Next Article in Journal
The Fuzzy DEA-Based Manufacturing Service Efficiency Evaluation and Ranking Approach for a Parallel Two-Stage Structure of a Complex Product System on the Example of Solid Waste Recycling
Previous Article in Journal
Medicinal Plant Drying Using a Superabsorbent Polymer Dryer Incorporated with an Insulated Heater
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

The Feasibility Assessment of Power System Dispatch with Carbon Tax Considerations

1
School of Mechanical and Electrical Engineering, Xiamen University Tan Kah Kee College, Zhangzhou 363105, China
2
Department of Electrical Engineering, National Sun Yat-Sen University, Kaohsiung 807, Taiwan
3
Department of Electrical Engineering, Cheng-Shiu University, Kaohsiung 833, Taiwan
*
Author to whom correspondence should be addressed.
Processes 2022, 10(11), 2321; https://doi.org/10.3390/pr10112321
Submission received: 14 October 2022 / Revised: 29 October 2022 / Accepted: 3 November 2022 / Published: 8 November 2022
(This article belongs to the Section Environmental and Green Processes)

Abstract

:
Traditional economic dispatch methods, which are used to minimize fuel costs, have become inadequate because they do not consider the environmental impact of emissions in the optimization process. By taking into account the horizon year load and carbon taxes, this paper examines the operation and dispatch of power units in a power system. The objective function, including the cost of fuels and the cost of carbon taxes, is solved by the modified particle swarm optimization with time-varying acceleration coefficient (MPSO-TVAC) method under operational constraints. Based on different load scenarios, the influences of various carbon taxes for the dispatch of units are simulated and analyzed. The efficiency and ability of the proposed MPSO-TVAC method are demonstrated using a real 345KV system. Simulation results indicate that the average annual CO2 emissions are 0.36 kg/kwh, 0.41 kg/kwh, and 0.44 kg/kwh in 2012, 2017 and 2022, respectively. As the capacity of gas-fired plants was increased in 2017 and 2022, the average cost in 2017 and 2022 doubled or tripled compared with the average cost in 2012. Reasonable solutions provide a practical and flexible framework for power sectors to perform feasibility assessments of power system dispatch. They can also be used to assist decision-makers in reaching minimal operation cost goals under the policies for desired emissions.

1. Introduction

Economic dispatch (ED) is used to manage the generating unit output for the purpose of minimizing the total dispatch cost while satisfying operating constraints. However, as global warming increases, handling greenhouse gases (GHGs) has become an important issue to. The investigation by the Intergovernmental Panel on Climate Change (IPCC) found that the GHGs mainly came from CO2 gas [1]. Increased environmental awareness and the passing of environmental regulations have had a significant impact on the operation of power systems. Environmental concerns force utilities to revise their operating strategies to reduce pollution from coal-fired power plants. The United Nations Framework Convention on Climate Change (UNFCCC) [2] announced the adoption of the carbon tax concept to enforce carbon emission reduction, which later became an internationally recognized carbon emission reduction plan.
Power companies that use fossil fuel-fired plants need to address the emission problem. For example, CO2 poses a significant risk to the ozonosphere, causing global warming. Another theory suggests that gases are being trapped in the atmosphere, causing a greenhouse effect. Power companies offer their energy to markets by considering emission taxes. A carbon tax has been widely used in different countries as a policing instrument, and it imposes an extra cost on top of the operating cost of generators. Power companies must pay for the external cost of GHG damage to the environment [3]. Levying a carbon tax forces power companies’ dispatchers to consider emissions as a cost, and thus, it forms an important constraint in ED. However, in highly complex problems, the solution spaces involved in these applications are large, and the high number of searches and iterations is easily affected by the relevant control parameters. The efficiency may be downgraded. More efficient tools are therefore needed to obtain a better dispatch.
In general, the impact of the future electricity market on GHGs is becoming an issue for attention [4,5,6,7]. Power dispatch is an important inspection item for power companies. These scheduling strategies use mathematical minimization tools to seek objective functions while meeting system operating and emission constraints. Most studies use the concept of “emission as cost”, whereby emissions are controlled to obtain the minimal cost. Ref. [8] used a numerical polynomial no-convex continuation to solve the economic emission dispatch problem. Ref. [9] considered the dominant power retailer based on the dichotomous-market model to propose a bi-level economic dispatch algorithm.
Ref. [10] used an ε-defined multi-objective genetic algorithm to solve the system economic dispatching problem. Refs. [11,12,13] proposed a multi-objective mathematical programming approach to solve the economic and emission dispatch in energy markets. A new method was developed for planning energy and environmental systems under the various uncertainties to find optimal energy resource allocation and ideal policies for greenhouse gas reduction [14,15]. Ref. [16] integrated the charging system to perform the economic dispatch of plants for reducing CO2 emission. Ref. [17] adopted a multi-objective planning approach to minimize power generation costs and decreased CO2 emission by reducing the dual goals of building a supply dispatch model and target years. Ref. [18] combines quantum-behaved particle swarm optimization (QPSO) with a selective probability operator to find the optimal economic dispatch with valve-point effects and various fuel options. A weighting update artificial bee colony was deployed to solve the economic emission dispatch and demand response problem [19]. However, in most studies, the external pollution cost is converted to the internal cost, and the pollution amount of an individual unit and the minimal total cost are obtained by optimal economic dispatch. Taiwan is a densely populated island with limited natural resources, importing more than 98.1% of its total energy supply. The CO2 emission in the power sector accounts for an average of 59% of the total CO2 emissions. The Taiwan Power Company (TPC) is Taiwan’s sole utility company. By the end of 2021, Taiwan’s total installed capacity was approximately 5115.4 GW, where 67.7% of electricity was generated from fossil fuel-fired plants [20]. The CO2 emissions of fossil fuel-fired plants amounted to 84,380,000 tons, which is approximately 48% of Taiwan’s total annual CO2 emissions. Although Taiwan is not yet a signatory to the Kyoto Protocol, it still bears responsibility for reducing CO2 emissions. Therefore, suitable future strategies for the power sector are a very important factor in reducing CO2 emissions in Taiwan [21,22]. To analyze the feasibility assessment of power system dispatches, strategies, including the usage of the allocation of fossil fuel-fired plants and the introduction of a carbon tax in the power system dispatch, are considered in this paper.
This paper sets out to construct a model for the feasibility assessment of a power system dispatch by considering CO2 emissions. With various carbon taxes and horizon year loads, objectives including minimal total cost and minimal emissions are formulated, subject to operational constraints and emission conditions. A modified particle swarm optimization with time-varying acceleration coefficient (MPSO-TVAC) method is proposed to achieve this objective of optimal operation. The proposed MPSO-TVAC method is developed in such a way that PSO with the time-varying acceleration coefficient (TVAC) algorithm [23,24] is applied as a base-level search. To enhance the performance of the proposed algorithm, a power flow model with equivalent current injection (ECI) [25] was used to solve the power flow of power systems. The various scenarios associated with different levels of carbon taxes and loads are demonstrated by the simplified TPC 345 KV system [26]. Results can help decision-makers to achieve optimal economic dispatch and operation and optimize the tradeoffs between carbon taxes and economic objectives.

2. Problem Formulation

Objective Function and Constraints

The unit’s dispatch problem with CO2 emissions was described as a bi-objective problems.
(1) Minimal total cost
M i n .   T C = i = 1 N   F i P i + E i P i × T a x p r i c e NT $ / h
(2) Minimal CO2 emissions
M i n .   E m i _ C O 2 = i = 1 N E i ( P i ) Ton / h
The CO2 emission model may be defined as the amount of fuel consumed. For the TPC 345KV system, the model of CO2 emissions is formulated by the IPCC [1] as:
E i   P i   = H ( P i ) × 4.1868 × 44 12 × C E P i × C O R i
H ( P i ) = d i + e i P i + f i P i 2 + g i P i 3 gives the thermal conductivity of each type of unit; d i , e i , f i , g i are the coefficients of the emission of unit i ; C E P i is the CO2 emission parameter of unit i (21.1 kgC/GJ for oil, 25.8 kgC/GJ for coal, 15.3 kgC/GJ for natural gas); and C O R i is the CO2 rate of unit i (0.99 for oil, 0.98 for coal, 0.995 for natural gas).
The constraints are considered as follows.
  • The lower and upper limits of the generating capability.
    P i ,   min P i P i ,   max
  • The balance of power flow equations.
    i = 1 N P i = k = 1 N P l o a d _ k + P l o s s
  • The lower and upper limits of the voltage.
    V i min |     |   V i   |     |   V i max   |
  • The inequality constraints with the capacity limits of branches:
    S j S j max
  • The inequality constraints are the total amount of CO2 emission constraints:
    0   i = 1 N E i ( P i ) C O 2 _ C a p
P l o s s is the transmission line loss (MW). The formulation of P l o s s is defined as
P l o s s =   1 2   i = 1 N B j = 1 N B Re     Y i j   V i 2   +   V j 2     2   V i   V j cos θ i j

3. The Proposed Methodology

3.1. Power Flow Model with ECI

In the Newton–Raphson technique, a Jacobian matrix was usually used to model the power components [27]. For the Newton–Raphson method, the mismatch function can be written in the rectangular form as:
Δ P i Δ Q i   =       P i e i   P i f i   Q i e i   Q i f i   Δ e i Δ f i
Δ   P i = P i , s c h     P i , c a l and Δ   Q i = Q i , s c h     Q i , c a l . P i , s c h   = P d i is the net real power at the i-th bus; Q i , s c h   = Q d i , which is the net reactive power at the i-th bus;   P i , c a l /   Q i , c a l is the real/reactive power, which is calculated by power flow analysis.
The Jacobian matrix is shown in Equation (11):
J =   P i e i     P i f i   Q i e i     Q i f i
The mismatch function with the ECI-based power flow is rewritten in Equation (12).
Δ   I r Δ   I i   =     I r e     I r f   I i e     I i f   Δ e Δ f
Δ   I = I e q v I c a l = Δ   I r + j Δ   I i and Δ   V = Δ   e + j Δ   f are the real and imaginary components of the mismatch currents and mismatch voltages, respectively; I c a l is obtained from the power flow. I e q v is given by:
I e q v = P + j Q V = Re ( I e q v ) + j Im ( I e q v )
P , Q , and V are the real power, imaginary power, and voltage at a swing bus, respectively; P and Q are also the net power at a swing bus.
The constant Jacobian matrix is written in Equation (14).
J =   G       B B                 G
G and B are the conductance and the admittance matrices, respectively.

3.2. MPSO-TVAC Method

In the PSO system [28], birds (particle) aggregation optimizes a certain goal function. Each particle knows its current sweet spot ( p b e s t ), which is analogous to each particle’s personal experiences. Each particle also knows the current global optimal position ( g b e s t ) of all particles in the population. PSO can have multiple solutions at the same time, and there is a cooperative relationship between particles to share messages. Through specific algorithms, each particle can regulate its position to decide the search direction according to its search memory and that of the other particles. It also tries to reach compatibility between the local search and the global search. The search memory of a particle is the goal function and the optimal position found by the particle.
The velocity by using PSO-TVAC is described in Equation (15). A certain velocity is calculated due to the position of individuals gradually closer to p b e s t and g b e s t . The current position is modified in Equation (16).
v s t + 1 = c 1 = c 1 f c 1 i i t e r i t e r max + c 1 i r a n d p b e s t s t p s t   + c 2 = c 2 f c 2 i i t e r i t e r max + c 2 i r a n d g b e s t t p s t
P s t + 1 = P s t   +   V s t + 1
MPSO-TVAC introduces an operator, a “random feasible solution”, into the PSO-TVAC to increase the search ability. The “random feasible solution” process adds the proper random feasible own best position into the velocity vector when the solution is searched in each generation. MPSO-TVAC can be employed in the algorithm to make the search algorithm more efficient at the end of the search, and the success rate of the search for a global optimum can be increased. The formulation of MPSO-TVAC is expressed as Equation (17).
v s t + 1 = c 1 = c 1 f c 1 i i t e r i t e r max + c 1 i r a n d p b e s t r t p s t   + c 2 = c 2 f c 2 i i t e r i t e r max + c 2 i r a n d g b e s t t p s t
p b e s t r t is the own best position of the random particle r in all feasible particles at iteration t .

3.3. The Implement of the Proposed Algorithm

The proposed algorithm is described as follows.
(a)
Calculate the load data and installed capacity of the TPC system at a horizon year. The load data include the peak load of the year, average load of the year, and off-peak load of the year in different horizon years. The installed capacity of the TPC system includes the capacity of coal generation, the capacity of oil generation, the capacity of gas generation and the capacity of nuclear generation in different horizon years.
(b)
Input the line data and bus data of the TPC system. The bus data include the types of generators and the load in the horizon year.
(c)
Randomly initialize 30 particles with a generator-viable output in the PV buses.
P i k = P k i   ,   min   +   N ( 0 , 1 ) k ( P i , max P i , min )   ,   k = 30
N ( 0 , 1 ) is the normal distribution with mean 0 and standard deviation 1.
(d)
Use ECI to perform the power flow procedure and calculate the fitness values of each particle. The fitness function is defined in Equation (19).
F i t n e s s i = O b j ( i ) + m = 1 ne λ eq ,   m | h ( i ) | 2 + n = 1 nm λ ineq ,   n | g ( i ) g lim | 2
where O b j is the objective function; h ( i ) and g ( i ) are the equality and inequality constraints, such as Equations (4)~(8); ne and nm are the numbers of the equality and inequality constraints; and λ eq ,   m and λ ineq ,   n are the penalty factors that can be adjusted in the optimization procedure. g lim is defined by
g lim = i                 i f         i ,   min i i ,   max min           i f         i < i ,   min max           i f         i > i ,   max
If one or more variables violate their constraints, the penalty factors will be increased, and the corresponding individuals will be rejected to avoid an unfeasible solution. The fitness values are sorted in descending order from the maximum value ( F i t n e s s i ,   max ) to minimum value ( F i t n e s s i ,   min ).
(e)
The fitness value of each particle with the p b e s t is compared. If the fitness value is smaller than p b e s t . The value set as the current p b e s t .
(f)
Find the best particle associated with the minimal p b e s t of all particles, and the value of this is set as the g b e s t .
(g)
Update the vectors of velocity and position of each particle by using Equations (16) and (17).
(h)
The stopping condition is the maximal number of iterations. If the target has not yet been reached, then return to Step (c) and repeat the operation. A total of 500 generations are set out in this paper.
(i)
Calculate the total cost, the generation of the plants, and the CO2 emissions.
Figure 1 shows the flowchart of the proposed methodology.

4. Case Study

The proposed approach was tested on a simplified TPC 345 KV system. The generating technologies consist of nuclear-, coal-, gas-, and oil-fired plants. The installed capacity of different generating technologies in the committed schedule planning is shown in Table 1. The coal-fired plants, gas-fired plants, renewable power plants, and total capacity of the TPC system will increase in the future. As some nuclear plants are scheduled to be decommissioned in 2022, the capacity of nuclear power generation will decrease in the same year. The load of the TPC system in the different horizon years is shown in Table 2. All data were obtained from the TPC Power Development Planning [29]. Three cases with three different carbon taxes were analyzed to assess the feasibility of the proposed algorithm. The three cases are expressed as
  • Case 1: Minimal total cost without the total amount of CO2 emission constraints
  • Case 2: Minimal CO2 emissions
  • Case 3: Minimal total cost with the total amount of CO2 emission constraints
All case studies were analyzed with Matlab 7.3 on a 3.2 GHz Core2 computer with 4G MB RAM. The three horizon years 2012, 2017, and 2022 were used to estimate the economic dispatch of the TPC system. The carbon tax of NT$500/ton, NT$1500/ton, and NT$2500/ton were used in our study.

4.1. The Analysis of Case 1

The analysis of case 1 has three scenarios, which vary with the different carbon tax levels. The minimal total cost is an objective function, which sets the carbon taxes at 500 NT$/ton, 1500 NT$/ton, and 2500 NT$/ton without considering CO2 emission constraints. Table 3 shows the summary of the simulation results of Case 1. In 2012, when the carbon tax was set at 500 NT$/ton, the carbon emission was higher than when the carbon tax was set at 1500 NT$/ton and 2500 NT$/ton. As the capacity of coal-fired plants is expected to increase in 2022, the CO2 emissions produced will be nearly twice the emission output in 2012. The average costs are 3142.95 NT$/MW, 3665.53 NT$/MW, and 4251.42 NT$/MW if the carbon taxes are 500 NT$/ton, 1500 NT$/ton, and 2500 NT$/ton in 2012, respectively. Due to the increased cost of fuels, the average costs in 2017 and 2022 will double and triple, respectively, compared to the average cost in 2012. According to the data of the TPC [20], the average annual carbon emission in 2012 was 0.536 kg/kwh. As shown in Table 3, the results for 2012 and 2017 are close to the data of the TPC. As more coal-fired plants will commit in 2022, the average annual carbon emission will approach to 0.65 kg/kwh. The executed time of Case-1 is about 53.2 s.
Figure 2 shows the relationship between emission and time. Because nuclear plants are scheduled to be decommissioned, while coal-fired plants are added into the TPC system, the incremental emissions from 2017 to 2022 are greater than those from 2012 to 2017. Table 4 shows the generation of the various fossil fuel-fired plants. The generation of coal-fired plants decreases with a higher carbon tax, and vice versa. Table 4 shows that minimal operational costs in the different horizon years lead to the commission of more coal-fired units than gas-fired plants at a NT$500/ton carbon tax, and conversely, more gas-fired units will be committed at a NT$2500/ton carbon tax.

4.2. The Analysis of Case 2

The analysis of case 2 also has three scenarios that vary with the carbon tax. Table 5 shows the summary of the simulation results. Regardless of the amount of carbon tax, the lowest emission values are close to the same. After the new load growth and the coal-fired plants are added, the annual CO2 emissions will be approximately 82 million tons, 110 million tons, and 140 million tons in 2012, 2017, and 2022, respectively. In Taiwan, the policy target of CO2 emissions is to reduce to the power energy emission level in 2000, which was 139.1 million tons. Hence, in the next 10 years, low carbon power needs to be increased. In 2012, 2017, and 2022, the average annual CO2 emissions were 0.36 kg/kwh, 0.41 kg/kwh, and 0.44 kg/kwh, respectively. As the capacity of gas-fired plants was increased in 2017 and 2022, the average cost in 2017 and 2022 doubled or tripled compared to the average cost in 2012. The value of the average annual CO2 emissions is smaller than the data of the TPC (0.536 kg/kwh). The executed time of Case 2 is about 54.7 s.
Figure 3 shows the relationship between minimal emission and time. Because the target is to minimize emissions, the carbon emissions are very similar regardless of carbon taxes. Table 6 shows the generation of the various fossil fuel-fired plants. To reach the minimal emissions target, the system will require more gas-fired units than coal-fired plants. There is a clear relationship between carbon taxes and the generation of coal-fired plants.

4.3. The Analysis of Case 3

Table 7 shows the summary of the simulation results of case 3. As the total amount of CO2 emissions exhausted in 2022 violates the total amount of CO2 emission constraints, there are no feasible solutions in this study. After the capacity of gas-fired plants is increased to satisfy the emission constraints, the average costs are higher than the average costs in case 1. As shown in Table 7, due to the consideration of the total amount of CO2 emission constraints in case 3, the total yearly costs in the different horizon year are nearly the same for the various carbon taxes. In 2012 and 2017, the average annual CO2 emissions at the various carbon taxes, which range from 0.51 kg/kwh to 0.53 kg/kwh, are smaller than the data of the TPC (0.536 kg/kwh). The executed time of Case 3 is about 56.3 s.

5. Conclusions

Taiwan is committed to build a “nuclear-free homeland” by 2025 as a result of the Basic Environment Law. The Bureau of Energy will draft new regulations to facilitate the phasing out of Taiwan’s three existing nuclear power plants. Over the past 5 years, the average annual growth of installed power capacity was 3.1% and the average load growth was about 1.0%. Results will show that the generation deficit created by decommissioning nuclear plants can be filled by fired plants, thereby increasing both the costs and the CO2 emissions of power generation. Some government strategies for CO2 emission reduction include increases in the use of natural gas, the development of renewable energy, capacity allocation of fired plants, and the introduction of a carbon tax. Renewable power generators and their production are still in their growth and development stages in Taiwan. Furthermore, there are some unprecedented volatilities and risks involved in renewable energy development.
Because the TPC system is an isolated system unable to connect to other utilities, advancing planning and scheduling of power dispatch is an important issue. This study used an MPSO-TVAC method to analyze the feasibility assessment of the TPC system dispatch by considering CO2 emissions. To enhance the performance of the proposed algorithm, a power flow model with ECI was used to analyze the power flow of the power systems. Based on the various carbon taxes and the loads in the horizon years, a series of cost and feasibility analyses of the TPC plants were carried out. The relationship between cost and CO2 emissions was demonstrated by the simplified TPC 345 KV system. The scenarios presented in this study can assist decision-makers to achieve optimal economic dispatch and operation, and also provide an efficient power plan to meet the TPC’s CO2 emission target.

Author Contributions

W.-M.L. is the first author. He provided the project idea, related experiences, system model and revised English. C.-S.T. performed the experiments and conducted the simulations. M.-T.T. assisted the project and prepared the manuscript as the corresponding author. S.-J.L. performed the data collection and computer simulation. All authors discussed the simulation results and approved the publication. All authors have read and agreed to the published version of the manuscript.

Funding

The research was funded by the Scholar Research Funds of Xiamen University Tan Kah Kee College (JG2022SRF03 and JG2021SRF01).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

Nomenclature

T C the total production cost (NT$/h)
N the total number of generation units
F i ( P i ) the generation cost of power for the i - t h unit (NT$/h)
P i the power output of a committed unit i
F i ( P i ) = a i P i 2 + b i P i + c i the production cost of unit i
a i , b i , c i the coefficients of the production cost of unit i
E i ( P i ) the total amount of CO2 for the i - t h unit (ton/h)
T a x p r i c e the carbon tax of CO2 emission (NT$/Ton)
P l o a d _ k the total load (MW) at k - t h load bus
P i , min / P i , max the lower/upper limits of the real power of the i - t h unit (MW)
V min / V max the lower/upper limits of the voltage of the i - t h unit (0.97/1.03pu)
C O 2 _ C a p the total upper limit of CO2 emission
V i the voltage at bus i after load flow analysis
S j the line flow of j - t h branch
S j max the maximal flow of j - t h branch (1000 MW)
N B the total number of branches in the system
V i the voltage of i - t h bus
Y i j the admittance of branch i j
θ i j = θ i θ j the voltage phase angle difference between bus-i and bus-j.
c 1 f , c 2 f the initial acceleration constant; in this paper, c 1 f = 0.8   ,   c 2 f = 1.9
c 1 i , c 2 i the final acceleration constant, c 1 i = 1.88   ,   c 2 i = 0.7
i t e r max the maximal iteration
i t e r the current iteration
r a n d the uniform random value with a range of [0, 1]
P s t the position of particle s at iteration t
V s t the velocity of particle s at iteration t
p b e s t s t the own best position of particle s at iteration t
g b e s t t the best particle in the swarm at iteration t

References

  1. Intergovernmental Penal on Climate Change. Available online: https://www.ipcc.com/ (accessed on 20 July 2021).
  2. United Nations Framework Convention on Climate Change. Available online: https://unfccc.int/2860.php (accessed on 20 July 2021).
  3. Pases, C.E.; Gandelman, D.A.; Firmo, H.T.; Bahiense, L. The power generation expansion planning in Brazil: Considering the impact of greenhouse gas emissions in an Investment Decision Model. Renew. Energy 2022, 184, 225–238. [Google Scholar] [CrossRef]
  4. Kumbaroğlu, G. A sectoral decomposition analysis of Turkish CO2 emissions over 1990–2007. Energy 2011, 36, 2419–2433. [Google Scholar] [CrossRef]
  5. Wang, S.J.; Moriarty, P. Energy savings from Smart Cities: A critical analysis. Energy Procedia 2019, 158, 3271–3276. [Google Scholar] [CrossRef]
  6. Matthew, R.J.; Kumar, D.A. Evaluating long-term greenhouse gas mitigation opportunities through carbon capture, utilization, and storage in the oil sands. Energy 2020, 209, 118364. [Google Scholar]
  7. Rufael, Y.W.; Dowu, S. Income distribution and CO2 emission: A comparative analysis for China and India. Renew. Sustain. Energy Rev. 2017, 74, 1336–1345. [Google Scholar] [CrossRef]
  8. Oracio, I.; Jhon, A.; Cesar, E.; Adriana, S.R.; Arturo, A.A.; Jose, A. Solution to the Economic Emission Dispatch Problem Using Numerical Polynomial Homotopy Continuation. Energies 2020, 13, 4281. [Google Scholar]
  9. Zhou, H.; Ding, J.; Hu, Y.; Ye, Z.; Shi, S.; Sun, Y.; Zhang, Q. Economic Dispatch of Power Retailers: A Bi-Level Programming Approach via Market Clearing Price. Energies 2022, 15, 7087. [Google Scholar] [CrossRef]
  10. Osman, M.S.; Abo-Sinna, M.A.; Mousa, A.A. An ε-dominance-based multiobjective genetic algorithm for economic emission load dispatch optimization problem. Electr. Power Syst. Res. 2009, 79, 1561–1567. [Google Scholar] [CrossRef]
  11. Lai, W.; Zheng, X.; Song, Q.; Hu, F.; Tao, Q.; Chen, H. Multi-objective membrane search algorithm: A new solution for economic emission dispatch. Appl. Energy 2022, 326, 119969. [Google Scholar] [CrossRef]
  12. Sakthivel, V.P.; Suman, M.; Sathya, P.D. Combined economic and emission power dispatch problems through multi-objective squirrel search algorithm. Appl. Soft Comput. 2021, 100, 106950. [Google Scholar] [CrossRef]
  13. Chen, M.R.; Zeng, G.Q.; Lu, K.D. Constrained multi-objective population extremal optimization based economic-emission dispatch incorporating renewable energy resources. Renew. Energy 2019, 143, 277–294. [Google Scholar] [CrossRef]
  14. Li, Y.P.; Huang, G.H.; Chen, X. Planning regional energy system in association with greenhouse gas mitigation under uncertainty. Appl. Energy 2011, 88, 599–611. [Google Scholar] [CrossRef]
  15. Li, Y.F.; Li, Y.P.; Huang, G.H.; Chen, X. Energy and environmental system planning under uncertainty-an inexact fuzzy-stochastic programming approach. Appl. Energy 2010, 87, 3189–3211. [Google Scholar] [CrossRef]
  16. Özyön, S.; Temurtaş, H.; Durmuş, B.; Kuvat, G. Charged system search algorithm for emission constrained economic power dispatch problem. Energy 2012, 46, 420–430. [Google Scholar] [CrossRef]
  17. Supratik, S.B.; Anusuya, B. Multiobjective Optimization of Economic-Environmental Dispatch (EED) Problems Including CO2 Emission. In Proceedings of the 2022 International Conference for Advancement in Technology (ICONAT), Gua, India, 21–22 January 2022. [Google Scholar]
  18. Niu, Q.; Zhou, Z.; Zhang, H.Z.; Deng, J. An Improved Quantum-Behaved Particle Swarm Optimization Method for Economic Dispatch Problems with Multiple Fuel Options and Valve-Points Effects. Energies 2012, 5, 3655–3673. [Google Scholar] [CrossRef] [Green Version]
  19. Ryu, H.S.; Kim, M.K. Combined Economic Emission Dispatch with Environment-Based Demand Response Using WU-ABC Algorithm. Energies 2020, 13, 6450. [Google Scholar] [CrossRef]
  20. Taiwan Power Company. 2022. Available online: http://www.taipower.com.tw/ (accessed on 15 July 2021).
  21. Ko, L.; Chen, C.Y.; Lai, J.W.; Wang, Y.H. Abatement cost analysis in CO2 emission reduction costs regarding the supply-side policies for the Taiwan power sector. Energy Policy 2013, 61, 551–561. [Google Scholar] [CrossRef]
  22. Ko, F.K.; Huang, C.B.; Tseng, P.Y.; Lin, C.H.; Zheng, B.Y.; Chiu, H.M. Long-term CO2 emissions reduction target and scenarios of power sector in Taiwan. Energy Policy 2010, 38, 288–300. [Google Scholar] [CrossRef]
  23. Nourianfar, H.; Abdi, H. Solving the multi-objective economic emission dispatch problems using Fast Non-Dominated Sorting TVAC-PSO combined with EMA. Appl. Soft Comput. 2019, 85, 105770. [Google Scholar] [CrossRef]
  24. Hadji, B.; Mahdad, B.; Srairi, K.; Mancer, N. Multi-objective PSO-TVAC for Environmental/Economic Dispatch Problem. Energy Procedia 2015, 74, 102–111. [Google Scholar] [CrossRef] [Green Version]
  25. Sheen, J.N.; Tsai, M.T.; Wu, S.W. A benefits analysis for wind turbine allocation in a power distribution system. Energy Convers. Manag. 2013, 68, 305–312. [Google Scholar] [CrossRef]
  26. Lin, S.J. Feasibility Assessment of Carbon Emission Cap for Power Dispatch in Taiwan. Master’s Thesis, Nation Sun Yat-Sen University, Kaohsiung, Taiwan, 2013. [Google Scholar]
  27. Chen, T.H.; Chen, M.S.; Hwano, K.J.; Kotas, P.; Chenli, E.A. Distribution system power flow analysis-a grid approach. IEEE Trans. Power Deliv. 1981, 6, 1146–1152. [Google Scholar] [CrossRef]
  28. Bhattacharyya, B.; Raj, S. PSO based bio inspired algorithms for reactive power planning. Int. J. Electr. Power Energy Syst. 2016, 74, 396–402. [Google Scholar] [CrossRef]
  29. Taiwan Power Company. The Sustainable Operation of White Paper for Taiwan Power Company; Taiwan Power Company: Taipei, Taiwan, 2020. [Google Scholar]
Figure 1. Flowchart of the proposed methodology.
Figure 1. Flowchart of the proposed methodology.
Processes 10 02321 g001
Figure 2. The relationship between emissions and time in the analysis of Case 1.
Figure 2. The relationship between emissions and time in the analysis of Case 1.
Processes 10 02321 g002
Figure 3. The relationship between emissions and time in the analysis of Case 2.
Figure 3. The relationship between emissions and time in the analysis of Case 2.
Processes 10 02321 g003
Table 1. The capacity of different generation types in the TPC system.
Table 1. The capacity of different generation types in the TPC system.
TypeCoalOilGasNuclearRenewable PowerTotal (MVA)
Year
Capacity
(MVA)
201212,637.2275015,2035144271238,446.2
201714,237.2275016,1335144282441,088.2
202220,837.2275024,634.54602426457,087.7
Table 2. The load of the TPC system in different horizon years.
Table 2. The load of the TPC system in different horizon years.
Load StatusPeak Load of YearAverage Load of YearOff-Peak Load of Year
Year
Load
(MW)
201233,92724,81615,706
201740,26329,45118,337
202247,03334,40320,465
Table 3. The summary of the simulation results of Case 1.
Table 3. The summary of the simulation results of Case 1.
Horizon Year 2012
Carbon Tax Peak Load of YearAverage Load of YearOff-Peak Load of YearTotal of One YearAverage
500 NT$/tonCost(NT$)136,452,44673,822,30441,327,484713,713,197,9453142.95 NT$/MW
Emission18,997 ton14,349 ton4714 ton121,181,245 ton0.53 kg/kwh
1500 NT$/tonCost(NT$)150,614,56289,076,05946,494,151832,169,107,7283665.53 NT$/MW
Emission18,643 ton14,030 ton4714 ton118,744,464 ton0.52 kg/kwh
2500 NT$/tonCost(NT$)172,235,055104,020,82251,236,443961,375,061,5574251.42 NT$/MW
Emission18,831 ton13,500 ton4634 ton115,948,849 ton0.51 kg/kwh
Horizon year 2017
Carbon tax Peak load of yearAverage load of yearOff-peak load of yearTotal of one yearAverage
500 NT$/tonCost(NT$)291,992,877166,171,77482,239,6281,565,816,472,2625839.18 NT$/MW
Emission22,795 ton17,3497060 ton147,997,680 ton0.55 kg/kwh
1500 NT$/tonCost(NT$)315,083,938183,244,93891,535,1791,715,700,961,2506395.39 NT$/MW
Emission22,755 ton16,895 ton7249 ton145,591,889 ton0.54 kg/kwh
2500 NT$/tonCost(NT$)344,727,851210,355,403103,532,1541,868,646,826,3636954.14 NT$/MW
Emission22,899 ton15,805 ton6802 ton143,753,562 ton0.53 kg/kwh
Horizon year 2022
Carbon tax Peak load of yearAverage load of yearOff-peak load of yearTotal of one yearAverage
500 NT$/tonCost(NT$)559,436,600332,369,666158,359,7233,080,730,478,5679798.19 NT$/MW
Emission29,718 ton24,620 ton9929 ton205,297,648 ton0.65 kg/kwh
1500 NT$/tonCost(NT$)583,498,540358,510,171145,496,3623,254,828,575,28710,436.28 NT$/MW
Emission29,606 ton24,449 ton8496 ton202,243,434 ton0.65 kg/kwh
2500 NT$/tonCost(NT$)607,219,762406,551,480159,594,6393,588,460,506,08411,514.25 NT$/MW
Emission29,469 ton23,010 ton8785 ton194,192,570 ton0.62 kg/kwh
Table 4. The generation of plants among the various fossil-fired plants in case 1.
Table 4. The generation of plants among the various fossil-fired plants in case 1.
The Generation of Plants in 2012
Carbon Tax (NT$/ton)Coal-Fired (MW)Oil-Fired (MW)Gas-Fired (MW)
50011,064.74449.356474.18
150010,757.12246.746903.38
250010,226.81377.497178.99
The generation of plants in 2017
Carbon tax (NT$/ton)Coal-fired (MW)Oil-fired (MW)Gas-fired (MW)
50012,944.13710.258730.28
150012,532.66732.079020.22
250010,945.831158.5410,268.35
The generation of plants in 2022
Carbon tax (NT$/ton)Coal-fired (MW)Oil-fired (MW)Gas-fired (MW)
50019,420.63512.067888.85
150018,936.22377.368168.05
250017,129.18759.809612.13
Table 5. The summary of the simulation results of Case 2.
Table 5. The summary of the simulation results of Case 2.
Horizon Year 2012
Carbon Tax Peak Load of YearAverage Load of YearOff-Peak Load of YearTotal of One YearAverage
500 NT$/tonCost
(NT$)
153,874,048102,692,25943,334,881911,259,092,2513987.67 NT$/MW
Emission16,860 ton8314 ton4183 ton82,376,890 ton0.36 kg/kwh
1500 NT$/tonCost
(NT$)
171,617,829111,440,76148,116,210998,442,831,7674369.32 NT$/MW
Emission16,775 ton8313 ton4186 ton82,226,839 ton0.36 kg/kwh
2500 NT$/tonCost
(NT$)
188,582,058119,134,79052,952,0881,078,328,301,3124722.17 NT$/MW
Emission16,879 ton8251 ton4230 ton82,111,087 ton0.36 kg/kwh
Horizon year 2017
Carbon tax Peak load of yearAverage load of yearOff-peak load of yearTotal of one yearAverage
500 NT$/tonCost
(NT$)
295,808,850225,227,22293,564,9131,923,645,203,2117149.72 NT$/MW
Emission22,513 ton11,454 ton5263 ton111,575,762 ton0.41 kg/kwh
1500 NT$/tonCost
(NT$)
318,221,540236,888,584101,241,2882,039,398,788,4027605.25 NT$/MW
Emission22,464 ton11,312 ton5333 ton110,774,201 ton0.41 kg/kwh
2500 NT$/tonCost
(NT$)
342,560,588247,064,302108,146,8652,149,055,264,8137980.42 NT$/MW
Emission22,581 ton11,135 ton5411 ton110,073,596 ton0.41
Horizon year 2022
Carbon tax Peak load of yearAverage load of yearOff-peak load of yearThe total of one yearAverage
500 NT$/tonCost
(NT$)
632,318,823514,811,623205,315,0414,308,943,921,21713,534.66 NT$/MW
Emission26,439 ton14,951 ton6993 ton140,638,787 ton0.44 kg/kwh
1500 NT$/tonCost
(NT$)
658,896,295537,733,865209,411,6154,491,409,799,49814,142.42 NT$/MW
Emission26,421 ton14,995 ton7034 ton140,915,036 ton0.44 kg/kwh
2500 NT$/tonCost
(NT$)
685,741,249528,474,256218,453,5934,497,599,103,86014,115.03 NT$/MW
Emission26,380 ton14,919 ton7030 ton140,400,596 ton0.446 kg/kwh
Table 6. The generation of plants among the various fossil-fired plants in case 2.
Table 6. The generation of plants among the various fossil-fired plants in case 2.
The Generation of Plants in 2012
Carbon Tax (NT$/ton)Coal-Fired (MW)Oil-Fired (MW)Gas-Fired (MW)
5003312.48767.0413,834.22
15003280.56773.1113,858.82
25003315.39768.8913,753.46
The generation of plants in 2017
Carbon tax (NT$/ton)Coal-fired (MW)Oil-fired (MW)Gas-fired (MW)
5004854.262434.0915,063.41
15004730.202421.7815,163.53
25004619.852248.0815,539.96
The generation of plants in 2022
Carbon tax (NT$/ton)Coal-fired (MW)Oil-fired (MW)Gas-fired (MW)
5005454.502161.8820,633.52
15006249.021304.1121,649.37
25005739.401461.2721,093.25
Table 7. The summary of the simulation results of Case 3.
Table 7. The summary of the simulation results of Case 3.
Horizon Year 2012
CARBON TAX Peak Load of YearAverage Load of YearOff-Peak Load of YearTotal of One YearAverage
500 NT$/tonCost
(NT$)
142,554,09574,897,39441,898,689731,275,414,5333201.41 NT$/MW
Emission19,529 ton14,291 ton4886 ton122,008,876 ton0.53 kg/kwh
1500 NT$/tonCost
(NT$)
158,309,49189,743,76747,834,002851,213,119,0903734.95 NT$/MW
Emission18,573 ton14,159 ton4852 ton119,537,619 ton0.52 kg/kwh
2500 NT$/tonCos
t(NT$)
177,904,341105,406,05252,559,934980,934,218,9114313.99 NT$/MW
Emission19,012 ton13,505 ton4872 ton116,607,114 ton0.51 kg/kwh
Horizon year 2017
Carbon tax Peak load of yearAverage load of yearOff-peak load of yearTotal of one yearAverage
500 NT$/tonCost
(NT$)
298,218,408175,992,02593,730,5961,647,739,242,3516122.63 NT$/MW
Emission22,930 ton15,805 ton6314 ton138,463,166 ton0.51 kg/kwh
1500 NT$/tonCost
(NT$)
316,656,495189,385,40695,349,3801,758,431,764,8816543.57 NT$/MW
Emission22,707 ton15,836 ton6843 ton138,942,356 ton0.52 kg/kwh
2500 NT$/tonCost
(NT$)
343,532,347205,252,405104,528,4201,907,926,211,9857088.90 NT$/MW
Emission22,940 ton15,767 ton6731 ton138,815,337 ton0.52 kg/kwh
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Lin, W.-M.; Tu, C.-S.; Lin, S.-J.; Tsai, M.-T. The Feasibility Assessment of Power System Dispatch with Carbon Tax Considerations. Processes 2022, 10, 2321. https://doi.org/10.3390/pr10112321

AMA Style

Lin W-M, Tu C-S, Lin S-J, Tsai M-T. The Feasibility Assessment of Power System Dispatch with Carbon Tax Considerations. Processes. 2022; 10(11):2321. https://doi.org/10.3390/pr10112321

Chicago/Turabian Style

Lin, Whei-Min, Chia-Sheng Tu, Sang-Jyh Lin, and Ming-Tang Tsai. 2022. "The Feasibility Assessment of Power System Dispatch with Carbon Tax Considerations" Processes 10, no. 11: 2321. https://doi.org/10.3390/pr10112321

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop