1. Introduction
In the modern world, electric power systems (EPS) are exposed to partial or complete blackout due to human-facilitated or disastrous natural events. The EPS is prone to large-scale disruptions due to interconnection, renewable resource integration, and network complexity, resulting in the interruption of the market environment and significant socio-economic losses. One of the most extensive blackouts in the history of Pakistan halted the power industry, affecting nearly 200 million people in January 2021 [
1]. In recent years, natural calamities have also drastically influenced the global power industry, such as blackout in America (2021) and Australia (2021), which threatened the lives of people in America (10 million) and Australia (0.52 million) [
2,
3], respectively.
To mitigate the repercussions of disruptions in the power system, the world is experiencing a paradigm shift towards a more efficient, adaptable, and flexible approach to restoring the power system. Therefore, various heuristic algorithms are used to optimize the power system restoration. After a blackout, the Tabu Search algorithm is used to restore the cold load pickup (CLPU) to minimize the restoration time and prevent another outage [
4]. Discrete particle swarm optimization is used to restore the CLPU by reducing the total power consumption and dividing the system into sections [
5]. In [
6], topology analysis and genetic algorithm are used to determine intentional islanding, keeping power balance and transmission constraint in bounds. In [
7], FICO Xpress Optimizer is used to allocate the BS unit in the grid. Grid parameters are also included, such as generator model, nodal balance, voltage and power limits. A recent literature review is also provided in
Table 1.
In this paper, the optimal generation start-up sequence is optimized. The critical load is restored on a priority basis. A multi-objective genetic algorithm selects the shortest transmission path to energize the non-black start units and maximize overall generation with minimum restoration time. Maximum load is restored, and islands are synchronized to expedite the whole restoration process.
2. Post Fault Restoration
Power system restoration following a power outage poses many challenges for system planners and engineers as it includes a broad spectrum of independent entities, such as generation, transmission, and distribution owners. After a power outage, a grid-independent source is required to rejuvenate the power system to normal condition. A grid-independent and autonomous generating unit that does not rely on an external source is called a black start unit. Black start units deliver the cranking power to the non-black start unit, and optimal load restored is required to keep the grid parameter within permissible limits.
After a partial or complete power disruption, restoration of EPS is segregated into 3 stages: system preparation, system rejuvenation and load restoration. The system restoration stage consists of black start preparation, system status determination and network determination. The system restoration stage consists of transmission line energization, critical load pickup, cranking power to NBS units and synchronization of the island. The load restoration stage consists of minimizing the unserved load [
11]. Black start is necessary to respond to the blackout, to reinvigorate the system to its normal state in minimum restoration time.
3. Problem Formulation and Mathematical Modelling
Efficient and corrective steps need to be considered to avoid cascading power outages. The occurrence of blackouts is rare, but their impact is high. In order to avoid repercussions of power outage, following factors should be taken into account:
Maximizing the overall generation capability in minimum restoration time;
Optimal transmission path is selected to rejuvenate the NBSUs;
Minimum number of transmission switching is performed to restore the system.
These goals are achieved by using a genetic algorithm. The survival of the fittest remained the ultimate goal [
12].
3.1. MWH Capability Enhancement
The main focus is to maximize the overall MWh capability of the power system during the restoration process.
Esys is the total MW capability,
Eigen is the power of
ith generator,
Ejstart is the starting-up demand of the Non-black start
jth generator.
3.2. Constraint Power Requirement
Generation capability of unit
i minus the start-up power of NBS must not be equal to zero.
Pigen is the power requirement of unit
i, and
Pjstart(t) is the start-up power requirement of NBS unit
j.
3.3. Critical Time Interval Limits
NBSU
j will start within the critical minimum and maximum time interval.
is critical minimum interval constraint of NBSU
j,
is critical maximum interval of NBSU
j.
is the starting time of NBSU
j.
