Next Article in Journal
Consumption Preferences for Truffles and Truffle-Based Products: An Application of the PLS-SEM Model
Previous Article in Journal
Health Effects of Participation in Creating Urban Green Spaces—A Systematic Review
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Flash Flood Simulation for Hilly Reservoirs Considering Upstream Reservoirs—A Case Study of Moushan Reservoir

1
School of Civil Engineering, Shandong University, Jinan 250061, China
2
Department of Water Resources, China Institute of Water Resources and Hydropower Research, Beijing 100038, China
*
Author to whom correspondence should be addressed.
Sustainability 2024, 16(12), 5001; https://doi.org/10.3390/su16125001
Submission received: 7 April 2024 / Revised: 2 June 2024 / Accepted: 4 June 2024 / Published: 12 June 2024

Abstract

:
With the advancement of society and the impact of various factors such as climate change, surface conditions, and human activities, there has been a significant increase in the frequency of extreme rainfall events, leading to substantial losses from flood disasters. The presence of numerous small and medium-sized water conservancy projects in the basin plays a crucial role in influencing runoff production and rainwater confluence. However, due to the lack of extensive historical hydrological data for simulation purposes, it is challenging to accurately predict floods in the basin. Therefore, there is a growing emphasis on flood simulation and forecasting that takes into account the influence of upstream water projects. Moushan Reservoir basin is located in a hilly area of an arid and semi-arid region in the north of China. Flooding has the characteristics of sudden strong, short confluence time, steep rise, and steep fall, especially floods caused by extreme weather events, which have a high frequency and a wide range of hazards, and has become one of the most threatening natural disasters to human life and property safety. There are many small and medium-sized reservoirs in this basin, which have a significant influence on the accuracy of flood prediction. Therefore, taking Moushan Reservoir as an example, this paper puts forward a flash flood simulation method for reservoirs in hilly areas, considering upstream reservoirs, which can better solve the problem of flood simulation accuracy. Using the virtual aggregation method, the 3 medium-sized reservoirs and 93 small upstream reservoirs are summarized into 7 aggregated reservoirs. Then, we construct the hydrological model combining two method sets with different runoff generation and confluence mechanisms. Finally, after model calibration and verification, the results of different methods are analyzed in terms of peak discharge error, runoff depth error, difference in peak time, and certainty coefficient. The results indicate that the flooding processes simulated by the proposed model are in line with the observed ones. The errors of flood peak and runoff depth are in the ranges of 2.3% to 15% and 0.1% to 19.6%, respectively, meeting the requirements of Class B accuracy of the “Water Forecast Code”. Method set 1 demonstrates a better simulation of floods with an average flood peak error of 5.63%. All these findings illustrate that the developed model, utilizing aggregate reservoirs and dynamic parameters to reflect regulation and storage functions, can effectively capture the impact of small water conservancy projects on confluence. This approach addresses challenges in simulating floods caused by small and medium-sized reservoirs, facilitating basin-wide flood prediction.

1. Introduction

With the development of society, extreme rainfall events occur frequently under the influence of many factors such as climate change, underlying surface conditions, and human activities [1,2,3]. In recent years, extreme heavy rain events have occurred frequently in China, especially in the arid and semi-arid areas in the north, causing serious losses [4]; for example, from 28 July to 1 August 2023, the flood that occurred in the Haihe river region (named “23 · 7” flood by the Ministry of Water Resources, Beijing, China) [5], and on 20 July 2021, the heavy rain [6] that occurred in Zhengzhou, Henan Province, resulting in serious flood disaster losses (namely “7 · 20” flood). In hilly areas, floods are characterized by rapid onset, short response time, steep rise and fall, and high destructive potential. Additionally, many water conservancy projects such as reservoirs, locks, and dams have been usually constructed in river basins for the development of water resources. The construction of reservoirs changes the natural hydrological characteristics of rivers, resulting in changes in the production and aggregation mechanism [7,8,9,10,11], especially for extreme rainstorm events. In addition, most small reservoirs and pond dams in China have no operation facilities and lack a long series of observation data. However, in the process of reservoir flood prediction, not only the precipitation and runoff process but also the influence of the storage and release of upstream reservoirs should be considered. Therefore, in order to improve flood disaster prevention abilities, it is crucial to study flood simulation methods for hilly reservoirs that take into account the impact of upstream water conservancy projects. This will greatly enhance flood forecasting and control efforts while reducing losses.
For flood simulation and prediction, after years of research, domestic and foreign scholars have proposed lumped models such as the HBV model, Tank model, and Xin’anjiang model [12]. With the development of information and computer technology, scholars put forward distributed hydrological models such as Top model, VIC model, SWAT model, and HEC-HMS [13,14,15,16,17,18]. According to different climate zones and watershed characteristics of our country, Chinese scholars established multiple distributed hydrological models adapting to different watershed characteristics [19,20].
As for the impact of human activities, in foreign countries, hydrological models are mainly used to study runoff changes through land use/cover change [21,22,23]. In the study and application of conceptual hydrological models, many domestic scholars considered the impact of small and medium-sized reservoirs on production and confluence. For example, Guo Shenglian et al. [19] converted the interception of small and medium-sized reservoirs in the basin into the water storage capacity of Xin’an River model. Ling Minhua et al. [24] put forward the Xin’an River model considering pond storage to simulate runoff and analyze the impact of pond storage on river runoff. Chen Jian et al. [25] converted small and medium-sized reservoirs in the basin into virtual reservoirs and proposed an improved Xin’an River model.
In practical application, the flood forecasting method considering the influence of human activities mainly adds the influence factors of human activities into the lumped model. For example, Cheng Chuntian and Wang Bende [26] estimated the cumulative net rainfall value of each unit at different time periods, as well as the intercepting capacity of the upstream reservoir and paddy field during the growth period based on flood stage and crop irrigation so as to estimate the maximum intercepting capacity and runoff correction coefficient. They then fine-tuned and optimized the parameters through human–computer interaction to obtain the parameters of flow production and the influence of human activities and pointed out that the forecast accuracy was 9% higher than that without considering the influence of human activities for Shitokoumen Reservoir in Jilin Province, reflecting the influence of human activities on the runoff forecast. Guo Shenglian et al. [19] classified the water conservancy projects in the basin according to their storage capacity, converted the cumulative storage capacity of the same type of reservoir into the maximum storage capacity, and added it into the soil storage capacity of the Xin’an River model to put forward a flood forecasting scheme considering the influence of human activities. Sun Xinguo et al. [27] aggregated many water projects in the basin into a virtual reservoir, formulated the water storage and release law of the aggregate reservoir, effectively quantified the impact of reservoir storage and discharge on the flooding process of the basin, and increased the Nash efficiency coefficient of flood prediction in Fengman Reservoir basin by 22%. Aiming at the problem of poor simulation accuracy of floods with rainfall centers distributed in the upper reaches, Yao Shiqian [28] analyzed and evaluated the impact of changes in land use and water conservancy construction on runoff.
The above studies coupled the lumped model with the reservoir module did not fully consider the spatial distribution of water conservancy projects in the basin and did not describe the regulation and storage function of many small and medium-sized reservoirs with insufficient precision. Therefore, some scholars combined the advantages of the lumped model and distributed the hydrological model to establish a grid-based hydrological model considering the influence of water conservancy projects to further improve the accuracy of watershed flood prediction. For example, Yao Cheng et al. [29] established a grid-based new Anjiang River model (Grid-XAJ) to consider the influence of Kutangdam storage and drainage on the process of production and convergence. The water distribution process along the river course is described well.
Domestic flood simulation and forecast studies on the impact of water conservancy projects are mainly in humid or semi-humid areas, whereas studies on arid and semi-arid areas [9,11,28] only consider drought and humid conditions, but do not reflect semi-drought, and do not study flood simulation and forecast under extreme rainstorm scenarios. This paper proposed a flood simulation method for reservoir basins in hilly areas considering the distribution characteristics of upstream reservoirs and their influence on runoff in semi-humid areas. The method was established on the basis of a reservoir flood simulation model, further studied the flood holding capacity and the influence on runoff of many small and medium reservoirs upstream, and simulated the flooding process under different pre-influence rainfall so as to realize the flood forecast of the watershed as a unit and provide the basis for the following flood control scheduling. Firstly, according to the physical geography and hydrological characteristics, the hydrological model of the Moushan Reservoir basin was constructed based on HEC-HMS, in which two different combination methods of runoff generation and confluence, namely, the steady infiltration method with Snyder unit line method (method set 1) and the SCS-CN curve method with SCS unit line method (method set 2), were selected, respectively, in addition to the Muskingum method, which was used for the river flood evolution. Then, the distribution characteristics of the reservoirs in the basin were analyzed, the three medium and 93 small reservoirs in the upper reaches of the basin were generalized into seven aggregated reservoirs and added to the constructed hydrological model using the “Add Reservoirs” module in HEC-HMS. Finally, nine historical floods under different early influence rainfall were simulated and verified, of which six floods were for parameter calibration and three floods were for parameter verification. The peak discharge error, runoff depth error, peak current difference, and certainty coefficient were analyzed; a comparison between the results from different method sets was made with observed floods to verify the applicability and superiority of this approach.

2. Study Area and Data

2.1. Study Area

Moushan Reservoir is situated on the Wenhe River in Weifang City, Shandong Province, and covers a total drainage area of approximately 1262 km2. The upstream main stream is 71 km long with an average gradient of 0.00212, as shown in Figure 1. The basin is located in the East Asian monsoon region and has a continental climate. The annual average rainfall is 702.1 mm, and heavy rains mostly occur in mid-summer and early autumn, with obvious seasonality. Because the stone mountain area in the basin accounts for about 58%, the duration of the flood generated by the rainstorm is short, the flooding process line has a steep rise and steep fall, and the larger flooding process is generally 20–30 h.
In order to fully deploy and utilize the water resources, many small and medium-sized reservoirs have been constructed within the basin (can be seen in Figure 1), which have a significant influence on the accuracy of flood prediction. There is 1 large reservoir (Gaoya Reservoir), 3 medium-sized reservoirs (including Daguan reservoir, Yishan reservoir, and Shangzhuang reservoir), and 93 small reservoirs in the area.
In Figure 1, for the water conservancy projects, only the large and medium-sized reservoirs and small (1) reservoirs are marked, and the rest of the small reservoirs and pond dams are not marked.

2.2. Data Source and Processing

For the Digital Elevation Models (DEMs), the Geospatial Digital Elevation Model of version V3 (namely GDEMV3) is used and obtained from the Geospatial data cloud (http://www.gscloud.cn (accessed on 6 April 2024)), the horizontal resolution is 30 m and the vertical resolution is 1 m.
By using the expansion module of ArcGIS 10.5 software HEC-GeoHMS, which was developed by the Hydrologic Engineering Center (HEC) of the US Army Corps of Engineers to simulate the Hydrologic Modeling System (HMS) in a watershed, the scope of the study area was determined, as shown in Figure 2, through depression filling, flow direction calculation, confluence calculation, river network extraction, sub-basin division, and basin outlet definition, and the study area was divided into 22 sub-basins. Then, we calculated the slope, center location, longest flow path, hydraulic parameters of each sub-basin, and set the network elements of the HMS hydrological model to obtain the digital watershed that meets the requirements of the HEC-HMS model, as shown in Figure 2.
In Figure 2, W510, W560, W590, W610, W640, W650, W660, W690, W700, W720, W900, W740, W780, W790,W800, W810, W850, W860, W880, W890, W910, and W920 are the 22 sub-basins divided.
The land use-type data and soil-type data were obtained from Data Center for Resources and Environmental Sciences, Chinese Academy of Sciences (https://www.resdc.cn/ (accessed on 6 April 2024)) and China Soil Database (http://vdb3.soil.csdb.cn (accessed on 6 April 2024)), with an accuracy of 30 m. After tailoring and reclassification by ArcGIS, land use types were mainly divided into farmland, forest land, grassland, water body, urban buildings, and undeveloped soil, as shown in Figure 3. Soil types are mainly divided into sandy loam, clay loam, sandy clay, silty clay loam, and loam, as shown in Figure 4.
There are nine rainfall measuring stations in the basin of Moushan Reservoir, including Daguan (R1), Taoyuanzi (R2), Jiangyu (R3), Lijiagou (R4), Liuzhai (R5), Dianzi (R6), Nanwu (R7), Tangwu (R8), and Sujiazhuang (R9), as well as, two rainfall and hydrology stations in Gaoya (R10) and Moushan (R11). The rainfall data of 11 different rainfall stations were provided by Weifang Water Resources Bureau and floods information of the hydrographic station was provided by Moushan Reservoir operation and maintenance center.
Daily water evaporation was obtained from the China Meteorological Data Sharing Service System.

3. Methods

3.1. Flood Simulation Model

The basin of Moushan Reservoir is a semi-arid and semi-humid area with complex underlying surface conditions. There is basically no base flow in the river course, and the flood caused by rainfall is mainly generated by the rainfall of each event, so the influence of base flow is ignored.
In addition, based on the principle of fewer parameters, easy data access, and stable and reasonable simulation results, combined with the topographic conditions, meteorological conditions, soil conditions, and vegetation conditions of the basin of Moushan Reservoir, the methods with better application effects in semi-arid and sub-humid areas [9,10,11] are compared and analyzed, and two sets of methods (shown in Table 1) are selected for simulation calculation.
In Table 1, SCS-CN is the Soil Conservation Service Curve Number model proposed by the United States Department of Agriculture based on practical experience in 1972; CN is the number of runoff curves and has no dimension.
For runoff generation, the initial loss and steady infiltration method has strong applicability in simulating runoff in short-term rainfall scenarios and can accurately simulate the runoff process of short-term rainfall events and for long-term or complex rainfall patterns; the simulation accuracy of this method may be limited. However, the SCS-CN method may show higher simulation accuracy in long-term or complex rainfall patterns and may lead to prediction errors in the case of short-duration heavy rainfall due to simplified assumptions of the model. In the study area, the soil type and distribution are complex, the data are relatively lacking, and short-duration heavy rainfall events commonly occur. Therefore, the above two methods are used to calculate and analyze runoff production, respectively.
For confluence, the SCS unit line method has been widely used worldwide, and its parameters can be adjusted according to different basin characteristics. The combination of the SCS unit line method and SCS-CN current production method significantly improves the accuracy of flood prediction. This combination enables the model to better reflect the geomorphic characteristics of the basin, especially for the small watershed in the hilly area where data are lacking. The Snyder unit line method can reflect the characteristics of the basin well, including the influence of the basin area, topography, and other factors on the runoff process, but the parameter determination may be more complicated, and more field investigation and tests are needed to determine the appropriate parameters. The study area is a hilly area and data are lacking, so the above two methods are used for comparative analysis.

3.1.1. Flow Generation with Initial Loss and Steady Permeability Method

The Thiessen polygon method is used to divide the Thiessen polygon according to the distribution of rain measuring stations, as shown in Figure 5.
For the sub-basin inside the Thiessen polygon, the area rainfall is the rainfall of the rainfall station. For sub-basins spanning multiple Thiessen polygons, the surface rainfall is calculated with the polygon area as the weight listed in Table 2. The calculation formula is as follows:
P ¯ = i = 1 n A i F P i
where P ¯ is the area mean rainfall of sub catchment i, mm. n is the number of rain measuring stations. Ai is the area controlled by the ith rain measuring station in the sub-watershed, km2. F is the area of the sub-watershed, km2. Pi is the amount of rainfall at the i station, mm.
The initial loss steady infiltration method has strong practicability in simulating runoff in short-term rainfall scenarios, and the runoff production process of rainfall can be divided into two stages: initial loss and post-loss. The calculation formula is as follows:
p e t = 0                                       p i < I a P t f c           P i > I a   and   P t < f c 0                   P i > I a   and   P t < f c
where p e t is the net rainfall, mm.   P t is the average rainfall over the surface from time t to time t + Δ, mm, where Δ is the time step. I a is the initial loss of rainfall, mm. f c is the soil infiltration rate, mm/h.

3.1.2. Flow Generation with SCS-CN Curve Method

The SCS-CN curve method contains only one dimensionless parameter CN value, with few parameters, and the calculation process is relatively simple. However, this value is related to soil moisture, land use type, and soil type in the previous period, and can reflect the comprehensive characteristics of the underlying surface in the study area in a more comprehensive way. The theoretical value range of the CN value is 0–100, and the specific initial value is generally calculated according to the National Engineering Manual of the United States [15]. In actual simulation calculation, the common value range is 40–98 [6,30]. When there are multiple land use types and soil types in the basin, the compound CN w value of the basin is calculated according to the equation as follows:
CN w = A j CN j A j
where j is the number of land use types and soil types in the basin. A j is the area of land use type and soil type of mass j. CN j is the CN value of land use type and soil type of mass j.

3.1.3. Confluence Calculation Method—Snyder Unit Line Method

Under ideal conditions, there is the following relationship between the flood peak lag time Tp and the precipitation duration Tr of the unit line:
T p = 5.5 T r
Under standard conditions, the relationship between peak flow Up and peak time Tp of the unit line is as follows:
U P A = C C p T p
where Up is peak flow, m3/s. Tp is the peak time, h. A is the catchment area, km2. C is the conversion coefficient; for SI units, the value is 2.75. Cp is the unit line peak coefficient with values ranging from 0.4 to 0.8.
When the actual basin is very different from the ideal condition, the following changes should be made for the peak duration of the unit line:
T p R = T p T r T R 4
where T p R is the expected peak duration of the unit line. T R is the expected unit line period; that is, the set time step.
In 1992, Bedient and Huber [31] proposed the calculation formula of expected peak duration of unit line as follows:
T p R = C C t ( L L c ) 0.3
where L is the length of the main stream of a basin, Lc is the distance from the basin center to the basin outlet, C is the conversion constant, which is 0.75 in international units, and Ct is the stagnation of the basin coefficient, usually taking 1.8 to 2.2.

3.1.4. Confluence Calculation Method—Unit Line Method

The relationship between peak flow and peak occurrence time of unit line is as follows:
U p = C 1 A T p
T p = t 2 + t l a g
where C 1 is the conversion coefficient; for SI units, the value is 2.08. t is net rainfall duration. t l a g is the lag time of the basin; that is, the time difference between the peak of the unit line and the location of the net rain center. t l a g can be obtained by formula as follows:
t l a g = l 0.8 ( S + 25.4 ) 0.7 7069.7 y 0.5   and   S = 25400 CN 254
where l is the length of channel, m. S is the maximum possible amount of stagnant water in the basin, mm. y is watershed slope, whose value can be extracted by HEC-GeoHMS tool.

3.1.5. Confluence Calculation Method—The Muskingum Method

The Muskingum method is a channel confluence algorithm based on tank storage equation and water balance equation and widely used in basin routing because of its simplicity, high efficiency, and relatively low data requirement [32]. The segmental Muskingen method, Muskingum–Cunge method with the nonlinear calculus [33,34,35], and the meshing calculus, as well as the Muskingum–Cunge–Todini with variable parameter method [36,37] were proposed successively.
There are two important model parameters in the Muskingum method: slope K of the tank storage curve and specific gravity factor of discharge X. The estimation formulas are as follows [19]:
K = L n 0.6 1944 λ S 0 0.3 Q 0 0.2
X = 1 2 n 0.6 Q 0 0.3 5.14 λ S 0 1.3 L
where L is the length of river, m. n is the roughness coefficient. λ is the conversion coefficient. S 0 is the gradient of the riverbed. Q 0 is steady flow, m3/s.

3.2. Simulation Method for Regulation and Storage of the Reservoirs in the Upper Reaches

There is 1 large-sized reservoir which is Gaoya reservoir, 3 middle-sized reservoirs including Daguan Reservoir, Yishan Reservoir, and Shangzhuang Reservoir, and 93 small-sized reservoirs in the upper reaches. The projects greatly increase the difficulty of the flood forecast.

3.2.1. Large-Sized Reservoir

For the large upstream Gaoya reservoir, it can be seen from the water level information after the beginning and end of each flood that the maximum water level datum is about 153.0 m. The water storage and discharge rules are simulated by using the top overflow model on a horizontal dam. The water storage capacity of the reservoir is represented by the relation between water level and storage capacity (seen in Table 3 and Figure 6).
The initial storage capacity is obtained according to the input initial water level conditions of the reservoir. The dam top elevation is set at 153.0 m; when the water level is lower than 153.0 m, all the incoming water is intercepted, and when the water level exceeds 153.0 m, the excess water is discharged and the overflow length of the dam top is set to 40 m.

3.2.2. Small and Medium-Sized Reservoirs

In order to assess the impact of small and medium-sized reservoirs, the concept of virtual aggregation is employed to simulate the influence of water conservancy projects on production and confluence in the basin by creating aggregate reservoirs. The specific steps are as follows:
(1) Aggregation of small and medium-sized reservoirs. The study area is divided into 22 sub-basins; the small and medium-sized reservoirs located in the same sub-basin are aggregated into a virtual reservoir by analyzing the distribution. Those reservoirs upstream are then aggregated into seven virtual reservoirs (AR1, AR2, AR3, AR4, AR5, AR6, and AR7), as shown in Figure 7.
(2) Determination of water level–storage capacity relationship for aggregate reservoir. The “Add Reservoir” module in HEC-HMS is utilized to add those virtual reservoirs using a dam top overflow mode to replace their storage and discharge processes. Since an aggregate reservoir consists of several smaller ones, it can be assumed as a circular platform with its total volume representing the total storage capacity. By establishing this relationship based on a circular platform model (narrow at the bottom and wide at the top), we can obtain the water level–storage capacity curve for the aggregate reservoir, as depicted in Figure 8.
(3) Determine the moisture of the land according to the previous rainfall. If the initial water level is known, the initial storage capacity and interception capacity of the aggregate reservoir can be obtained from Figure 8.
The initial water level is closely related to the previous rainfall amount, evaporation, and water consumption, and the previous rainfall amount is an important factor. Firstly, according to the catchment area and the available storage capacity [11] of small and medium-sized reservoirs, the interception capacity Pt of the aggregate reservoir is calculated, as well as the cumulative rainfall P1f, P2f, and P3f of the 15 days, 30 days, and 60 days before the occurrence of the flood, respectively, are calculated, and the rainfall is divided into three categories including arid, semi-arid, and humid [12] according to the formula as follows:
P 3 f < P t or P t P 3 f < 2 P t and   P 3 f > k × P 2 f arid P t P 3 f < 2 P t   and   P 3 f k × P 2 f or 2 P t P 3 f 3 P t   and   P 3 f > k × P 2 f semi-arid P 1 f 2 P t or 2 P t P 3 f 3 P t   and   P 3 f k × P 2 f or P 3 f > 3 P t         humid
where k is the weight coefficient, k ≥ 2. P 3 f     k   ×   P 2 f indicates that the rainfall is mainly concentrated in the beginning of the flood season to the previous month. P 3 f     k   ×   P 2 f indicates that the rainfall mainly occurred within one month before the occurrence of rainfall.
(4) Determine the initial water level of the aggregate reservoir. When under arid conditions, assuming the aggregate reservoir water level is zero, the reservoir intercept ability is the strongest. When it is wet, it is assumed that the water level is located at the elevation H of the wide-top weir, and the reservoir is in the full state; at this time, the reservoir has almost no interception effect on the runoff generated by rainfall. In the case of semi-drought, assuming that the level of the aggregate reservoir is H/2, the retention capacity is half of the maximum retention capacity.
The total catchment area of the small and medium-sized reservoirs is 329 km2 and the total storage capacity is 43.61 million m3. The interception capacity of the aggregate reservoirs can be calculated to be 132.6 mm. According to the above classification methods, the nine floods selected for simulation research are classified as shown in Table 4.

3.3. Parameter Calibration

Two methods are used to automatically adjust the model parameters. The first is the Nelder–Mead algorithm, proposed by Nelder and Mead, for finding the extreme value of a multidimensional function, and the second is the Percent Error Peak function, one of the seven optimization objective functions provided in HEC-HMS. The automatically obtained parameter values would often ignore the actual physical meaning of the parameters, resulting in unreasonable values. Then, the unreasonable values are fine-tuned according to the actual meaning of parameters to obtain the calibration values of model parameters. The parameter calibration process is shown in Figure 9, the optimization results of flow-producing and confluence parameters in the method set 1 and set 2 are shown in Table 5, and the optimization results of river confluence are shown in Table 6.

4. Results and Discussions

4.1. Simulation Results

Nine flooding processes were selected for simulation, among which six floods were used to determine model parameters and three floods were verified and analyzed. The simulation results of six floods used to calibrate the model parameters are shown in Figure 10, Figure 11, Figure 12, Figure 13, Figure 14 and Figure 15. The model parameters obtained by the above calibration are used to verify the three floods, and the simulation results are shown in Figure 16, Figure 17 and Figure 18.
As can be seen from Figure 10, Figure 11, Figure 12, Figure 13, Figure 14, Figure 15, Figure 16, Figure 17 and Figure 18, the flooding processes simulated by the two method sets are consistent with the measured ones. The errors in flood peak discharge Q and runoff depth H, difference in peak time t , and certainty coefficient C of the simulation results were compared and analyzed, as shown in Table 7, Table 8 and Table 9.
As can be seen from Table 9,
(1) The flood peak errors simulated by method set 1 are between 2.4% and 15%, with an average error of 5.63%, and those simulated by method set 2 are between 2.3% and 12.3%, with an average error of 5.72%. Except the floods on 11 October 2003 and 10 August 2019, the flood peak error of the other seven fields simulated by method set 1 is smaller than those simulated by method set 2. The simulated runoff depth errors of method set 1 are between 0.1% and 16.1%, with an average value of 5.87% and those of method set 2 are between 3.0% and 19.6%, with an average value of 12.33%. It can be seen that the accuracy of the simulation results of the two method sets meets the requirements of Class B accuracy of the “Water forecast Code” [38]; that is, the two simulation method sets can be used for the flood forecast of the Moushan Reservoir basin, and method set 1 shows better simulation results compared to method set 2.
(2) The average simulation certainty coefficient of method set 1 and set 2 are both greater than 0.7, which meets the accuracy requirements of Class B and can be used for flood forecasting. The average simulation certainty coefficient of method set 1 is 0.89 and that of method set 2 is 0.85, which also shows that the simulation effect of method set 1 is better than that of method set 2.
(3) According to Figure 10, Figure 11, Figure 12, Figure 13, Figure 14, Figure 15, Figure 16, Figure 17 and Figure 18, considering the regulation and storage function of small and medium-sized reservoirs, both methods have better simulation effects, and the simulated flooding process is more consistent with the actual flooding process, which solves the difficult problem of flood simulation and provides a reference for other river basin flood simulations.
(4) By using the reservoir module of HEC-HMS, the initial water level of the aggregate reservoir is determined by considering the three initial states of “drought, semi-drought and wet”, ensuring accurate flood holding capacity to accommodate incoming flooding process curves and improve flood forecasting accuracy.

4.2. Discussions

To test the validity of the model proposed, some discussions about the model are presented below.
(1) The generalization of rainfall data results in differences between simulated and measured values. The distribution of rainfall stations in the study area are not uniform, and the areal rainfall of each sub-watershed is generalized by the Thiessen polygon method, but the areal rainfall calculated by the weight of the control area of each rainfall station in the sub-watershed is too average, ignoring the influence of the rainstorm center. The rainstorm center has an obvious peaking effect, which has a great influence on the flood peak and the confluence time, so there are differences between the simulated values and the measured values.
(2) The setting of the aggregation reservoir causes the difference between the simulated values and the measured values. In this paper, there are some shortcomings in considering the influence of small and medium-sized reservoirs. The uneven spatial distribution of small and medium-sized reservoirs is not taken into account in the model, and the storage capacity of small reservoirs is only a quantitative estimate. Therefore, with the reinforcement of small reservoirs and the increase in monitoring stations in the basin overcoming the lack of data at present, a distributed hydrological model should be established to simulate the influence of a large number of upstream water conservancy projects on the downstream hydrological process, and the accuracy of watershed flood simulation could improve.
(3) The difference in runoff depth between simulated results and measured values. The flood control standards of small reservoirs in the basin are not high, and this paper does not consider the phenomenon of a sudden increase in water intake in the reservoir caused by dam break and dam collapse under extreme circumstances. In addition, there are a large number of small reservoirs in the study area. This paper generalizes these reservoirs and greatly improves the accuracy of flood simulation. However, the generalized treatment results are different from the actual situation, especially the small water storage buildings such as ponds and dams, which will partially intercept flood waters, resulting in the simulated runoff depth generally being slightly larger than the actual situation.
(4) Calculation accuracy of storage capacity of small and medium-sized reservoirs. The model of the aggregation reservoir established in this paper only considers the influence of small and medium-sized reservoirs on flooding, and the storage capacity of aggregation reservoirs is mainly calculated according to the soil water content in the early stage. However, actually, the influencing factors of hydraulic engineering should generally be considered in addition to the upstream small and medium-sized reservoirs, as well as ponds and dams, farmland, and water blocking projects on rivers, etc., and the influencing factors for the impaction of reservoirs are not only the soil water storage in the early stage. So, in future studies, the influence of other hydraulic projects and other indicators affecting storage capacity can be added to further improve the model.
Despite the analysis of the above shortcomings, the simulation results of the established model still meet the accuracy requirements and can provide more accurate forecast information for defense decisions such as flood control scheduling, according to the result analysis in 4.1. Of course, aiming at the above shortcomings, the following research plan will further improve accuracy.
(5) Further research plans for flash flood simulation methods. The above analysis and discussion results show that the rainfall center and the setting of the aggregate reservoir have an important influence on the flood simulation accuracy. Therefore, it is planned to carry out studies on the regulating effect of rainfall distribution and reservoir aggregation methods on the confluence process of small and medium-sized reservoirs; for example, calculating the water storage capacity of both upper and lower soil layers in the basin by developing a model to simulate and rate various types of floods and then determine the soil water content over the first 30 days using the Thiessen polygon method to weight the rainfall of each sub-region and calculate the preliminary filling rate and storage capacity of the aggregate reservoir to improve the calculation accuracy of flood peak discharge and peak time.
(6) The focus of this paper is how to consider the impact of upstream water conservancy projects and simulate the flooding of hilly reservoirs under extreme rainstorm conditions. The impact of climate change on rainfall and flood simulation is not taken into account. Although climate change is recognized as a key factor affecting the frequency and intensity of extreme weather events [39], studies have shown that there is a significant correlation between temperature and rainfall for the Northeastern Himalayas [40], and climate change affects the spatial distribution of precipitation and heavy precipitation [41], potentially increasing the risk of flash floods in the basin [42,43]. Therefore, research on predicting changes in climate and environmental factors and their impact on rainfall is beneficial for simulating floods in hilly area reservoirs.

5. Conclusions

This paper takes the basin of Moushan Reservoir as the research object, considers the influence of small and medium-sized reservoirs in the upstream of the basin, and summarizes them as aggregate reservoirs. HEC-HMS is used to construct the hydrological model of the basin, and two kinds of flow generation and confluence simulation methods are developed. The effects of the two method sets in the flood simulation of the basin of Moushan Reservoir are compared in terms of peak flow, runoff depth, and peak occurrence time and certainty coefficient. The main conclusions are as follows:
(1) Based on HEC-HMS, the hydrology model of the Moushan Reservoir basin is constructed by using two different production–confluence combination method sets. Both methods are suitable for flood simulation and forecast of the basin. The simulated flood peak errors of method set 1 are between 2.4% and 15%, and those of method set 2 are between 2.3% and 12.3%. The errors of simulated runoff depth in method set 1 are between 0.1% and 16.1%, and those in method set 2 are between 3.0% and 19.6%. The accuracy of the simulation results of the two method sets can meet the requirements of Class B accuracy of the “Water Forecast Code”.
(2) Of the models established by the two method sets, method set 1 can better simulate the flood in the basin of Moushan Reservoir. The average flood peak error simulated by method set 1 is 5.63%, and that simulated by method set 2 is 5.72%. The average errors of runoff depth simulated by method set 1 and method set 2 are 5.87% and 12.33%, respectively. The simulated average certainty coefficient of method set 1 is 0.89, and that of method set 2 is 0.85. Therefore, the simulation effect of the first method is better than that of the second method in the Moushan Reservoir basin in terms of the certainty coefficient, the precision of the peak discharge, and the precision of the runoff depth.
(3) Many small and medium-sized reservoirs in the basin are summarized as aggregate reservoirs and dynamic parameters are used to reflect the regulation and storage functions under the three scenarios of drought, semi-drought, and humid, which can better reflect the influence of small water conservancy projects on confluence, solve the problem of flood simulation difficulties caused by small and medium-sized reservoirs, and facilitate the realization of flood prediction for the basin. It provides the basis for the next flood control operation and has certain reference significance for other related river basins.
(4) In order to enhance the accuracy of basin flood simulation and forecasting, further research on the impact of climate change on rainfall distribution and intensity is crucial for addressing the precision issue caused by above-average area rainfall. As well, for calculating the aggregation and storage capacity of small and medium-sized reservoirs, more factors should be taken into account. It is necessary to improve the model or establish a watershed-distributed hydrological model so as to better reflect the impact of small and medium-sized reservoirs on the basin flooding process.

Author Contributions

All authors contributed to this study’s conception and design. Material preparation, data collection, and analysis were performed by H.Z. (Huaqing Zhao), H.W., Y.Z., R.Z. and Z.Q. The first draft of the manuscript was written by H.Z. (Huaqing Zhao) and all authors commented on previous versions of the manuscript. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by National Natural Science Foundation Projects of China (52009140), Water Conservancy Research and Technology Extension Project of Shandong Province (SDSLKY201902).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The authors have no permission to submit the data since they belong to the Ministry.

Acknowledgments

We thank the anonymous editors and reviewers for their constructive comments and advice.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Shao, J.; Wang, J.; Wang, W.; Li, F.; Wu, C. Research on the Degree of Non-Stationarity in Extreme Precipitation in the Continental United States. Water Resour. Manag. 2024, 38, 537–551. [Google Scholar] [CrossRef]
  2. Salman, A.M.; Li, Y. Flood Risk Assessment, Future Trend Modeling, and Risk Communication: A Review of Ongoing Research. Nat. Hazards Rev. 2018, 19, 04018011. [Google Scholar] [CrossRef]
  3. Abdullah, J.; Muhammad, N.S.; Muhammad, S.A.; Julien, P.Y. Envelope curves for the specific discharge of extreme floods in Malaysia. J. Hydro-Environ. Res. 2019, 25, 1–11. [Google Scholar] [CrossRef]
  4. Jiang, Y.; Ye, Y.; Zhao, H.; Liang, L.; Cao, Y.; Gu, J. Research status and prospects on water conservancy big data. J. Hydroelectr. Eng. 2020, 39, 1–32. [Google Scholar]
  5. Yao, W. Practice and reflection of flood defense of “July 23” catastrophic flood in the Haihe River Basin. China Water Resour. 2023, 18, 1–4. [Google Scholar]
  6. Zhang, Y.; Duan, Y.; Wu, Z.; Liu, Y.; Cao, Y.; Lei, Y. Response of flood inundation depth intensity to landscape characteristics in small watershed of hilly areas under extreme rainstorms: An example of “7–20” rainstorm in Henan Province. Acta Ecol. Sin. 2023, 43, 8359–8374. [Google Scholar]
  7. Callow, J.N.; Smettem, K.R.J. The effect of farm dams and constructed banks on hydrologic connectivity and runoff estimation in agricultural landscapes. Environ. Model. Softw. 2009, 24, 959–968. [Google Scholar] [CrossRef]
  8. Cao, M.; Zhou, H.; Zhang, C.; Zhang, A.; Li, H.; Yang, Y. Research and application of flood detention modeling for ponds and small reservoirs based on remote sensing data. Sci. China Technol. Sci. 2011, 54, 2138–2144. [Google Scholar] [CrossRef]
  9. Deitch, M.J.; Merenlender, A.M.; Feirer, S. Cumulative Effects of Small Reservoirs on Streamflow in Northern Coastal California Catchments. Water Resour. Manag. 2013, 27, 5101–5118. [Google Scholar] [CrossRef]
  10. Liang, G.; Lu, G.; Dai, J.; Wang, X. Research on Flood Forecasting of Huanren Reservoir Considering the Impact of Upstream Water Conservancy Projects. J. North China Univ. Water Resour. Electr. Power (Nat. Sci. Ed.) 2023, 44, 71–77. [Google Scholar]
  11. Peng, Y.; Sun, X.; Zhang, X.; Zhou, H.; Zhang, Z. A Flood Forecasting Model that Considers the Impact of Hydraulic Projects by the Simulations of the Aggregate reservoir’s Retaining and Discharging. Water Resour. Manag. 2017, 31, 1031–1045. [Google Scholar] [CrossRef]
  12. Rui, X.; Jiang, C.; Zhang, J. Development of Watershed Hydrologic Models. J. China Hydrol. 2006, 26, 22–26. [Google Scholar]
  13. Xu, Z. Hydrological Models: Past, Present and Future. J. Beijing Norm. Univ. Nat. Sci. 2010, 46, 278–289. [Google Scholar]
  14. Li, J.; Wang, W.; Che, P.; Li, Q. Application Research on HEC-HMS Model and TOPMODEL Model in Mountain Flood Forecasting of Donzhuang Watershed. Water Resour. Power 2019, 37, 50–53. [Google Scholar]
  15. Meng, X. Application of HEC-HMS Flood Forecasting Model for Dazhan Reservior Basin; Shandong University: Jinan, China, 2019. [Google Scholar]
  16. Tian, J.; Xia, J.; Zhang, Y.; Chen, N. Application of HEC-HMS model in the Guanshan River Basin. Eng. J. Wuhan Univ. 2021, 54, 8–14. [Google Scholar]
  17. Cheng, X.; Ma, X.; Wang, W.; Liu, X.; Wang, Q.; Xiao, Y. Applicability Research of HEC-HMS Model Parameter Regionalization in Small Basin of Henan Province. J. China Hydrol. 2022, 42, 40–46. [Google Scholar]
  18. Shi, L.; Chen, Z.; Zhang, G. Applicability of HEC-HMS Model in Dali River Basin in the Middle Reaches of the Yellow River. Yellow River 2020, 42, 21–24. [Google Scholar]
  19. Guo, S.; Xiong, L.; Yang, J.; Peng, H.; Wang, J. A DEM and physically based distributed hydrological model. Wuhan Univ. HydrElec. Eng. 2000, 33, 1–5. [Google Scholar]
  20. Fu, X.; He, X.; Ding, L. Stochastic Flood Simulation Method Combining Flood Intensity and Morphological Indicators. Sustainability 2023, 15, 14032. [Google Scholar] [CrossRef]
  21. Bronstert, A.; Niehoff, D.; Bürger, G. Effects of climate and land-use change on storm runoff generation: Present knowledge and modelling capabilities. Hydrol. Process 2002, 16, 509–529. [Google Scholar] [CrossRef]
  22. Barlage, M.J.; Richards, P.L.; Sousounis, P.J.; Brenner, A.J. Impacts of Climate Change and Land Use Change on Runoff from a Great Lakes Watershed. J. Great Lakes Res. 2002, 28, 568–582. [Google Scholar] [CrossRef]
  23. Pfister, L.; Kwadijk, J.; Musy, A.; Bronstert, A.; Hoffmann, L. Climate change, land use change and runoff prediction in the Rhine—Meuse basins. River Res. Appl. 2004, 3, 229–241. [Google Scholar] [CrossRef]
  24. Ling, M.; Chen, X. Simulation of Impacts of Depression and Pond Water Storages on Runoff. Water Resour. Power 2010, 28, 14–16. [Google Scholar]
  25. Chen, J.; Wang, J.; Xie, X.; Li, C. Improved XAJ Model Hydrological Forecasting Considering Human Activities Influence. Water Resour. Power 2014, 32, 22–25. [Google Scholar]
  26. Wang, B.; Cheng, C. Determination of parameters of hydrologic model considering effect of human activity on runoff. J. Dalian Univ. Technol. 1995, 35, 400–404. [Google Scholar]
  27. Sun, X.; Peng, Y.; Zhang, X.; Zhou, H. A method for flood forecasting based the operation chart of aggregated reservoir. Shuili Xuebao 2017, 48, 308–316. [Google Scholar]
  28. Yao, S. Study on Flood Forecast and Dispatch of Dahuofang. In Reservoir Considering the Impact of Hydraulic Engineering; Dalian University of Technology: Dalian, China, 2022. [Google Scholar]
  29. Yao, C.; Li, Z.; Zhang, K.; Zhu, Y.; Liu, Z.; Huang, Y.; Gong, J.; Zhang, J.; Tong, B. Fine-scale flood forecasting for small and medium-sized rivers based on Grid-Xin’anjiang model. J. Hohai Univ. (Nat. Sci.) 2021, 49, 19–25. [Google Scholar]
  30. Zhang, H. Study on Flood Prediction and Operation of Flood Control in Moushan Reservoir Basin; Shandong University: Jinan, China, 2023. [Google Scholar]
  31. Bedient, P.B.; Huber, W.C. Hydrology and Floodplain Analysis. Master’s Thesis, Addison-Wesley, Reading, MA, USA, 1992. [Google Scholar]
  32. Wang, W.C.; Tian, W.C.; Xu, D.M.; Chau, K.W.; Ma, Q.; Liu, C.J. Muskingum Models’ Development and their Parameter Estimation: A State-of-the-art Review. Water Resour. Manag. 2023, 37, 3129–3150. [Google Scholar] [CrossRef]
  33. Zang, S.; Li, Z.; Yao, C.; Zhang, K.; Sun, M.; Kong, X. A New Runoff Routing Scheme for Xin’anjiang Model and Its Routing Parameters Estimation Based on Geographical Information. Water 2020, 12, 3429. [Google Scholar] [CrossRef]
  34. Norouzi, H.; Bazargan, J. Flood routing using the Muskingum-Cunge method and application of different routing parameter. Sādhanā 2022, 47, 282. [Google Scholar] [CrossRef]
  35. Lu, C.; Ji, K.; Wang, W.; Zhang, Y.; Ealotswe, T.K.; Qin, W.; Lu, J.; Liu, B.; Shu, L. Estimation of the interaction between groundwater and surface water based on flow routing using an improved nonlinear Muskingum-Cunge Method. Water Resour. Manag. 2021, 35, 2649–2666. [Google Scholar] [CrossRef]
  36. Todini, E. A mass conservative and water storage consistent variable parameter Muskingum-Cunge approach. Hydrol. Earth Syst. Sci. 2007, 11, 1645–1659. [Google Scholar] [CrossRef]
  37. Reggiani, P.; Todini, E. On the validity range and conservation properties of diffusion analogy and variable parameter Muskingum. J. Hydrol. 2018, 563, 167–180. [Google Scholar] [CrossRef]
  38. Ministry of Water Resources of the People’s Republic of China. Standard for Hydrological Information and Hydrological Forecasting; China Water & Power Press: Beijing, China, 2000. [Google Scholar]
  39. Huntington, T.G. Evidence for intensification of the global water cycle: Review and synthesis. J. Hydrol. 2006, 319, 83–95. [Google Scholar] [CrossRef]
  40. Haq, M.A. CDLSTM: A novel model for climate change forecasting. Comput. Mater. Contin. 2022, 71, 2363–2381. [Google Scholar]
  41. Overland, J.E.; Wang, M. Large-scale atmospheric circulation changes are associated with the recent loss of Arctic sea ice. Tellus A Dyn. Meteorol. Oceanogr. 2010, 62, 1–9. [Google Scholar] [CrossRef]
  42. Zhang, Y.; Wang, Y.; Chen, Y.; Liang, F.; Liu, H. Assessment of future flash flood inundations in coastal regions under climate change scenarios—A case study of Hadahe River basin in northeastern China. Sci. Total Environ. 2019, 693, 133550. [Google Scholar] [CrossRef]
  43. Haq, M.A.; Ahmed, A.; Khan, I.; Gyani, J.; Mohamed, A.; Attia, E.A.; Mangan, P.; Pandi, D. Analysis of environmental factors using AI and ML methods. Sci. Rep. 2022, 12, 13267. [Google Scholar] [CrossRef]
Figure 1. Map of Moushan Reservoir basin.
Figure 1. Map of Moushan Reservoir basin.
Sustainability 16 05001 g001
Figure 2. Digital elevation diagram of Mu Shan reservoir basin.
Figure 2. Digital elevation diagram of Mu Shan reservoir basin.
Sustainability 16 05001 g002
Figure 3. Land use situation of Moushan Reservoir basin.
Figure 3. Land use situation of Moushan Reservoir basin.
Sustainability 16 05001 g003
Figure 4. Soil types in Moushan Reservoir basin.
Figure 4. Soil types in Moushan Reservoir basin.
Sustainability 16 05001 g004
Figure 5. Subdivided watershed with the Thiessen polygon method.
Figure 5. Subdivided watershed with the Thiessen polygon method.
Sustainability 16 05001 g005
Figure 6. Map of the relationship between water level capacity for Gaoya Reservoir.
Figure 6. Map of the relationship between water level capacity for Gaoya Reservoir.
Sustainability 16 05001 g006
Figure 7. Distribution of the aggregate reservoirs.
Figure 7. Distribution of the aggregate reservoirs.
Sustainability 16 05001 g007
Figure 8. Curves of water level and storage capacity of aggregate reservoirs.
Figure 8. Curves of water level and storage capacity of aggregate reservoirs.
Sustainability 16 05001 g008
Figure 9. The parameter calibration process.
Figure 9. The parameter calibration process.
Sustainability 16 05001 g009
Figure 10. Comparison of the flood on 22 August 1998.
Figure 10. Comparison of the flood on 22 August 1998.
Sustainability 16 05001 g010
Figure 11. Comparison of the flood on 11 October 2003.
Figure 11. Comparison of the flood on 11 October 2003.
Sustainability 16 05001 g011
Figure 12. Comparison of the flood on 11 August 2011.
Figure 12. Comparison of the flood on 11 August 2011.
Sustainability 16 05001 g012
Figure 13. Comparison of the flood on 6 July 2017.
Figure 13. Comparison of the flood on 6 July 2017.
Sustainability 16 05001 g013
Figure 14. Comparison of the flood on 18 August 2018.
Figure 14. Comparison of the flood on 18 August 2018.
Sustainability 16 05001 g014
Figure 15. Comparison of the flood on 10 August 2019.
Figure 15. Comparison of the flood on 10 August 2019.
Sustainability 16 05001 g015
Figure 16. Comparison of the flood on 2 August 2017.
Figure 16. Comparison of the flood on 2 August 2017.
Sustainability 16 05001 g016
Figure 17. Comparison of the flood on 23 July 2018.
Figure 17. Comparison of the flood on 23 July 2018.
Sustainability 16 05001 g017
Figure 18. Comparison of the flood on 23 July 2020.
Figure 18. Comparison of the flood on 23 July 2020.
Sustainability 16 05001 g018
Table 1. Two sets of simulation methods.
Table 1. Two sets of simulation methods.
Method SetMethod
Runoff GenerationSlope ConfluenceRiver Channel Evolution
Set 1initial loss and
steady permeability
method
Snyder unit
line method
Muskingum method
Set 2SCS-CN curve methodSCS unit
line method
Muskingum method
Table 2. The weight calculated for each rainfall station in each sub-basin.
Table 2. The weight calculated for each rainfall station in each sub-basin.
Sub-BasinRainfall StationWeightSub-BasinRainfall StationWeight
W510R50.036W740R10.016
R80.964R30.367
W560R111.000R40.010
W590R80.209R100.549
R90.602R60.059
R110.189W780R70.695
W610R40.030R90.305
R50.810W790R60.063
R100.160R70.937
W640R50.213W800R60.404
R100.434R70.592
R80.341R90.005
R90.012W810R100.647
W650R111.000R60.169
W660R70.287R70.013
R90.616R80.008
R110.098R90.163
W690R70.638W850R20.208
R90.054R30.498
R110.308R40.295
W700R30.002W860R31.000
R40.712W880R10.553
R50.033R30.447
R100.253W890R20.781
W720R101.000R30.219
W900R10.653W910R10.239
R20.206R60.761
R30.140W920R61.000
Table 3. The relationship between the water level and capacity of the Gaoya Reservoir.
Table 3. The relationship between the water level and capacity of the Gaoya Reservoir.
Water level/m131.6132133134135136137138139140
Capacity/104 m300.142.3813.2943.92100.4187.1304.3446.4637.8
Water level/m141142143144145146147148149150
Capacity/104 m3893.9120815771990245529733534415248105500
Water level/m151152153154155156157158159160
Capacity/104 m36245705179318904998511,17512,47813,88815,43017,080
Table 4. Classification for the floods selected for simulation research.
Table 4. Classification for the floods selected for simulation research.
Flood NumberP1f (mm)P2f (mm)P3f (mm)Classification
22 August 1998104211.4400.4wet
11 October 200313.524.8258.4arid
11 August 2011140.4173.9330.5wet
6 July 201760.563.590.2arid
2 August 201738200.9263.4wet
23 July 20186236.1263.7semi-drought
18 August 201841169.4405.5wet
10 August 201995110.5147.5semi-drought
23 July 202040.4101.1144.7semi-drought
Table 5. Optimization results of flow-producing and confluence parameters.
Table 5. Optimization results of flow-producing and confluence parameters.
Method Set 1Method Set 2
Sub-BasinIa/mmStable Permeability fc/(mm/h)Time Lag of the Basin tpR/minPeak Coefficient CpArea/km2CN ValueTime Lag of the Basin tpR/min
W51014.22.962280.5143.570179.6
W56013.62.482720.7566.572158.2
W59012.42.594490.51148.575335.4
W61013.21.943410.22104.679212.5
W640142.661970.5532.276127.9
W65011.22.98930.6810.47746.9
W66011.12.073240.6172.274260.6
W69014.13.343560.59139.480264.2
W70013.42.351920.4357.866161.7
W72013.12.30800.405.16960.6
W74011.82.682180.3742.366192.6
W78014.42.701240.4212.27483.0
W79011.53.311950.5460.776148.2
W80013.82.541610.5926.173128.2
W81012.82.851860.1560.771139.2
W85013.62.352020.3960.265167.0
W86011.83.001570.7810.963137.0
W88011.52.141420.6337.869108
W89013.12.721760.5048.170136.9
W90011.92.351990.8396.971167.3
W91014.92.631920.7750.471164.8
W92014.42.131450.6963.372110.7
Table 6. The optimization results of river confluence.
Table 6. The optimization results of river confluence.
Channel NumberKXChannel NumberKX
R100.10.11R2402.10.22
R601.70.23R2501.30.1
R800.30.21R2600.50.26
R11010.16R2701.20.13
R1201.30.15R3300.70.15
R1301.40.12R3401.80.29
R1500.60.2R3501.10.27
R2200.60.19R3601.80.19
Table 7. The flood results simulated by the method set 1.
Table 7. The flood results simulated by the method set 1.
Flood EventFlood Peak Discharge Q/m3/sRunoff Depth H/mmDifference in Peak Time Δt/hCertainty Coefficient C
Measured ValueSimulated ValueErrorMeasured ValueSimulated ValueError
22 August 19981375.81409.52.4%73.8472.112.3%10.91
11 October 2003368.9424.215%22.8623.11.0%10.83
11 August 2011538.2551.62.5%38.1944.3316.1%30.86
6 July 20171169.41222.84.6%54.7863.2115.4%20.92
18 August 20184150.44019.23.2%185.51200.27.9%00.89
10 August 201920252155.56.4%132132.070.1%30.92
2 August 2017896.4840.16.3%57.7461.115.8%30.90
23 July 20181047.4981.66.3%40.8141.581.9%10.92
23 July 2020890.5926.24%33.534.272.3%20.87
Table 8. The flood results simulated by the method set 2.
Table 8. The flood results simulated by the method set 2.
Flood EventFlood Peak Discharge Q/m3/sRunoff Depth H/mmDifference
of Peak
Time/h
Certainty
Coefficient
Measured ValueSimulated ValueErrorMeasured ValueSimulated ValueError
22 August 19981375.813313.3%73.8462.9614.7%20.88
11 October 2003368.9414.312.3%22.8625.4111.2%10.78
11 August 2011538.2507.45.7%38.1934.898.6%30.84
6 July 20171169.41225.34.8%54.7849.978.8%20.92
18 August 20184150.44293.13.4%185.51203.79.8%20.79
10 August 201920252071.32.3%132109.5217%20.87
2 August 2017896.4942.55.1%57.7459.53.0%20.89
23 July 20181047.41107.75.8%40.8148.2718.3%00.88
23 July 2020890.5968.58.8%33.540.0819.6%10.87
Table 9. Comparison and analysis of the simulation results from two method sets.
Table 9. Comparison and analysis of the simulation results from two method sets.
PeriodFlood EventMethod Set 1Method Set 2
Error of Q/%Error of H%Δt/hCError of Q/%Error of H%Δt/hC
Calibration period22 August 19982.42.310.913.314.720.87
11 October 200315.01.000.8512.311.210.77
11 August 20112.516.130.865.78.630.8
6 July 20174.615.420.924.88.820.91
18 August 20183.27.910.873.49.820.79
10 August 20196.40.130.912.317.020.87
Validation period2 August 20176.35.820.95.13.020.89
23 July 20186.31.910.925.818.300.88
23 July 20204.02.320.878.819.610.78
Mean value5.635.871.670.895.7212.331.670.84
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Zhao, H.; Wang, H.; Zhang, Y.; Zhao, R.; Qi, Z.; Zhang, H. Flash Flood Simulation for Hilly Reservoirs Considering Upstream Reservoirs—A Case Study of Moushan Reservoir. Sustainability 2024, 16, 5001. https://doi.org/10.3390/su16125001

AMA Style

Zhao H, Wang H, Zhang Y, Zhao R, Qi Z, Zhang H. Flash Flood Simulation for Hilly Reservoirs Considering Upstream Reservoirs—A Case Study of Moushan Reservoir. Sustainability. 2024; 16(12):5001. https://doi.org/10.3390/su16125001

Chicago/Turabian Style

Zhao, Huaqing, Hao Wang, Yuxuan Zhang, Ranhang Zhao, Zhen Qi, and Haodong Zhang. 2024. "Flash Flood Simulation for Hilly Reservoirs Considering Upstream Reservoirs—A Case Study of Moushan Reservoir" Sustainability 16, no. 12: 5001. https://doi.org/10.3390/su16125001

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop