·X11 + X2·X6
X12 + X2·X7·X10 + X2·X7·X11 + X2·X7·X12
where T is the top event; the intermediate events are X1, X3, X8, and X9; basic events are X2, X4, X5, X6, X7, X10, X11, and X12.
MCS is a combination of basic events which would lead to the top events occurring. It cannot be simplified again and still ensure the occurrence of the top events. If this MCS is in the fail state, the entire system is out of order state.
K1 = [X2 X4 X10], K2 = [X2 X4 X11], K3 = [X2 X4 X12]
K4 = [X2 X5 X10], K5 = [X2 X5 X11], K6 = [X2 X5 X12]
K7= [X2 X6 X10], K8 = [X2 X6 X11], K9 = [X2 X6 X12]
K10 = [X2 X7 X10], K11 = [X2 X7 X11], K12 = [X2 X7 X12]
From the above result of analysis, we could find the key factors of top event are air, any heating source, and human error or mechanical failure.

3.3.1. Importance (I) of the Basic Events

We performed a relative importance sorting of the base events and the MCSs. The purpose was to find the basic events and MCS that contributed more to the top event. According to risk management, if the basic event and the MCS contributed much to the top event, we proposed to lessen the probability of the risk. The risk reduction would be more prominent. Based on the cost-effective consideration, we established the priority time ranking for completing the improvement suggestions.
In general, an MCS containing which has only one basic event was more likely to cause system failure than an MCS which contained two basic events. An MCS containing two basic events was easier to make a system malfunction than a minimum cut which contained three basic events. By analogy, the fewer basic events the MCS has, the more likely the system would fail. From the MCS, we can acquire the basic events importance sorting (Table 4). According to Table 4, the importance of the basic event is calculated and sorted as follows:
I(X2) > I(X10) = I(X11) = I(X12) > I(X4) = I(X5) = I(X6) = I(X7)
Importance sorting of the basic event provides the theoretical basis for preventing and controlling measures of the fire and explosion accident in heating furnace. From a system security perspective, to prevent the top event and promote the reliability of equipment, we could use the fault tree to convert into the corresponding success tree. The success tree could be, in turn, simplified by using Boolean algebra and obtaining the minimal path sets (MPSs):
The success tree includes:
T’ = (X1·X2·X3)’
T’ = X1’ + X2’ + X3’
T’ = (X4+X5+X6+X7)’ + X2’ + (X10+X11+X12)’
T’ = X4’·X5’·X6’·X7’ + X2’ + X10’·X11’·X12’
P1 = [X2]
P2 = [X4, X5, X6, X7]
P3 = [X10, X11, X12]
Hence, the MPSs represent the degree of system safety. According to the above simplification results, there are three groups of MPSs, which means that three possible ways could help prevent the fire and explosion accident in the heating furnace. From the above analysis, we could find the key factors of system security (the furnace would not explode) were neither air in the furnace, nor any heating source and human error or mechanical failure.
From FTA and the success tree analysis, to prevent the explosion of the heating furnace and improve the reliability of the equipment, the following aspects could be considered to develop improvement measures.
  • When abnormal status happens, reduce the air concentration in heating furnace by inert gas. Then, the previous installed emergency shutdown valve would cut off fuel gas from entering the heating furnace.
  • Strengthen the management of heat sources, such as hot work and static electricity.
  • Enhance the improvement of personnel operation capability and equipment reliability.

3.3.2. ALOHA Simulation Analysis

The results of ALOHA simulation analysis were immediately completed and provided for reference by the business authority. According to the simulation results, there are injuries within about 56 m and fatal risks within 10 m, as illustrated in Figure 8.
With reference to the simulation results, many people and equipment within the scope of influence could be considered to establish second management strategies and feasible emergency response mechanisms.

4. Results of Analysis and Discussion with the Method of Improvement

4.1. Results of Analysis

From the result of the qualitative analysis, this accident’s causes could be figured out. Therefore, we could take measures to enhance the management, human behavior modes, operating procedures, equipment reliability, and other environmental conditions. The detailed methods of improvement are shown in Section 5.
It demonstrates a momentous point: When an abnormal operating situation occurred in the heating furnace (F101), after the F101 burner was extinguished, the fuel continued to enter the furnace and accumulated a high concentration of combustible particles. It was exposed to the high temperature surface of the furnace and caused flashing; the operator did not start the emergency interlock to close the fuel valve according to the SOP. Meanwhile, other conditions, such as air concentration and high temperature heat source, led to combustion and explosion conditions, so an accident occurred.

4.2. Improvement Strategy

Based on the accident investigation and qualitative analysis results, we recommended the following improvement (engineering or management) measures to prevent similar accidents.

4.2.1. Improvement of Engineering Approach

  • Mechanical and equipment integrity (MI)
    • Remake the furnace body and check the status of the attached equipment as well as pipelines.
    • Monitor equipment integrity: Record maintenance history and regularly replace equipment components.
    • Add safety improvement advice, replace fuel gas cock valve with additional limited type switch, regulate all gas burners into the burner, as all could not be reset when the fuel valve was not fully closed.
  • Inherent safety design (ISD)
To prevent furnace abnormal combustion (combustion gas short-circuit, incomplete combustion, and afterburning), we recommend installing a furnace combustion detection system and fuel gas interception interlock device.
According to PSM, 14 items were reviewed to make the ISD more secure. The device installation is shown in Figure 9:
(a)
Oxygen detector
  • In the original design, there was only one oxygen detector. When the process was running, the offset anomaly could not be found immediately. One oxygen detector was added to improve the O2 detection reliability of the equipment.
  • Installed the other oxygen detector which was at the same height as the existing oxygen detector location; immediately notified the operator to maintain and calibrate it if the oxygen concentration difference was more than 1% original setting value.
  • Checked the detector was vetted every month, which was using zero and full-scale calibration by standard gas.
(b)
Improvement of chimney baffle
  • Made sure chimney baffle opening degree was controlled by distributed control system (DCS) in the original design. The signal was transmitted to the site controller to actuate the chimney baffle. The DCS could not detect the actual opening degree value of the chimney baffle in the field.
  • Installed a positioner in the chimney baffle and transfer the actual opening degree value of the chimney baffle on site to the DCS. Then, compared the value of DCS to master the opening degree with the actual value on site, whether DCS was consistent with the actual opening degree value of the site.
  • Improved flame detector setting position.
The flame detector scanned up from the bottom of the furnace in the original design. It was easy to accumulate ash in the detector lens surface and generate a false signal scanning. We recommended that the location of the flame detector could be changed to the side of the furnace wall; it scanned down to improve the case of false signals due to fouling. The flame detector setting position is shown in Figure 10.

4.2.2. Improvement of Management Approach

  • Rechecked the entire plant furnaces SOP, strengthen operators’ education and training.
  • Established maintenance, check history, and check procedures.
  • Pre-startup safety review (PSSR) for heating furnace (F101).
The PSSR is a systematic and thorough check to a process unit; the purpose of a PSSR is to help confirm that adequate safety measures are in place and are operational before a hazardous chemical is stored or into the process. Ensured that installations meet the original design criteria or operating procedure, then found any potential hazard and modify facilities to meet the management of change requirements. In other words, ensured the “Ready for Start-up” status of process facility/units.
The PSSR should confirm the following:
  • Rechecked the PSSR of the heating furnace (F101). The PSSR covered four major aspects: Process, safety, and environmental protection (safety/fire protection/environmental protection), equipment (machinery) maintenance, and instrument equipment maintenance.
  • Self-inspection by process and maintenance operators for the four major inspection items.
  • A process hazard analysis for the heating furnace (F101). The recommendations should be implemented before startup, and modified facilities must meet the management of change requirements.
  • Completed the training of each employee involved in operating a process.