3.4. Energization of the Connected Bus Will Energize the Line and Vice Versa
If both the connected busses are energized or deenergized the corresponding line is energized or deenergized
ubusnt,
ulinemnt are decision variables of bus and line, Ω
t, Ω
line and, Ω
bus are set of time, line and buses number.
3.5. If Connected Buses/Line Is Rejuvenated, Then They Will Not Turn-Off Again
At any time interval if the bus or line is energized, that bus or line will not be deenergized again.
is a binary decision variable of line mn at time
t.
is decision variable of bus mn at time t. 0 means that line or bus is not energized and 1 means line or bus is energize at time
t. Ω
t = 1,…., T, Ω
t − 1 = 1, …, T − 1, and Ω
t − 2 = 2, …, T are sets of time.
3.6. Initially, the Line and Bus of the Black Start Unit Are Just Connected
Intially. All the line and buses are de-energized except the line and bus connected with the black start unit.
is set of line numbers, equal to 1…… N
line.
is the set of busses connected with black start unit.
is the set of bus number that is equal to 1…N
Bus.
is the binary decision variable of bus m at time t.
is the set of binary decision variable of line mn at time t.
is the binary decision variable of bus m at time t.
3.7. Non-Black Start Unit Is Energized after the Energization of Its Connected Bus
The NBSU will start after the connected bus is energized.
is the binary decision variable of bus
m at time
t.
is the set of busses connected with non-black start unit.
is the set of non-black start unit that is equal to 1…N
BSU is the set of time that is equal to 1…T.
4. Case Study
The IEEE-39 benchmark system is utilized to validate the effectiveness of the proposed algorithm. IEEE 39 bus system data is taken from [
8]. It includes 46 branches, 39 buses and ten generators. Among ten generators, there are 3 BS units and 8 NBS units. The scenario of complete blackout is considered. The BSU (G1) is located at bus 30 in Island 1. The BSU (G2) is located at bus 31 in Island 2. The BSU (G6) is located at bus 35 in Island 1. Non-black start units in Island 1 are G8, G9, and G10. NBSU in Island 2 is G3. NBSUs in Island 3 are G4, G5, and G7. The proposed model is solved in MATLAB R2018a on a laptop with an Intel i7-10510U processor and 8 GB RAM.
5. Results and Discussion
In this paper, each island has at least one black start unit; three islands were created [
13]. Loads on each bus were restored in minimum time. The status of each generator is shown in
Table 2. In Island 1, the black start unit (G1) is placed at bus 30, G2 is placed at bus 31 in Island 2 and G6 is placed at bus 35 in Island 3. Each black start unit restore other’s NBSUs in their vicinity, as shown in
Table 3. Loads are gradually connected to avoid the voltage dip or frequency drop. Total restoration time is 36 min, and prioritized load is energized at first. G5 is restored on priority basis in Island 3. The optimal transmission path from BSU to NBSUs in each island is shown in
Figure 1a. After 36 min of restoration process, total the MW capability restored is shown in
Figure 1b. The total restoration time is minimized because of the optimal generator start-up sequence, the optimal transmission path search and the resynchronization of three islands.
6. Conclusions
Parallel power system restoration using the multi-objective Genetic algorithm is proposed. The optimal start-up sequence of generating units has further minimized the overall restoration time. The path that requires the minimum switching actions is considered the optimal transmission path. Three islands are created, and each island has one black-start unit that transfers the cranking power to other NBSU. The shortest transmission line path using a genetic algorithm has enhanced the restoration time. The overall combination of the optimal start-up sequence of the generating unit, the optimal transmission line path search and synchronization of the island has improved the efficiency of the proposed algorithm.
Author Contributions
Conceptualization, S.U.A. and M.N.; methodology, S.U.A.; software, S.U.A.; validation, S.U.A., M.N. and N.A.; formal analysis, S.U.A.; investigation, S.U.A.; resources, S.U.A.; data curation, S.U.A., H.F. and Z.U.H.; writing—original draft preparation, S.U.A.; writing—review and editing, S.U.A., N.A., H.F. and Z.U.H.; supervision, M.N. All authors have read and agreed to the published version of the manuscript.
Funding
This research received no external funding.
Institutional Review Board Statement
Not applicable.
Informed Consent Statement
Not applicable.
Data Availability Statement
Not applicable.
Conflicts of Interest
The authors declare no conflict of interest.
References
- Zhu, Y.; Zhou, Y.; Wang, Z.; Zhou, C.; Gao, B. A terminal distribution network black-start optimization method based on pruning algorithm considering distributed generators. Energy Rep. 2021, 8, 237–244. [Google Scholar] [CrossRef]
- Busby, J.W.; Baker, K.; Bazilian, M.D.; Gilbert, A.Q.; Grubert, E.; Rai, V.; Rhodes, J.D.; Shidore, S.; Smith, C.A.; Webber, M.E. Cascading risks: Understanding the 2021 winter blackout in Texas. Energy Res. Soc. Sci. 2021, 77, 102106. [Google Scholar] [CrossRef]
- Lyster, R.; Verchick, R.R.J.F.i.C. Building a Climate-Resilient Power Grid: Lessons from Texas-Size Storms and the Queensland Floods. Front. Clim. 2021, 3, 734227. [Google Scholar] [CrossRef]
- Widiputra, V.; Jung, J. Development of restoration algorithm under cold load pickup condition using tabu search in distribution system. In Proceedings of the 2018 IEEE Power & Energy Society General Meeting (PESGM), Portland, OR, USA, 5–10 August 2018; pp. 1–5. [Google Scholar]
- Widiputra, V.; Jufri, F.H.; Jung, J. Development of service restoration algorithm under cold load pickup condition using conservation voltage reduction and particle swarm optimization. Int. Trans. Electr. Energy Syst. 2020, 30, e12544. [Google Scholar] [CrossRef]
- Wu, Y.; Tang, Y.; Han, B.; Ni, M.; Systems, E. A topology analysis and genetic algorithm combined approach for power network intentional islanding. Int. J. Electr. Power Energy Syst. 2015, 71, 174–183. [Google Scholar] [CrossRef]
- Patsakis, G.; Rajan, D.; Aravena, I.; Rios, J.; Oren, S. Optimal Black Start Allocation for Power System Restoration. IEEE Trans. Power Syst. 2018, 33, 6766–6776. [Google Scholar] [CrossRef]
- Qiu, F.; Wang, J.; Chen, C.; Tong, J. Optimal Black Start Resource Allocation. IEEE Trans. Power Syst. 2016, 31, 2493–2494. [Google Scholar] [CrossRef]
- Patsakis, G.; Rajan, D.; Aravena, I.; Oren, S. Strong mixed-integer formulations for power system islanding and restoration. IEEE Trans. Power Syst. 2019, 34, 4880–4888. [Google Scholar] [CrossRef]
- Zhao, J.; Zhang, Q.; Ziwen, L.; Xiaokang, W. A distributed black-start optimization method for global transmission and distribution network. IEEE Trans. Power Syst. 2021, 36, 4471–4481. [Google Scholar] [CrossRef]
- Sun, K.; Hou, Y.; Sun, W.; Qi, J. Power System Control under Cascading Failures: Understanding, Mitigation, and System Restoration; John Wiley & Sons: Hoboken, NJ, USA, 2019. [Google Scholar]
- El-Werfelli, M.; Dunn, R.; Iravani, P. Backbone-network reconfiguration for power system restoration using genetic algorithm and expert system. In Proceedings of the 2009 International Conference on Sustainable Power Generation and Supply, Nanjing, China, 6–7 April 2009; pp. 1–6. [Google Scholar]
- Pirzadi, M.; Ghadimi, A.A.; Daeichian, A.J.E.P.S.R. Distributed multi-agent transmission system restoration using dynamic programming in an uncertain environment. Electr. Power Syst. Res. 2021, 196, 107270. [Google Scholar] [CrossRef]
| Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).