1. Introduction
With the rapid development of the economy and the continuous improvement of residents’ living standards, consumers’ requirements for power demand, power quality and power supply reliability are constantly improving. On the other hand, with the increasing frequency of extreme weather such as typhoons, hail and thunderstorms, extreme weather brings great risks to the safe operation of a power grid [
1]. Many failures caused by extreme weather have brought great economic losses to the power grid all over the world. For example, in 2005, Typhoon Davy brought a heavy blow to the Hainan power grid, causing nearly one hundred 110 kV lines to trip [
2].In 2008, severe snow and ice disasters occurred in China, more than 2000 substations were shut down, more than 8500 power poles and towers collapsed, and residents in more than 170 cities experienced power outage losses [
3]. Typhoon Sandy in 2012 afflicted New York and Caused 85% of residents to lose power [
4].
In order to improve the resistance of power systems to extreme weather, long-term planning and short-term dispatch of power systems should be carried out before extreme weather occurs [
5]. In previous studies, the planning method refers to reinforcing the infrastructure in the power system with stronger materials or improving the strength of the system by physical means [
6], including vegetation management, equipment installation and line reinforcement [
7]. However, the planning method generally has a long time cycle and needs a lot of economic costs. The short-term dispatch method refers to improving the operating characteristics of power systems under extreme weather by scheduling resources such as generators in power systems. Dispatch methods include topology transformation, generator dispatching, protection control, state perception and so on. These measures are active, real-time and low economic cost. They are common ways used in power systems to resist extreme weather. Different from a large main network, the voltage level of a distribution network is relatively low, the strength of poles, towers, lines and other components is not high, and the resistance ability to extreme weather is poor. In fact, 80–90% of power system outages are related to distribution networks [
8]. Therefore, it is necessary to make the dispatch plan of the distribution network in advance to resist the negative impact of extreme weather and reduce the economic loss caused by load shedding.
As shown in
Figure 1, with the development of weather forecasting and monitoring technology, the power system operators can get the specific information of typhoon login several days in advance, and create conditions for the dispatch of a distribution network in advance. Many scholars have studied the pre-dispatch strategy of distribution networks and have achieved remarkable results. Literature [
9] proposed a switching dispatch scheme in advance, which sorts lines with possible faults in the distribution network according to the fault probability and disconnects them in advance so that all loads can ensure work in normal operation and the distribution network operates in a low-risk state. Literature [
10] establishes a pre-dispatch model for switches and distributed generation in a microgrid. This model takes the most serious line failure scenarios into account. The case analysis shows that the pre-dispatch strategy can effectively reduce the load loss of a distribution network under extreme weather conditions. Literature [
11] considers the random fault scenario of a distribution network under extreme weather and aims at minimizing the system load shedding amount, thus establishing a novel component repairer scheduling model.
In addition, the differences in regional economic development and natural conditions cause the unbalanced development of automation of distribution networks in China [
12]. In particular, China’s rural power grid has a large area and scattered load, which brings inconvenience to adopt the latest automation and communication technology [
13], even some rural power grids still have not adopted automation technology. Since it is impossible to manually operate the equipment in the distribution network that does not adopt automation technology [
14] during the process of extreme weather, the distribution network cannot remotely operate the equipment to quickly isolate the fault, and also lacks the ability to respond to the fault state of components in real-time, so it is more vulnerable to cause load shedding [
15]. A reasonable pre-dispatch strategy will help reduce its economic loss under extreme weather conditions. However, there is little research on the pre-dispatch strategy for the distribution network without automation technology.
Based on the above analysis, this paper proposes a pre-dispatch model for distribution networks to deal with typhoon weather based on line fault consequence analysis. The remainder of this paper is as follows: firstly, based on the vulnerability curves of lines and towers under typhoon weather, the random fault probability of lines can be calculated, and the line fault scenario is generated by Monte Carlo simulation. Then, according to the fault location, the distribution network is partitioned according to the location of the switch, and the block breaker correlation matrix is established. The breaker trip identification vector is designed to characterize the whole trip process. Combined with the line fault state, a fault consequence model of lines, which is related to the pre-dispatch strategy, is established. Finally, based on the model above and the line fault scenario generation method, a pre-dispatch model for distribution network to cope with typhoon weather is established. The model mainly changes the state of the switch in the distribution network before a typhoon lands and modifies the network topology to reduce the possible influence of Typhoon wind on the distribution network. In essence, the model is a two-stage stochastic optimization model, which is solved by the progressive hedging (PH) algorithm in this paper.
The innovation of this article can be summarized as follows:
- (1)
Firstly, previous studies mainly focused on the power grid with a high degree of automation. However, some regions in China still need field operations. When the typhoon comes, it poses a potential threat to the security operation of China. To overcome this challenge, a novel pre-dispatch model for the system without automation is established in this paper.
- (2)
From the perspective of the model and algorithm, the pre-dispatch model is a mixed-integer linear programming problem. A traditional solving method such as the Benders Decomposition method is not suited for the model in this paper, because many scenarios are randomly generated. Therefore, PH (Progressive Hedging) algorithm is adopted in this paper to reduce the computational complexity and improve computational efficiency.
2. Generation of Line Fault Scenario under Typhoon Weather
In the pre-dispatch model of the distribution network, typhoons have not yet occurred. However, the impact of the upcoming Typhoon on the distribution network needs to be considered, that is, the randomness of component faults in the distribution network under extreme weather conditions. In this section, line faults under extreme weather are regarded as independent random events and the line fault scenarios are extracted by the Monte Carlo simulation method based on the fault probability.
Figure 2 shows a typical distribution network component vulnerability curve. As shown in
Figure 2, the fault probability of lines or towers in distribution networks is influenced by wind speed. When the typhoon is coming, the fault scenarios of lines and towers can be obtained. To reduce the complexity of computation, we used the Monte Carlo simulation method to choose these scenarios.
According to the literature [
16,
17], when the wind speed in the next few hours can be predicted or measured, the failure probability of lines or towers can be seen as a function of wind speed, and the relationship curve between failure probability and wind speed is called the component vulnerability curve of distribution network.
Assuming that the predicted wind speed at time
t is
vt, the failure probability of tower on line
ij at time
t is the function
Pij,Tower (
vt) of wind speed
vt, and the failure probability of line
ij is
Pij,C (
vt). The failure probability of a single tower or line can be obtained from the vulnerability curve of the distribution network in
Figure 2.
It is assumed that there are
Nij,T towers between line
i and line
j, then the relationship between
Pij,Tower (
vt) and
Pij,T (
vt) is shown as Equation (1).
The fault of the tower or line will lead to a line fault between two nodes. Therefore, the line fault probability
Pij,L (
vt) between nodes
ij is shown as Equation (2):
Due to the large number of lines in the distribution network, there are many scenarios in which line faults may occur under extreme weather. In order to reduce the scenarios and speed up the calculation, this paper sets the failure rate threshold to screen the fragile lines. When the failure probability of the line exceeds the threshold, the line is considered a fragile line. If the threshold is not exceeded, the line is considered to be a stronger line and will not break down.
Suppose the typhoon weather event happens in the time period from
t1 to
t2, and the predicted wind speed is
vt. According to the above calculation method of line fault probability, that is, Equations (1) and (2), the fault probability
Pij,L (
vt) between line
i and line
j can be obtained. Suppose the fault probability threshold of a fragile line as
Pstep and
fij,t as the sign of fragile line. Then for any line
ij, the following Equation (3) is satisfied.
The set of all lines whose the value of fij,t are equal to 1 is the system fragile line set ΩLf. Suppose that there are NLf elements in the set in total, that is, there are NLf fragile lines in the distribution network that may occur failure, and each fragile line ij may occur failure in the period from t1 to t2.
For scenario
s, a random number
τij,t,s ∈ [0, 1] is extracted for the fragile line
ij ∈ Ω
Lf. Then, when the value of
τij,t,s is smaller than the line fault probability
Pij,L (
vt), the line will break down, and the value of line fault state
uij,t,s is 1. When the value of
τij,t,s is larger than or equal to the line fault probability
Pij,L (
vt), the line will not fail and can operate normally, and the value of line fault state
uij,t,s is 0. The detailed mathematical expression is shown in (4):
For the fragile line
ij ∈ Ω
Lf that has failed at the last time, the fault state of the line remains unchanged because the line cannot be repaired within the duration of extreme weather:
Since the faults of different lines are independent events, the fault status of each fragile line can be sampled one by one, and then the results are aggregated. Once a line fails at a certain time through sampling, because the line cannot be repaired during a typhoon, it will always maintain the fault state in the remaining time, that is, there is no need to sample to determine the fault state at the subsequent time. If the sampling results find that the line works normally in the whole typhoon period, consider the next line until the fault status of all lines has been determined, and the sampling process of one scenario is completed.
5. Case Study
5.1. Introduction of Test System
The dispatch model in
Section 4 is applied to the IEEE-69 node system. The topology of the IEEE-69 node system is shown in
Figure 6. The total load of the system is 6.715 MW, and the node load of the system can be referred to [
23]. According to Ref. [
24], the typical day in summer is selected to expand the node load by the hour. Basis capacity is
Sbase = 100 MW, and basis voltage is
Vbase = 12.66 kV. The upper and lower limits of node voltage amplitude are 1.05 p.u. and 0.95 p.u., respectively. The switching cost of the pre-dispatch operation is 1000
$/times, and the power outage loss is 10
$/kWh when the event occurs. According to the literature [
25,
26], the penalty coefficient of the PH algorithm is set to 1000, and the convergence threshold
ε is 0.0001.
Set the duration of extreme weather events as 7 h, from 9 a.m. to 4 p.m. According to the predicted wind speed and the vulnerability curve of distribution lines in
Figure 2, set the failure rate threshold
Pstep of vulnerable lines as 0.05, and get that the vulnerable lines of the system are lines 7–8, 9–10, 12–13 and 13–14.
5.2. Analysis of Pre-Dispatch Results
The two-stage stochastic dispatch model is solved by MATLAB 2018a, using a desktop computer with Intel 5th processor and 8 G memory. The solution program is written in the Yalmip language and solved through solver Cplex 12.4. The solution time is 2395 s, and the PH algorithm converges after 12 iterations.
Next, we compare the two dispatch strategies of distribution networks to illustrate the effectiveness of the pre-dispatch model proposed in this paper.
Strategy 1: the distribution network maintains normal operation in advance;
Strategy 2: in advance, the distribution network implements the pre-dispatch strategy proposed in this paper.
The economic cost of the distribution grid under the two dispatching strategies is compared and analyzed, and the results are shown in
Table 1.
When Strategy 1 is adopted, the cost of dispatch in advance was 0, but there was a large power outage loss of $130,362.85. This is because the distribution network has not been regulated in advance, and the distribution network operates in a high-risk state. Therefore, the consequences of line failure are serious and the loss of power failure is high. When the pre-dispatch strategy 2 is adopted, three switch actions occurred, each switching operation cost was $1000, and the cost of pre-dispatch switch was $3000. After this switch operation, the distribution network operates in a low-risk state, the fault influence range of the distribution line is small, the power failure loss is reduced. By comparing the results of strategy-1 and strategy-2, we can see that a certain dispatch cost of $3000 is needed before a typhoon occurs, but the power outage loss in dispatch is reduced by $6397.09.
As shown in
Table 2 above, there is no line fault in the distribution network from time 1 to 3, and the pre-dispatch strategy-2 has a smaller load shedding amount of about 0.26 MW. After line 12–13 failure, the fault consequence of the pre-dispatch strategy-2 is small, so the load shedding amount from time 4 to time 5 is far less than the strategy-1. The sum of load shedding amount using strategy 1 under this scenario is 13.56 MWh. The load shedding amount using strategy-2 is 10.29 MWh, which reduces 3.27 MWh compared with strategy 1 in advance. It illustrates the feasibility and effectiveness of adopting the pre-dispatch strategy 2 under this scenario.
Based on the above analysis, for the distribution network without automatic access, the switching state of switchgear can be adjusted before extreme weather occurs, and the topology can be changed to the state with fewer fault consequences. This pre-dispatch method is able to use less pre-dispatch costs instead of large amounts of losses caused by extreme weather, which is technically and economically feasible.
6. Conclusions
In view of the lack of researches on the pre-dispatch of distribution networks, this paper establishes a fault consequence model of distribution lines based on block breaker correlation matrix and circuit breaker trip identifier. Combined with the line fault scenario generation method, a pre-dispatch model of distribution network considering the consequences of random failure is proposed, and the PH algorithm is used to solve the two-stage stochastic optimization model. The following conclusions are obtained from the research on the IEEE-69 node system. The proposed method can effectively reduce the adverse effects and economic losses caused by extreme weather represented by a typhoon, and improve the resilience of the power grid. The model solving method based on the PH algorithm has good convergence and robustness and meets the requirements of online calculation in practical application.
In the future, the following points can be further studied. Firstly, the action mechanism, evolution process and uncertainty modeling of extreme weather such as typhoons and icing will be carried out in the future. Secondly, for the power system with automation access, how to consider communication delay and congestion in the practical application is still a difficult problem. Last but not the least, when the towers and lines in the distribution networks operate in an abnormal state, maintenance personnel should consider the dynamic characteristics of the traffic network, thus reducing economic loss.