4.2.3. Cost-effectiveness Analysis: As Low as Reasonably Practicable Sorting Analysis

If there is no industrial activity, it is completely free from risk. Many companies around the world ask that risks be reduced to levels that are as low as reasonably practicable, or “ALARP”.
By definition, the ALARP principle is the minimum level of residual risk that needs to be reduced to reasonable limits. ALARP is used to reduce potentially harmful risks as much as possible. When deciding whether the ALARP point has been reached, the following factors should be seriously considered:
  • Safety and health guide
  • Codes of practice
  • Industry practice
  • Manufacturer specifications and government regulations
  • Compliance with international standards and codes
  • Comparison with dangerous events in similar industries
  • Further reduction of the cost of risk in proportion to the benefits obtained.
A cost benefit analysis is used to determine if the risk has fallen to ALARP. This included weighing cost, time and technical sacrifices, and reducing risk levels. According to the above-mentioned investigation analysis and improvement measures (engineering method or management method), applying the cost effect analysis (ALARP principle) and sorting analysis (high risk and low cost) was proposed, and the priority was improved. The principles of ranking risk and cost are listed as Table 5, Table 6, Table 7 and Table 8 [24,25]. The results of analysis are shown in Figure 11.
Where risk level is from 1 to 5 in the vertical axis. Numbers 1 to 2 are acceptable risk. Numbers 3 to 5 are unacceptable risk. Cost level is from A to E in the horizontal axis. The cost is gradually increasing from A to E. Numbers 1 to 7 are the order of reduction risk measures in the matrix. This is a risk decision matrix, representing the relationship between cost and risk, numbers 6 to 7, We can consider negligible or defer implementation. However, numbers 1 to 3 are listed as priorities for improvement and numbers 4 to 5 as an ALARP.

4.2.4. ALARP Sorting

The improvement measures were ranked according to the principle of ALARP (high risk and low cost), the results were as follows:
  • Rebuilt the heating furnace (F101) body and evaluated the damage status of the surrounding ancillary equipment and pipelines.
  • Rechecked the furnace SOP.
  • Improved worker education and training.
  • Monitored equipment integrity: Recorded maintenance history and regularly replaced equipment components.
  • Established maintenance, checked history, and followed procedures.
  • Erected a gas feed interruption device.
  • Installed a furnace combustion condition detection device.

5. Conclusions and Recommendations

We learned from the fault tree qualitative analysis and field investigation results that the accident was caused by high temperature sources, mixed flammable gas, and human factors. Among them, the human factors were the most important reason, such as the classification of human factors (i.e., misoperation, misjudgment, unmoved action, lack of training, or lack of skill). The key points of human factors were on how people interact with tasks, with machine/equipment/technologies, and with the environment, in order to comprehend and assess these interactions. The goals of human factors were to optimize human and system efficiency and effectiveness, operation safety, health, comfort, and quality of living. If the interface among human body, machine and environment were not properly deployed, accordingly, the problem of human error should be solved from the heating furnace design.
On the other hand, when human factors are not avoided, we should improve from existing management systems and equipment.
Through FTA, cost-effectiveness analysis, and on-site investigation of the accident, the following recommendations were drawn:
  • Units with different specializations must cooperate with each other to investigate accidents: Previous accident investigation reports biased in fire expertise should include chemical process and other background experts to investigate. To find the real root cause of an accident, we should establish an investigation team by accident procedure, and then take control measures to avoid the accident from happening again.
  • To improve the operation safety of the equipment, including ISD, mechanical and MI.
  • To develop procedures of MOC (management of change), when the heating furnace (F101) uses different fuels.
  • To avoid increasing the risk of exchanging fuels (fuel oil and fuel gas), we suggest using a single fuel.
  • To enhance the operators’ ability of response when the heating furnace (F101) abnormal situation occurs.
  • To improve operator training and equipment regular maintenance.
  • Before the heating furnace was opened, PSSR for F101 was divided into four major aspects: Process, (industrial safety/firefighting/environmental protection), equipment (mechanical) maintenance, and instrument as well as electrical section (safety) maintenance.
  • Case exchanging experience should be promoted to the grassroots.
  • Installing a system for nitrogen into the furnace to reduce the concentration of combustible gases.

Author Contributions

Y.-C.W. wrote this manuscript; B.L. provided idea; C.-M.S. rendered suggestions for the manuscripts. All authors supplied comments on this theme.

Funding

This research received no external funding.

Acknowledgments

Thanks to Wei-Cheng Lin for his valuable suggestions and help.

Conflicts of Interest

The authors declare no competing interests.

References

  1. Ng, H.D.; Lee, J.H.S. Comments on explosion problems for hydrogen safety. J. Loss Prev. Process Ind. 2008, 21, 136–146. [Google Scholar] [CrossRef]
  2. Workplace Health, Safety and Compensation Commission (WHSCC) of New Brunswick. Accident Investigation Report on the Explosion and Fire at the Irving Oil Refinery, New Brunswick; The Commission: Fredericton, NB, Canada, 1999. [Google Scholar]
  3. Ranganathan, S.; Gillis, S. Oven Furnace and Dryer Explosion Incidents; Fire Protection Research Foundation: Quincy, MA, USA, 2016. [Google Scholar]
  4. Zhou, Y.; Zhao, X.; Zhao, J.; Chen, D. Research on Fire and Explosion Accidents of Oil Depots. Chem. Eng. Trans. 2016, 51, 163–168. [Google Scholar] [CrossRef]
  5. Large-Scale Petrochemical Supervision Meeting; Bureau of Industry, Ministry of Economic Affairs: Taipei, Taiwan, 2017.
  6. Babrauskas, V. Explosions of ammonium nitrate fertilizer in storage or transportation are preventable accidents. J. Hazard. Mater. 2016, 304, 134–149. [Google Scholar] [CrossRef] [PubMed]
  7. Hu, K.H.; Kao, C.S.; Duh, Y.S. Studies on the runaway reaction of ABS polymerization process. J. Hazard. Mater. 2008, 159, 25–34. [Google Scholar] [CrossRef] [PubMed]
  8. Kao, C.S.; Duh, Y.S. Accident investigation of an ABS plant. J. Loss Prev. Process Ind. 2002, 15, 223–232. [Google Scholar] [CrossRef]
  9. ABS Powder Storage Tank (H701F) Flash Accident Report; Mai Lao PABS Plant of Taiwan Chemical Company: Yunlin, Taiwan, 2017.
  10. Kelly, B.D. Investigation of a hydrogen heater explosion. J. Loss Prev. Process Ind. 1997, 11, 257–259. [Google Scholar] [CrossRef]
  11. Siwek, R. Determination of technical safety indices and factors influencing hazard evaluation of dusts. J. Loss Prev. Process Ind. 1996, 9, 21–31. [Google Scholar] [CrossRef]
  12. Nedkova, S.; Lybchev, L.; Lybcheva, M.; Kolev, N. Human factor analysis in the risk management in technological processes and in A glass production plant. Sci. Technol. 2013, 3, 11–15. Available online: http://www.sustz.com/journal/VolumeIII/Number4/Papers/SabinaNedkova.pdf (accessed on 10 August 2018).
  13. Dugué, J. Fired equipment safety in the oil & gas industry. A review of changes in practices over the last 50 years. Energy Procedia 2017, 120, 2–19. [Google Scholar] [CrossRef]
  14. Mirza, N.R.; Degenkolbe, S.; Witt, W. Analysis of hydrogen incidents to support risk assessment. Int. J. Hydrogen Energy 2011, 36, 12068–12077. [Google Scholar] [CrossRef]
  15. Xue, Z.M. Research on FTA of fire and explosion in the crude oil gatheringtransport combination station. Procedia Eng. 2011, 11, 575–582. [Google Scholar] [CrossRef]
  16. Abuswer, M.; Amyotte, P.; Khan, F. A quantitative risk management framework for dust and hybrid mixture explosions. J. Loss Prev. Proc. Ind. 2013, 26, 283–289. [Google Scholar] [CrossRef] [Green Version]
  17. Halme, J.; Aikala, A. Fault tree analysis for maintenance needs. In Proceedings of the 25th International Congress on Condition Monitoring and Diagnostic Engineering, Huddersfield, UK, 18–20 June 2012; pp. 1031–1041. [Google Scholar] [CrossRef]
  18. Yasushi, N.; Rolf, L.; Philip, A. Fault tree analysis of system anomaly leading to red oil explosion in lutonium evaporator. J. Nucl. Sci. Technol. 1994, 31, 850–860. [Google Scholar] [CrossRef]
  19. Ruijters, E.; Stoelinga, M. Fault Tree Analysis: A survey of the state-of-the-art in modeling, analysis and tools. Comput. Sci. Rev. 2015, 15–16, 29–62. [Google Scholar] [CrossRef]
  20. Moreno, V.C.; Papasidero, S.; Scarponi, G.E.; Guglielmi, D.; Cozzani, V. Analysis of accidents in biogas production and upgrading. Renew. Energy 2016, 96, 1127–1134. [Google Scholar] [CrossRef]
  21. Fuentes-Bargues, J.L.; González-Cruz, M.C.; González-Gaya, C.; Baixauli-Pérez, M.P. Risk Analysis of a Fuel Storage Terminal Using HAZOP and FTA. Int. J. Environ. Res. Public Health 2017, 14, 705. [Google Scholar] [CrossRef] [PubMed]
  22. Siu, N.; Herring, J.S.; Lee, C.; Reece, W.; Byers, J. Qualitative Risk Assessment for an LNG Refueling Station and Review of Relevant Safety Issues; Idaho National Engineering and Environmental Laboratory: Idaho Falls, ID, USA, 1999.
  23. Mohammadfam, I.; Zarei, E. Safety risk modeling and major accidents analysis of hydrogen and natural gas releases: A comprehensive risk analysis framework. Int. J. Hydrogen Energy 2015, 40, 13653–13663. [Google Scholar] [CrossRef]
  24. Figueroa Jiménez, S.P.; Lombana Carmona, S.C.; Ruiz De La Cruz, I.L. Application of HAZOP, LOPA and SIL to the Alkylation Unit Catalyzed with Hydrofluoric Acid at Ecopetrol Refinery in Cartagena–Colombia; Mary Kay O’Connor Process Safety Center, Texas A&M University: College Station, TX, USA, 2015. [Google Scholar]
  25. Moonis, M.; Wilday, A.J.; Wardman, M.J. Semi-quantitative risk assessment of commercial scale supply chain of hydrogen fuel and implications for industry and society. Process Saf. Environ. Prot. 2010, 88, 97–108. [Google Scholar] [CrossRef]
  26. Linkov, I.; Bates, M.; Loney, D.; Sparrevik, M.; Bridges, T. Risk Management Practices-Cross-agency Comparisons and Tolerable Risk. In Climate: Global Change and Local Adaptation; Springer: Dordrecht, The Netherlands, 2011. [Google Scholar]
  27. Kletz, T.A. Looking beyond ALARP: Overcoming its limitations. Process Saf. Environ. Prot. 2005, 83, 81–84. [Google Scholar] [CrossRef]
Figure 1. Accident scene photos: (a) Heating furnace (F101) shell cracking situation-part 1 and (b) Heating furnace (F101) shell cracking situation-part 2.
Figure 1. Accident scene photos: (a) Heating furnace (F101) shell cracking situation-part 1 and (b) Heating furnace (F101) shell cracking situation-part 2.
Applsci 09 00503 g001
Figure 2. Location of the accident site.
Figure 2. Location of the accident site.
Applsci 09 00503 g002
Figure 3. Time sequence for the heating furnace (F101) accident. DCS: distributed control system; EB: ethylbenzene; SM: styrene monomer.
Figure 3. Time sequence for the heating furnace (F101) accident. DCS: distributed control system; EB: ethylbenzene; SM: styrene monomer.
Applsci 09 00503 g003
Figure 4. Process diagram and reaction equation for the alkylation reaction.
Figure 4. Process diagram and reaction equation for the alkylation reaction.
Applsci 09 00503 g004
Figure 5. Schematic diagram of F101 furnace.
Figure 5. Schematic diagram of F101 furnace.
Applsci 09 00503 g005
Figure 6. Accident case risk assessment process [10]. ALOHA: areal locations of hazardous atmospheres; FTA: fault tree analysis; PDCA: plan-do-check-act; ALARP: risks reduced to levels that are as low as reasonably practicable.
Figure 6. Accident case risk assessment process [10]. ALOHA: areal locations of hazardous atmospheres; FTA: fault tree analysis; PDCA: plan-do-check-act; ALARP: risks reduced to levels that are as low as reasonably practicable.
Applsci 09 00503 g006
Figure 7. FTA diagram for this study.
Figure 7. FTA diagram for this study.
Applsci 09 00503 g007
Figure 8. ALOHA simulation results-C4 Gas for this study.
Figure 8. ALOHA simulation results-C4 Gas for this study.
Applsci 09 00503 g008
Figure 9. Strengthening inherent safety design (ISD) measures for the alkylation tower.
Figure 9. Strengthening inherent safety design (ISD) measures for the alkylation tower.
Applsci 09 00503 g009
Figure 10. Design improvement of flame detector position.
Figure 10. Design improvement of flame detector position.
Applsci 09 00503 g010
Figure 11. Results of the cost-effective ALARP sorting analysis [26,27].
Figure 11. Results of the cost-effective ALARP sorting analysis [26,27].
Applsci 09 00503 g011
Table 1. Furnace explosion accident case summary in U.S.
Table 1. Furnace explosion accident case summary in U.S.
Date of IncidentLocationSpecific
Details
Explosion DetailsInjuries/
Fatalities
CauseConsequence
2 November 2002Vernon, CAUsed for
smelting
lead
Weakened
furnace wall
(holes)
compromised the integrity of the furnace
Explosion
spewing hot
lead slag and
dust
1 employee
received 2nd and 3rd degree burns
16 March 2004Cucamonga,
CA
Electric arc
furnace
Attempted
maintenance
on a water
leak from the furnace, loud popping
noise resulted in
explosion
Explosion
resulting in
hot steam
and flying
debris
1 severe
injury, 2 minor
burns and cuts
10 March 2006Midlothian, TX Melt shop
furnace
(steel)
Furnace was
tilted forward to
begin tapping
when the hydraulic hose cylinder failed
Molten steel
leaked out of
slag door, slag pot overfilled
and an explosion occurred
1 employee was killed
27 May 2007Coatesville, PAElectric arc furnaceMolten steel
caused a water leak to become
superheated
high-pressure
vapor
Explosion,
molten steel
1 employee killed, 2
seriously
burned
29 November 2007Manchester, GA Used to
melt
aluminum
Aluminum
car rims were
placed
into the furnace,
moisture was still on the rims and a
violent explosion
occurred
Explosion,
molten metal
1 fatality,
6 serious
injuries
21 March 2011Louisville, KY Large
electric arc
furnace
Water leaked
into furnace
which caused
an overpressure
event
Explosion from overpressure
that sent furnace
contents spewing into air
2 workers
killed, 2
seriously
injured
21 September 2014Fairfield, AL N/AWorkers were opening/closing a furnace valve that
contained oxygen and hydrated lime, while the furnace
was in operation
Fiery explosion2 workers
killed, 1
critically
injured
Table 2. Select cases on furnace explosion accident in Taiwan and Mainland China.
Table 2. Select cases on furnace explosion accident in Taiwan and Mainland China.
Date of IncidentLocationEquipmentExplosion DetailsInjuries/Fatalities
7 November 2006 Mainland ChinaFurnaceDuring fuel gas into the furnace, causing the gas pipe of heating furnace to burst and explosion.Equipment damage
3 May 2008Mainland ChinaFurnaceHeating furnace tube coking.Equipment damage
6 March2017Taiwan
SM plant
FurnaceIn the diesel plant, during starting the furnace, the tube of furnace was cracked and led to explosion.4 seriously
injured
29 January 2018Taiwan Taoyuan RefineryFurnaceIn the diesel plant, during starting the furnace, the tube of furnace was cracked and lead to explosion.No casualties
Equipment damage
Table 3. Factors table of the heating furnace explosion (F101) fault tree.
Table 3. Factors table of the heating furnace explosion (F101) fault tree.
FactorMeaningFactorMeaning
THeating furnace explosionX1Heating source
X2AirX3Excessive combustibles
X4Furnace temperatureX5Heated surface
X6Heating furnace flameX7Electrical spark
X8Into the furnace fuel oil abnormallyX9Into the furnace fuel gas abnormally
X10Human errors—do not operate
emergency shutoff valve
X11Mechanical failure—oil
X12Mechanical failure—gas
Table 4. Basic events importance sorting. MCS: minimal cut sets.
Table 4. Basic events importance sorting. MCS: minimal cut sets.
Basic Event CodeThe Times of Occurrences in the MCSImportance Sorting
X2121
X433
X533
X633
X733
X1042
X1142
X1242
Table 5. Severity levels [26,27].
Table 5. Severity levels [26,27].
Severity of ConsequencesDescription
5Safety: One or more fatalities or permanent disabling injuries (PDIs)
Environmental: Major impact, making the national news
Economic: Losses greater than $10 million USD
4Safety: PDIs, or serious injury to three or more people
Environmental: Continuous large impact, making the local news
Economic: Losses between $1 million and $10 million USD
3Safety: Serious injury to one or two people, or minor injury to three or more
Environmental: Moderate impact, must be reported to environmental agency
Economic: Losses between $100,000 and $1 million USD
2Safety: Minor injury to no more than two people. First aid.
Environmental: Minor impact
Economic: Losses less than $100,000 USD
1Safety: No adverse health effects
Environmental: No detectable impact
Economic: Negligible economic impact
Table 6. Likelihood of occurrence [26,27].
Table 6. Likelihood of occurrence [26,27].
Likelihood of OccurrenceDescription
5The event has happened several times at the plant. Likelihood is more than once in 1 year.
4The event has occurred at the plant and frequently in industry. Likelihood is between once in 1 year and once in 10 years.
3Incident has occurred at the plant, but is not common in industry. Likelihood is between once in 10 years and once in 100 years.
2Incident has occurred in industry. Likelihood is less than once in 100 years
1The event has a remote chance of happening and is unheard of in industry.
Table 7. Classification of risk level [26,27].
Table 7. Classification of risk level [26,27].
Frequency of Occurrence
(Likelihood)
Consequences (Severity)
Catastrophic
(5)
Major
(4)
Serious
(3)
Minor
(2)
Incidental
(1)
Frequency (5)54432
Occasional (4)44322
Seldom (3)43321
Remote (2)33211
Unlikely (1)322r1
Risk levelRisk Control MeasuresNote
5-extremeReduction risk measures need to be taken immediately, and tasks should not be started until the risk is reduced.Unacceptable risk
4-very highRisk control measures must be taken within a certain period of time, and tasks cannot be started until the risk is reduced.
3-highBased on cost or financial considerations, risk reduction measures should be taken gradually.
2-mediumThere is no need to take risk reduction measures at the moment, but it is necessary to ensure the effectiveness of existing protection facilities.Acceptable risk
1-lowNo risk reduction measures are required, but the effectiveness of existing safeguards must be ensured.
Table 8. Classification of cost level [26,27].
Table 8. Classification of cost level [26,27].
Cost LevelDescription
ESpending more than $10 million USD for risk reduction measures.
DSpending range from $1 million to $10 million USD for risk reduction measures.
CSpending range from $100,000 to $1 million USD for risk reduction measures.
BSpending range from $10,000 to $100,000 USD for risk reduction measures.
ASpending less than $10,000 USD for risk reduction measures.

Share and Cite

MDPI and ACS Style

Wu, Y.-C.; Laiwang, B.; Shu, C.-M. Investigation of an Explosion at a Styrene Plant with Alkylation Reactor Feed Furnace. Appl. Sci. 2019, 9, 503. https://doi.org/10.3390/app9030503

AMA Style

Wu Y-C, Laiwang B, Shu C-M. Investigation of an Explosion at a Styrene Plant with Alkylation Reactor Feed Furnace. Applied Sciences. 2019; 9(3):503. https://doi.org/10.3390/app9030503

Chicago/Turabian Style

Wu, Yao-Chang, Bin Laiwang, and Chi-Min Shu. 2019. "Investigation of an Explosion at a Styrene Plant with Alkylation Reactor Feed Furnace" Applied Sciences 9, no. 3: 503. https://doi.org/10.3390/app9030503

APA Style

Wu, Y. -C., Laiwang, B., & Shu, C. -M. (2019). Investigation of an Explosion at a Styrene Plant with Alkylation Reactor Feed Furnace. Applied Sciences, 9(3), 503. https://doi.org/10.3390/app9030503

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop