Next Article in Journal
Experimental Investigation of the Bond Performance at the Interface between Engineered Geopolymer Composites and Existing Concrete
Previous Article in Journal
Enhancing BIM Integration: A Comparative Analysis of Novel Composite Structure Documentation Methods
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Effect of Project Control Practices on the Performance of Building Construction Companies in Uganda: A Case Study of the City of Kampala

College of Civil Engineering, Liaoning Technical University, Fuxin 123000, China
*
Author to whom correspondence should be addressed.
Buildings 2024, 14(6), 1818; https://doi.org/10.3390/buildings14061818
Submission received: 11 March 2024 / Revised: 14 April 2024 / Accepted: 22 April 2024 / Published: 15 June 2024
(This article belongs to the Section Construction Management, and Computers & Digitization)

Abstract

:
This research paper analytically evaluates the project control practice levels used by the building construction companies within Kampala, Uganda. The research also assesses the impact of project control practices on the productivity of companies. The research was performed to ascertain the current control practices among 160 respondents from various construction companies registered with the Uganda Registration Services Bureau. This research used amalgamation from multiple studies in the literature to obtain the variables. This research adopts 34 standard control practices from 4 vital project control duties: planning, monitoring, analyzing, and reporting. These project control tasks were organized using mean response ratings grounded in their relevance to the construction companies. This process authorized researchers to prioritize tasks based on their perceived importance or relevance to the construction companies involved. Results showed that evaluating performance with the use of S-curves (4.32), timely access to information and encouragement (4.55), report representation using quantitative tools 4.75, and cost value comparison application during analysis (4.76) were rated least among the control practices. On the other hand, the top project control practices included formulation of the project schedule (8.88), project feasibility validation (8.86), budgeting for each activity (8.84), key project route definition (8.81), team awareness of the budget (8.77), setting realistic targets for projects (8.50), and consultation from subcontractors (8.74). From the results obtained by the sample respondents specified, it can be concluded that planning is the most vital project control task practiced in the building construction industry in Uganda. In addition, this research ascertained a substantial relationship between project control practices and the performance of building construction companies. Accordingly, this research recommends that project control practices be effectively observed by both contracting and consulting companies to enhance their overall performance and governance.

1. Introduction

Project control practices are pivotal in successfully executing construction projects, particularly civil engineering. Project control practices involve various processes and tools that aim to ensure the successful completion of projects within the specified scope, budget, and time frame [1]. This is particularly important in civil engineering, where complex projects require detailed planning and coordination. Construction projects are complex and large in scale. To effectively manage these projects, project control practices offer a structured approach to handling resources, schedules, and costs. Refs. [2,3] note that using project control techniques in civil engineering leads to better project outcomes by reducing delays, optimizing the use of resources, and enhancing overall project efficiency. A critical factor in project management for civil engineering is the focus on thorough planning and scheduling. Widely practiced tools like the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) create detailed project schedules. Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are scheduling methods designed to plan a construction project and to analyze and represent the tasks involved in completing a given project by employing a network of associated and similar activities, coordinating optimum cost and time criteria [4]. These techniques help identify critical activities and dependencies, enabling project managers to allocate resources and minimize potential bottlenecks efficiently [5]. By utilizing these scheduling methodologies, civil engineering projects can maintain a structured timeline, reducing the risk of delays and cost overruns [3].
In civil engineering project management, cost control is as important as scheduling. According to researchers [6], it is crucial to have cost estimation and monitoring mechanisms in place to ensure that projects remain within budgetary constraints. Tools such as Earned Value Management (EVM) provide a systematic approach to tracking project costs against the planned budget, enabling real-time modifications and proactive decision making [7].
Techniques such as CPM, PERT, and EVM provide a systematic approach to planning, resource allocation, and cost management [8]. When we consider the case study of the city of Kampala in Uganda, it is vital to understand how these practices impact the performance of building construction companies in the local context. The construction industry is known for its complex and challenging large-scale projects that require robust project control practices. According to [9], uncertainties relating to weather conditions, resource unavailability, and unforeseen site conditions are expected. Project control practices are essential to alleviate these uncertainties by providing a structured framework for planning, monitoring, and adjusting project activities. Mega construction projects worldwide have high stakes and minimal margin for error, as noted by [2]. Project control practices are adopted to ensure the successful completion of these projects and contribute to overall economic development.
The economic impact of construction projects is substantial, and effective project control practices play a pivotal role in optimizing costs. According to a study by [6], cost overruns are prevalent in the construction industry, leading to financial strain on public and private stakeholders. Project control practices, such as cost estimation, help identify potential cost issues early in the project lifecycle [10]. By integrating these practices, building construction companies can enhance cost efficiency, avoid budget overruns, and contribute to the sustainable development of the construction sector. This economic stability is crucial for the companies involved and the overall growth of economies globally.
Effective collaboration and communication among stakeholders are imperative for the success of construction projects. Project control practices provide a structured platform for communication, ensuring that all stakeholders are well informed and aligned with project objectives. According to [11], the lack of communication and coordination significantly contributes to project delays and disputes. Project control practices, such as Building Information Modelling (BIM) and collaborative project management tools, facilitate real-time communication and information sharing among project participants [12]. Fostering a collaborative environment, reducing conflicts, and enhancing the efficiency and effectiveness of construction projects are achieved through this approach.
Transitioning from the global perspective to a developing country context underscores the critical role of project control practices in overcoming inimitable challenges. In developing countries, including Uganda, construction projects face additional hurdles related to inadequate infrastructure, limited resources, and regulatory constraints [13]. Collaboration with policymakers and regulatory agencies could facilitate a better understanding of regulatory requirements and potential areas for streamlining processes. Effective project control practices are crucial to overcoming challenges in construction projects by providing a structured approach to managing resources, ensuring quality, and mitigating risks. In Uganda’s building sector, it is essential to apply these practices to promote sustainable development, enhance infrastructure resilience, and cater to the unique needs of the local communities [14].
In the context of Uganda, a developing country with a burgeoning construction sector, the need for effective project control practices becomes even more pronounced. Like many other developing nations, Uganda has challenges such as limited financial resources, weak infrastructure, and evolving regulatory frameworks [15]. Project control practices offer a tailored solution to address these challenges by fostering a disciplined approach to project management.
Uganda’s construction industry is an essential economic growth and development driver, contributing significantly to the nation’s Gross Domestic Product (GDP), according to [16]. Infrastructure development is a crucial priority for Uganda’s government, aiming to improve connectivity, create employment opportunities, and enhance living standards. In this context, project control practices are vital in ensuring that infrastructure projects are executed efficiently, on schedule, and within budgetary constraints. The alignment of project objectives with national development goals is crucial for maximizing the positive impact of construction projects on the local economy [14].
Resource constraints are a common challenge in the construction sector of developing countries, including Uganda. Limited skilled labor, materials, and equipment availability can impede project progress and spearhead delays. Project control practices offer mechanisms to optimize resource allocation, mitigate risks associated with resource scarcity, and enhance overall project resilience. For instance, effective workforce management strategies and supply chain optimization, as highlighted by [17], become instrumental in navigating resource challenges specific to Uganda’s construction landscape.
Various factors contribute to the cost control and project duration of construction projects. These include political instabilities, inflation of material prices, poor controls and regulations, unreliable government guidelines, poor time management, and changes in design and estimates. Studies have shown that design changes and material price inflation are the most significant factors that cause cost overruns and delays in project completion. Planning is also crucial, as insufficient cash flow can lead to delays and even abandonment of unfinished structures. Client’s insurance that their demand for design alterations during the construction period has no adverse effects on the critical activities to avoid causing adjournments is vital [18]. Despite global efforts to meet construction objectives, the complexity of modern-day projects is higher than ever.
There is a mismatch in appreciating how project control practices expedite amalgamating social responsibility and dependability into construction projects in Kampala. According to research conducted by [19], it is crucial to integrate social responsibility into construction projects and ensure that they align with the local communities’ cultural and social subtleties. They encourage collaboration between construction companies, NGOs, and community groups to effectively identify and address social concerns within project management frameworks. The amalgamation of project control practices such as social impact assessments, community consultations, and sustainable development initiatives can significantly contribute to the success of the project and the overall well-being of the communities involved. Circumnavigating regulatory frameworks is a significant aspect of construction projects in Uganda. Project control practices assist building construction companies in adhering to local regulations and standards. Thorough risk assessments, compliance monitoring, and the incorporation of flexibility in project plans to accommodate regulatory changes are involved in this process [20]. Regulatory compliance is crucial for project sustainability and avoiding legal impediments, particularly in a developing country milieu where regulatory environments may be dynamic and subject to change. Generally, adopting project control practices in Uganda’s building construction sector is domineering for overcoming local challenges, optimizing resource utilization, and ensuring that construction projects contribute positively to economic development and community well-being. As Uganda strives for sustainable development, integrating effective project control practices remains central to the success and resilience of its construction industry [21].
Effective project control practices are essential for the success of building construction companies. However, the construction industry faces various challenges in achieving effective project control practices. One of the significant challenges is the dynamic nature of construction projects, as highlighted by [22]. The complexity and variability inherent in construction projects, driven by changing weather conditions, site-specific challenges, and evolving client requirements, make implementing rigid project control practices difficult. Therefore, it becomes crucial to maintain adaptability within project control frameworks to address astonishing challenges and ensure project success on a global scale. One of the main hitches developing countries such as Uganda face is the effective management and allocation of resources. These nations often lack skilled labor, materials, and financial resources, which makes it challenging to implement project control practices effectively, as highlighted by [23]. In Uganda’s construction sector, achieving optimal resource allocation requires innovative solutions and strategic planning to overcome the constraints imposed by limited resources. Failure to address these challenges through project control practices may lead to delays, cost overruns, and compromised project outcomes—the prerequisite for exploration of alternative solutions and tactics to overcome limitations in technological infrastructure. Infrastructure deficiencies and technological gaps present formidable challenges in pursuing effective project control practices. In many developing countries, including Uganda, inadequate technological infrastructure hampers the adoption of advanced project control tools and software [24]. The lack of reliable internet connectivity and access to cutting-edge project management technologies can impede real-time communication and collaboration. Project control practices must be adapted to local technological capabilities to overcome this, ensuring they remain effective in environments with limited technological resources. Advocation for investments in improving technological infrastructure in Uganda to support adopting advanced project control tools and software can be targeted.
Navigating regulatory frameworks and governance issues is a critical challenge in the context of developing countries. The prevailing lack of discussion on specific mechanisms within project control practices to ensure compliance with regulatory frameworks seems to be one of the breaches in Kampala. Like many other flexible developing nations, Uganda may face bureaucratic red tape, inconsistent regulatory enforcement, and ambiguous legal frameworks [25]. This poses a significant challenge to implementing standardized project control practices (SPM). Without a clear and stable regulatory environment, construction companies in Uganda may struggle to establish the necessary frameworks for project planning, risk management, and compliance monitoring. Understanding how project control practices are bespoke to suit unique challenges in Uganda’s construction industry is still lacking. Flexible project control practices that account for the local regulatory landscape are essential in overcoming these challenges. The reassurance of an alliance between academia, industry experts, and policymakers to develop guidelines or frameworks for adapting project control practices to the local context can be connected to the shortage of skilled professionals in the construction industry, which poses a challenge to the effective implementation of project control practices in developing countries. Uganda’s narrow focus on how project control practices contribute to training and capacity building in project management and construction hinders the sector’s growth. There is a shortage of trained project managers and personnel proficient in modern project control methodologies, which is a significant challenge [26]. Addressing this challenge requires a concerted effort toward capacity building, partnering with educational institutions and industry associations to develop training programs tailored to the needs of project managers and construction personnel, and skills development within the local workforce. The instituting of training programs and knowledge transfer initiatives precisely targeting project management skills within the construction industry in Uganda’s project control practices must incorporate training programs and knowledge transfer initiatives to build the necessary expertise in project management, ensuring that the workforce is equipped to accomplish projects.
In summary, the challenges in achieving efficacious project control practices extend globally but manifest uniquely in developing countries like Uganda [27]. From resource constraints to infrastructure deficiencies and regulatory complexities [25], these challenges demand adaptive and context-specific approaches within project control frameworks to foster successful construction project outcomes.
In a nutshell, this research paper attempts to investigate the profound impact of project control practices on the performance of building construction companies in Uganda. Unsatisfactory detail on the extent of quantitative analysis conducted regarding the effects of project control practices longs for further research [28]. The study aims to discern the specific impacts of project control practices on crucial performance indicators within the construction industry. Qualitative and quantitative research approaches are employed [29]. These methods allow for a comprehensive analysis of existing scholarly works, enabling the identification and synthesis of key findings related to the effects of project control practices. The subsequent sections of this paper delve into the research methods prevalent in construction studies, offering insights into the unique challenges and opportunities associated with project control in the building construction context. Following this, the paper outlines the research methodologies adopted to attain the objectives outlined in this scrutiny by ensuring transparency regarding the data collection and analysis methodologies. However, there is a necessity for additional quantitative analysis regarding the effects of project control practices [30]. Backup of collaboration with industry partners to access and analyze relevant datasets, such as project performance metrics and financial records, and involvement in gathering data on project completion rates, cost overruns, schedule adherence, and stakeholder satisfaction levels for hearty quantitative analysis.
Analyzing the various positive effects, such as increased cost efficiency, timely project completion, recuperated collaboration with stakeholders, and overall project success, leads to the company’s performance. The research results are poised to provide valuable insights for professionals in the industry, policymakers, and scholars, contributing to a deeper understanding of the intricate relationships between project control methods and the operational success of building construction companies in Uganda.

Research Objectives

The main objectives of this study are as follows:
1—To identify the control practices implemented by building companies in Kampala, in particular, to investigate the regulatory frameworks, internal control mechanisms, and other strategies used to manage and regulate companies’ operations.
2—To assess the performance of building companies by utilizing pertinent metrics, including financial performance, project completion time, quality of construction, and client satisfaction.
3—To examine how control practices influence the performance of building companies by evaluating the effectiveness of control measures in accomplishing predetermined objectives and ensuring adherence to standards within the construction industry.
4—To identify the obstacles encountered by building companies in implementing control practices, encompassing financial limitations, shortages of skilled personnel, regulatory intricacies, and technological shortcomings affecting the adoption and efficacy of control measures.
5—To provide recommendations to improve control practices and overall performance in Uganda’s building industry.

2. Methods and Materials

2.1. Research Methodology

A mixed research approach, utilizing both quantitative and qualitative research methods, was employed to achieve the aims and objectives of this study [31]. Mixed methods research integrates various methods to gain a qualitative and quantitative perspective. Choosing a methodology based solely on its strengths may lead to blind spots and skewed results. Qualitative research analyses non-numerical data to uncover underlying meanings and patterns, while quantitative research is commonly used for social research [31,32]. Quantitative research is characterized by collecting numerical data using deductive reasoning to link theory and research using experiments and surveys. Quantitative research is characterized by collecting numerical data using inductive reasoning to link theory and research by understanding the social world through the interpretation of social participants and a constructionist ontological position, which argues that social interactions influence social phenomena through a case study [32]. The use of two research techniques so that distinct components of an investigation can be combined: quantitative research to support qualitative research findings or vice versa, and one research methodology to support research using the other research methodology. In this research, the cross-sectional survey policy was employed in which the qualitative and quantitative procedures were used in the process of gathering comprehensive information which was used in the same way as what [33] used in their research where the quantitative and qualitative policies help in quantifying the research results of the study and the compilation of chronicle descriptive evidence, which will eventually support effect analysis on the company operation, respectively. The quantitative approach also helps in finding out and drawing conclusions about the findings from an enormous population, and decisions are made on a massive population.

2.2. Data Collection and Data Analysis

Data for the research were collected through a questionnaire that asked representatives from various construction companies for their insights. The data collection used a dual sampling approach that combined purposive sampling to target specific expertise and stratified simple random sampling for a broader and unbiased industry representation. This strategic approach ensured that the dataset was diverse and comprehensive, facilitating in-depth analysis of project control practices and their impact on construction companies’ performance. The collected responses were checked to ensure they were complete and readable before being processed through Excel 2019 and the Statistical Package for the Social Sciences (SPSS 24.0) for Analysis. Different percentages and ranks were calculated as part of descriptive analysis using various statistical techniques, including descriptive statistics approaches using Excel and SPSS, pattern matrix and reliability test, KMO and Bartlett’s tests to assess the suitability of data for factor analysis, Cronbach’s alpha test to evaluate the internal consistency reliability of the test [34], Total Variance Explained to guide and help in understanding how much of the variability in the data collected is captured by extracted factors, regression analysis for understanding the relationships between variables (dependent and independent), and Analysis of Variance (ANOVA) for standardized and unstandardized coefficients to compare means across the groups and conclude the research, similar to [35].

2.3. Scope of the Research

This research investigates the effect of project control practices on the performance of building construction companies in Uganda, with the city of Kampala as a case study. The study encompasses qualitative and quantitative research approaches to comprehensively analyze the intricate dynamics between project control practices and the performance of registered building construction companies in Kampala. The primary focus of this research is on the city of Kampala, Uganda, and it aims to investigate building construction companies that are fully registered with the Uganda Registration Services Bureau (URSB) and operate within this urban area. This study intends to provide a localized and context-specific understanding of project control practices and their impact on performance. This study concentrates on control practices in Uganda’s building construction industry and how they impact financial performance, project completion time, construction quality, and client satisfaction.

2.4. Study Area

This study was conducted in the city of Kampala, the capital of Uganda, as a case study. Kampala city is bordered by Mukono district to the east, Buikwe district to the south, Luweero district to the north, and Wakiso district to the west. It is one of the fastest-growing cities in Africa. Kampala’s estimated population for 2023 is around 3,846,102, with an annual population growth rate of about 4.03%, according to [36]. Its geographical coordinates are 0.3152° N and 32.5816° E, and it spans an area of 72.97 square miles, comprising 68 square miles of land and 5.0 square miles of water [37]. Kampala is 1200 m (3900 feet) above sea level [38]. It is characterized by hills and valleys filled with sluggish rivers and swamps, as shown in Figure 1. The city has five divisions: Central, Kawempe, Makindye, Nakawa, and Rubaga. Each division is headed by an elected Mayor who is popularly directed. Kampala serves as Uganda’s national and commercial capital and borders Lake Victoria, the largest lake in Africa [39]. Hills covered with red-tiled villas and trees encircle a modern urban center of skyscrapers. This information was obtained from the Kampala Capital City Authority, which is entirely in charge of the city.

2.5. Study Design

Sample Size and Population Targeted

Using different research approaches, research methods can be classified as qualitative or quantitative research, which stresses quantification in data collection and examination [29]. Determining the connection between theory and research takes into account a provable manner, and stress is kept on the confirmation of theories. The quantitative research method integrates the norms and practices of the natural scientific model and positivism. It views the social portent as an outer objective truth [29]. A systematic literature review can be classified as quantitative or qualitative as it identifies, selects, and critically appraises research to answer a formulated question [40]. This research aimed to explore the effect of project control practices on the performance of building companies in Uganda. A mixed research approach using qualitative and quantitative methods [41] was best suited to accomplish the aims and objectives of this research. The research started using a qualitative approach to identify the control practices most construction companies in Kampala commonly use.
After finding out the most commonly used control practices from the literature associated with the construction companies in Kampala, a quantitative approach was adopted to rank the essential and adequately used control practices that play a significant role in the performance of construction companies. A similar approach was also adopted by [42] in their research on the spaces under highways and bridges. A questionnaire was then developed and was sent to the selected respondents. This questionnaire aimed to establish the ranking of the control practices at the planning, monitoring, reporting, and analyzing levels, considering the profession, education level, company type, and the company’s annual turnover. The selected are the building and construction companies, construction maintenance companies, and consultancy companies that are fully registered with the Uganda Registration Services Bureau (URSB), and the study targeted practicing people with adverse knowledge about construction, ranging from Civil Engineers, Valuers, Masons (builders), Surveyors, and Architects. The population choice was open for as long as they were in the construction line, experienced, and ready to provide unbiased information. We used two sampling methods: purposive and simple random sampling [43]. We resorted to purposive sampling because it minimizes variations, aligns with research objectives, and is efficient. Purposive sampling targeted practitioners who have been in the construction field for more than 25 years and have characteristics needed in the study. Confidentiality protection was critical and emphasized throughout. Simple random sampling was used to avoid biased and statistical inferences, results, and information about the different operations of some control practices, as [44] asserted. This study also used the quantitative approach, and the number of respondents was 160 out of the 190 questionnaires supplied to different registered companies.
Relevant information related to the potential respondents for purposive sampling arrangement that included qualification, expertise, research interest experience, and email was obtained from their organization company websites and web pages to confirm eligibility similar to what [29] used. This criterion was based on educational qualifications, experience, expertise, and research interest to help receive proper information about the effectiveness of control practices on the performance of construction companies, and it was carried out with integrity. For respondents who used simple random sampling, caution was taken that they should lie within the qualification gaps and be able to provide accurate information for the study. The academic respondents’ minimum rank was a Bachelor’s degree, with a minimum of 5 years of working experience and interest in providing thorough information about the study. The respondents were required to have research interests relevant to the leitmotif of the current research, that is, the effect of control practices on the performance of building construction companies in Uganda through a case study of the city of Kampala.
The questionnaire developed based on the data collected during the initial stage of the research was divided into eight segments. The first segment provided information about this study’s purpose, confidentiality policy, and consent to participation. The second segment was about the personal information of the respondents, including gender, academic qualification, age, experience, and research interests. The third segment was based on the specialization and location of the respondents. Segments four to eight of the questionnaire were related to planning control practices, monitoring control practices, recording control practices, and analyzing control practices. Each level was divided into several sub-points, where respondents were asked to rate their effectiveness on a Likert scale of 1 (least effective) to 10 (most effective). Some of the questions asked included but were not limited to the following: How effectively does your company formulate a clear project schedule before commencing construction projects? How periodically is the progress of work inspected against predetermined milestones and benchmarks? How accurately are project data and information recorded, honestly verified, and documented throughout construction projects? How regularly are S-curves used in performance evaluation in your company? Many researchers, including [29], use a specific approach to rank the effects in their research studies. In the final section of the questionnaire, respondents were allowed to provide any additional comments they felt were essential for the study. Descriptive analyses were conducted using the Statistical Package for the Social Sciences SPSS (24.0) to determine the overall ranking of different control practices on companies’ performance, similar to the methods used by [29]. Control practices with a mean score of 6 or higher were considered adequate in this research, while those scoring below 6 were considered least effective. The table below displays this information. Table 1 presents the selection technique, targeted population, sampled population, and sample size.

2.6. Research Framework

This study looks into the role of operational management techniques in the delivery and performance of construction companies, especially in Uganda’s capital, Kampala. This study aims to investigate how project control practices impact the performance of construction entities in Kampala. Examining this connection seeks to provide insights into enhancing construction project management in Uganda’s capital city. The authors conducted a thorough literature review to determine appropriate indicators for these two areas. They identified several indicators for project control, such as planning, monitoring, reporting, and analyzing. For company performance, they looked at management skills and financial ability indicators. Based on these six leading indicators, the authors derived several components that can be used to categorize them under project control or company performance. An important finding from the interview research is that, in practice, project cost and time control are frequently separate. Consequently, the principal approach to project control in practice typically addresses time and cost control separately, aligning with standard practices. This research also reveals that project control typically embodies multiple tasks, as [45] highlighted.

3. Results

Ref. [46] accentuated the substance of adhering to the research method and process, even in the case of minor research endeavors. This study utilized a quantitative approach to gather relevant data from various building construction companies in the city of Kampala, Uganda. Experts such as Quantity Surveyors, Architects, Masons, Civil Engineers, and relevant departments within each company were targeted due to their construction cost and time control expertise. A questionnaire was designed with a 10-point rating scale, which allowed the respondents to assess project control practices obtained from the literature. One hundred ninety questionnaires were distributed to these firms to gather information on their project control practices and processes. Out of the 190, 160 respondent companies completed and returned the questionnaires, resulting in an 84% response rate deemed satisfactory for the research. The accumulated data were analyzed to evaluate the level of control practices within the building construction companies and to assess the impact of these practices on company performance, utilizing various statistical methods. Firstly, descriptive statistics were presented for respondent demographics such as gender, age, profession, work experience, education level, company type, establishment year, total technical staff, and annual revenue. After conducting a mean item rating to assess the level of project control practices, a factor analysis was performed to determine how these practices impact performance and operation. This research is concluded based on the study’s results, and the findings are presented below. Table 2 displays demographic details regarding the respondents and their respective companies, which furnishes essential information for assessing the data’s reliability and dependability. As explained below, these categories outlined comprehend the respondents’ career, education level, company type, and revenue.
Table 2 defines the respondents’ demographic synopsis, indicating that 23.1% were Civil Engineers, 26.2% were Quantity Surveyors, 29.4% were Architects, 19.4% were Masons, and 1.9% were Valuers. Concerning academic qualifications, this study found that 45.0% held National Diplomas, 38.1% possessed a Bachelor’s of construction management and project management, 15.0% held a Master’s of project management and construction management, and 1.9% had obtained a Doctorate. Regarding company categorization, 55.6% were local, 16.3% were international, and the remaining 28.1% were (combined) joint ventures. Examining the company’s annual revenue, Table 2 discloses that 13.1% of companies reported a yearly income of less than 5 million Ugandan shillings, 16.3% had revenue between 5 to 50 million Ugandan shillings, 29.4% fell within the 51 to 235 million Ugandan shillings, 25.0% reported turnovers between 236 to 500 million Ugandan shillings, 9.4% varied from 501 million Ugandan shillings to 2 billion Ugandan shillings, and 6.9% reported yearly revenue exceeding 2 billion Ugandan shillings. Table 2 defines the respondents’ demographic synopsis, indicating that 23.1% were Civil Engineers, 26.2% were Quantity Surveyors, 29.4% were Architects, 19.4% were Masons, and 1.9% were Valuers. Concerning academic qualifications, this study found that 45.0% held National Diplomas, 38.1% possessed a Bachelor’s of construction management and project management, 15.0% held a Master’s of project management and construction management, and 1.9% had obtained a Doctorate. Regarding company categorization, 55.6% were local, 16.3% were international, and the remaining 28.1% were (combined) joint ventures. Examining the company’s annual revenue, Table 2 discloses that 13.1% of companies reported a yearly income of less than 5 million Ugandan shillings, 16.3% had revenue between 5 to 50 million Ugandan shillings, 29.4% fell within the range of 51 to 235 million Ugandan shillings, 25.0% reported turnovers between 236 to 500 million Ugandan shillings, 9.4% varied from 501 million Ugandan shillings to 2 billion Ugandan shillings, and 6.9% reported yearly revenue exceeding 2 billion Ugandan shillings.

3.1. Level of Control Practices for Planning

This section evaluates the effectiveness of control practices implemented by building construction companies. Table 3 below depicts the implications of control practices in planning, monitoring, reporting, and analysis. Table 3 presents a ranking of variables based on their significance and relevance levels. The outcomes show that the most exploited control practice for planning is the formulation of project schedules, with a mean score of 8.88. The table highlights that companies consider the formulation of project schedules a vital practice, accenting its critical responsibility in the project control process. This finding aligns with ref’s [47] assertion that breaking a project into manageable work allocations through the Work Breakdown Structure augments project control efficiency. Project feasibility validation is the second most employed control practice, receiving a mean score of 8.86. Budgeting for each activity is ranked third with a mean score of 8.84, while the key project route definition claims the fourth position with a score of 8.81. Team awareness of the budget is ranked fifth, earning a score of 8.77. Consultation from subcontractors holds the sixth position with a score of 8.74. Smooth tender transition facilitation is seventh, with a score of 8.65, while setting realistic targets for projects and merging time budget considerations are ranked eighth and ninth, with scores of 8.50 and 5.57, respectively. Companies identify the formulation of project schedules and project feasibility validation as the most prevalent practices, avowing the significance highlighted by [48].
As illustrated in Table 4, periodic monitoring protocol/routine inspection emerges as the most effective control practice for monitoring, achieving a score of 8.70. The results indicate that a preponderance of companies in the city of Kampala absorbs this control practice, aligning with the emphasis by [1], who considers periodic monitoring protocol/routine inspection a highly critical and significant approval for operational project monitoring. Office-based regular monitoring is the second most effective control practice, garnering a mean score of 8.38. This supports ref’s [1] statement that project progress monitoring through site visitation is valuable but more fundamental than dependable routine monitoring. Real-time monitoring for design adjustments is the third most effective control practice, with a score of 8.29, while time wandering along the critical path is ranked fourth, with a score of 7.75. Monitoring tender allocation for procurement compliance holds the fifth position with a score of 7.49. Ongoing tracking of key checkpoints is ranked sixth with a score of 6.75, and educating the site team about control is seventh with a score of 5.81. Subcontractors’ cost validation system implementation and project cost and time output definition are ranked eighth and ninth, receiving scores of 5.13 and 5.12, respectively [47].
Table 5 indicates that exact data capture is the most effective control practice for reporting, receiving a score of 8.57. Following closely, verifying report accuracy and honesty is the second most effective control practice, earning a score of 8.48. Building an honest and open report with management is ranked third with a score of 8.31 while reporting cost and time data verification claims the fourth position with a score of 8.06. Periodic reporting on cost and time is the fifth most effective practice, scoring 6.25. Consequently, choosing simplicity in reporting technology is the sixth most effective practice, with a score of 5.04, and integrating qualitative findings into quantitative is ranked seventh, with a score of 4.97. Report representation using quantitative tools holds the eighth position with a score of 4.75. The results underline the significance of information gathered during the monitoring stage in control practices for reporting. This aligns with the assessment of [48], who emphasized that exact data capture in reporting is a crucial element of a cost control system. Furthermore, the importance of verifying report accuracy and honesty and building an honest and open report with management is highlighted in control practices for reporting [1].
Table 6 figures out the prominence of control practices for analysis. The findings indicate that staff employment for resource evaluation is the most effective and commonly applied control practice for analysis, scoring 6.57. Following closely, workforce efficiency emphasis on project time and cost is the second most effective control practice with a score of 6.06. Establishing prices for the period and earned value ranks as the third most effective control practice, achieving a score of 5.25. In contrast, cost and time integration in the analytical process is the fourth most significant practice, scoring 5.50. Time and cost analysis prediction at project completion is the fifth considerable practice, scoring 5.07. Additionally, cost value comparison application during analysis is the sixth most significant practice with a score of 4.76, and timely access to information and encouragement ranks seventh with a score of 4.55. Evaluating performance with the use of the S-curves, the eighth scored 4.32. In brief, the research underscores that staff employment for resource evaluation is deemed the most weighty and critical control practice for analysis in the city of Kampala. This is associated with ref’s [48] assertion that staff employment for resource evaluation is vital for ensuring reports are healthy, authentic, and honorable. Thus, the presence of independent higher management-level personnel to verify the believability of reports is regarded as an exceedingly treasured control practice [48].

3.2. Level of Control Practices in the Building Construction Companies

The intensity of control measures instigated within building construction companies relates to the scope and efficiency of the contrivances and processes established by these companies to oversee and govern different facets of their undertakings. As restricted by [48], control practices encompass supervisory actions and systems crafted to guarantee the efficient and effective realization of organizational goals and objectives.
The mean rankings for the thirty-four recommended good control practices from the existing literature are presented in Table 7. Control practices with mean response ratings between 8.00 and 6.00 are categorized as “essential”. Table 7 illustrates the level of relevance of control practices related to (CPP) for planning (CPM) for monitoring (CPR) for reporting and (CPA) for analysis.
Table 7 indicates that the most critical and effective control practice among the recommended thirty-four is the formulation of the project schedule (C211), with a mean score of 8.88. Following closely behind, project feasibility validation (C212) is the second most influential and vital practice, with a score of 8.86, while budgeting for each activity (C218) is the third, with a score of 8.84. Fundamental project route definition (C213) secures the fourth position with a score of 8.81. Other essential practices include team awareness of the budget (C217), scoring 8.77; consultation from subcontractors (C215), with a score of 8.74; and periodic monitoring protocol/routine inspection (C311), with a score of 8.70. Smooth tender transition facilitation (C216) is also considered influential and vital, scoring 8.65. Exact data capture (C414) and setting realistic targets for projects (C214) follow closely with scores of 8.57 and 8.50, respectively. Verifying report accuracy and honesty (C415) is deemed essential, with a mean score of 8.48, while real-time monitoring for design adjustments/changes (C313) is considered necessary, with a mean score of 8.29. Building an honest and open report with management (C415) shows a score of 8.31, office-based regular monitoring (C3112) shows a score of 8.38, and time wandering along the critical path (C312) shows a score of 7.75. Merging time budget considerations (C219) shows a score of 7.57, monitoring tender allocation for procurement compliance (C3110) shows a score of 7.49, ongoing tracking of key checkpoints (C316) shows a score of 6.75, and staff employment for resource evaluation (C511) shows a score of 6.57. Workforce efficiency emphasis on project time and cost (C517) scores 6.06, all being considered among the most crucial control practices in the construction process. Control practices with mean scores below 6.000 are categorized as “helpful”. Remarkably, evaluating performance using S-curves (C515) is the “most helpful” practice, with a score of 4.32. At the same time, timely access to information and encouragement (C513) follows with a mean score of 4.55.
In conclusion, the results indicate that construction companies’ predominant control practices in time and cost in the city of Kampala, Uganda, are related to planning. Specifically, the practices of formulation of project schedule, project feasibility validation, budgeting for each activity, key project route definition, consultation from subcontractors, periodic monitoring protocol/routine inspection, smooth tender transition facilitation, and exact data capture are highly emphasized. These windups align with [49], supporting the idea that project managers principally carry out planning practices in various construction companies.

3.3. Examining the Impact of Control Practices on the Efficiency of Building Construction Companies

Factor analysis was used to calculate factor scores for both control practices and the performance of construction companies. The purpose was to determine the impact of project control practices on the performance of building construction companies. Then, ordinary least square regression was applied to reveal the correlation between project control practices and the performance of building construction companies.
Before initiating factor analysis to ascertain variable factor scores, the outcomes in Table 7 were dissected to ensure the appositeness of the collected data for factor analysis. The purpose of factor analysis and regression is to examine the effect of project control practices, which denotes (independent variables) on the output of building construction enterprise designates (dependent variable) [50]. Specifically, it is recommended that a minimum of five subjects per variable is necessary for factor analysis appropriateness, as suggested by [50,51], which also indicated that a sample size within the range of 150–300 would fit for analysis. With over thirty-four variables, a sample size of sixty, warranting at least three representatives from each company, provided 160 respondents, outstripping the minimum prerequisite for factor analysis. Consequently, data fittingness was assessed before conducting principal component analysis. To determine if the data were suitable for factor analysis, we used the Kaiser–Meyer–Olkin (KMO) Test and Bartlett’s tests of sphericity to ensure the adequacy of the collected data and to measure the partial correlations between the variables (dependent and independent variables) [34].

3.3.1. The KMO and Bartlett’s Test

Table 8 reveals to appraise the appropriateness and adequacy of the data distribution for factor analysis, the Kaiser–Meyer–Olkin (KMO) Test was used and run by SPSS (24.0). Refs. [34,51] alluded to a minimum KMO index value of 0.60 for factor analysis correctness. Ref. [51] projected that the data agreed that achieving a KMO index of 0.50 and Bartlett’s test of sphericity with p < 0.05 is fit for factor analysis. The table below indicates a KMO index of 0.778 (surpassing 0.5) and Bartlett’s test of sphericity with chi-square = 1135.181 at a significance level of p-value = 0.00 (should be <0.05), which was acceptable and implying that the questionnaire is valid as asserted [52,53]. These discoveries ensure that the collected data on control practices, company operations, and performances were suitable for factor analysis.

3.3.2. Total Variance Explained (TVE)

According to Table 9, the principal component analysis was used to identify linear combinations of the original variables (components or factors) that captured the maximum variance in the data. In this case, two components were extracted. The variance explained by each component is represented by Eigenvalues, where two components with Eigenvalues greater than 1.0 were retained. We use factor loadings to represent the extracted components and determine which variables significantly contribute to each component based on correlations with a cut-off of 0.3 for the original variables [54]. The variables with a factor loading above this cut-off point are considered to be associated with the respective component.
Total Variance Explained indicates the percentage of the total variance in the data explained by each component, where Factor 1 explains 63.9% of the total variance while Factor 2 explains 19.2%. Together, these two components account for approximately 83.1% of the total Cumulative Variance. Once the components have been identified, as in this case, they can be analyzed based on the variables with high factor loadings on each element. These analyses can offer valuable insights into the underlying structure of the data and help comprehend the relationships between the variables.

3.3.3. Pattern Matrix of Variables

Table 10 below shows the pattern matrix evidences the affiliation and the bond between project control practices and company operation and performance. The first factor integrates four variables related to control practices for planning, monitoring, reporting, and analyzing. In comparison, the second factor includes two variables, namely financial ability and management skills. Following [30,46], reliability is judged to be acceptable when Cronbach’s Alpha tumbles and drops within the range of 0.6 to 0.7, and it is pondered and considered satisfactory when ranging from 0.8 to 0.95. Values outside these ranges may suggest termination and redundancy; notably, Cronbach’s Alpha values in Table 10 fall within the acceptable thresholds, strengthening the validity of this study’s findings. An ordinary least square regression analysis was conducted to appraise the correlation between project control practices and the performance of the building construction company.

3.3.4. The Regression Model Summary

Table 11 outlines the strength of the association between project control practices and the performance of building construction companies.
Two variables were used in the regression model that is to say the independent variable (project control practices) comprising project scheduling, project feasibility validation, budgeting for each activity, fundamental project route definition, team awareness of the budget, consultation from subcontractors, and routine inspection and the dependent variable (performance of building construction companies) comprises financial ability and management skills. The independent variable is used to predict and explain the dependent variable, as highlighted by [55]. These variables are analyzed to determine the association between the control practices and the performance of the companies.
The positive regression coefficient, R, is 0.435, which indicates a connection between independent and dependent variables (performance of building companies and control practices). The determination coefficient (R2) of 0.184 suggests that project control practices can explain 18.4 percent of the variability in the performance of building construction companies. This proposes that 18.4 percent of the performance variation can be attributed to the project team and stakeholders’ planning, monitoring, reporting, and analyzing control practices. The 0.0010.07 significance level shows how control practices are critical to building performance. Therefore, effective and efficient control practices are considered severe components that contribute to positive building performance, as asserted by [34]. This suggests that implementing adequate and efficient control practices in the construction industry could positively impact the performance of buildings in Kampala.

3.3.5. Regression Model Coefficients

The Regression model coefficients indicate the magnitude and direction of each independent variable’s effect on the dependent variable by representing the relationship between the independent and dependent variables.
Table 12 below, according to the findings presented, shows a β1Value as the regression coefficient, which shows the change in the dependent variable (the performance indicator) for one unit change in the independent variable (control practices), keeping other factors constant, meaning that the β1 value of 0.435 suggests that for every one unit increase in control practices, there is a 43.5% increase in the performance indicators variable. The T value 7.62 is statistically significant at 0.000, indicating a low probability of obtaining such results by chance. Based on these results, the null hypothesis is rejected in favor of the alternate hypothesis, demonstrating that project control practices, the substantial β1 coefficient, and the T value support this conclusion, signifying that positive modifications in control practices are linked with positive changes in building construction companies’ performance indicators. This outcome aligns with the observations of [56], supporting the argument that critical project management practices are significantly associated with project performance and operation [55].

3.3.6. The Analysis of Variance (ANOVA)

Table 13 below presents the ANOVA, which assesses the statistical significance of the regression model and compares the networks between independent and dependent variables. The table below designates that these relationships collectively exhibit significance (F = 49.598; p = 0.000). This implies that the specified regression model is statistically significant and well incorporated [31]. This validates the understanding that the selected study variables (control practices) are joint predators of the dependent variables (performances of building companies), and the data parameters are ideal for determining the research variables. This outcome aligns with the petition by [52], which states a positive association between project control (premeditated planning) and company operation and performance.

4. Discussion

These research paper findings accentuate a significant relationship between project control practices and the performance of building construction companies in Uganda’s capital, Kampala. This research reveals compelling evidence through rigorous statistical analysis, which demonstrates that effective control practices contribute to positive results in building construction projects, and identifying specific control practices, such as planning, monitoring, and reporting, are crucial factors influencing company performance and provide valuable perceptions for stakeholders in the construction industry. The research employed well-established criteria, such as Cronbach’s Alpha test, to ensure the reliability and validity of the findings, enhancing the credibility of the research carried out.
A detailed analysis of the management practices in the context of project control measures and the company performance in building construction, as the results prove. This is carried out by squaring off different variables and practicing advanced statistical techniques. This study comprehensively explains how various control practices influence company purposes and performance. Similarly, the relevant and practical nature of this research is characterized by the use of empirical evidence collected from real-world data (actual data drawn from practical sites of construction), which plays a massive role in giving a solid base for the professionals in the construction industry and the decision makers to utilize. Such a holistic approach makes this research unique, pioneering, and distinct from the existing developments in construction management.
Even though this research has significantly advanced our perspective, a significant research gap still deserves further attention. While the analysis demonstrates a significant association between control practices and company performance, the specific instruments through which these practices influence outcomes may require deeper exploration. Factors such as project size, complexity, geographic location, and stakeholder dynamics may interact with control practices differently, modeling their impact on performance outcomes. Factors that may restrict the adoption and use of control practice implementation within construction firms include reluctance towards change, resource limits, poor technology, and organizational culture. Exploring these barriers and identifying strategies to overcome them represents a critical area for future research. Shedding light on the underlying mechanics and contextual factors determining the linkage between control policies and performance measures is one of the domains of future research work.
In a nutshell, considering the dynamic nature of the construction industry and evolving project management methodologies, there is a need for ongoing research to stay up to date on emerging trends and best practices. Future studies could explore the potential integration of emerging technologies, such as Building Information Modelling and Artificial Intelligence, into project control practices within the construction industry. Addressing these gaps would not only augment the scholarly contribution of this research but also provide actionable guidance for improving project management effectiveness in the construction sector, thus consolidating its position as an innovative endeavor in the construction discipline.

5. Conclusions

This paper inspected the level of control practices in the building construction companies in the city of Kampala, Uganda. Through a comprehensive analysis involving regression modeling and Analysis of Variance, it becomes evident that effective control practices, encompassing planning, monitoring, reporting, and analysis, play a critical role in shaping the performance indicators of construction projects in Kampala city. This research reveals a positive correlation between these control practices and key performance metrics such as financial ability, management skills, profitability, and completion time. Notably, the regression coefficient highlights that for every unit increase value of 0.435 in control practices, there is a substantial increase of 43.5 percent in the performance indicator. Furthermore, the results underscore the statistical significance of the regression model of 0.184, which suggests that project control practices can explain 18.4 percent of the variability in the performance of building construction companies, confirming the joint predictive power of control practices on building company performance. These findings underline the importance of strategic project management practices in enhancing overall operational efficiency and performance outcomes within the construction industry.
This research demonstrates the imperative role of effective project control practices in driving positive outcomes in building construction projects. The verdicts affirm that accurate planning, rigorous monitoring, and insightful analysis significantly enhance financial viability, management efficacy, and project success rates. With control practices explaining a lower percentage of 18.4 variability in performance, this study accentuates the need for stakeholders to prioritize adopting robust project management strategies. By embracing and implementing these practices, construction companies in Kampala can effectively navigate complexities, mitigate risks, and optimize performance, ultimately fostering sustainable growth and success in the ever-dynamic construction environment.

6. Recommendations

Based on the results and conclusions, contractors must carry out indispensable phases to improve project results by increasing monitoring and control efforts. This can be achieved by engaging critical stakeholders during the planning phase and proactively addressing financial and management concerns. To address the challenge of inadequate monitoring in the building construction industry, it is recommended that a standardized procedure be implemented. Comporting variance and trend analyses before each activity and action is indispensable for appropriate and effective corrective actions during the analysis phase, ensuring accurate and realistic information for cost control reporting. Furthermore, further research is essential to understand project control practices better, given the current limitations of existing studies. In conclusion, time and cost control are of dominant importance in the building construction industry and should be a priority for all stakeholders involved.

7. Limitations

Several potential challenges and limitations need to be considered in this research. One of the significant challenges is the skilled worker shortage, which means that the construction industry is facing substantial challenges. The fact that urbanization is the most pressing reason why projects are constantly growing makes it challenging to work effectively, as some tasks like planning and resource allocation require quality human capacity, which is missing. In addition, a prolonged take up of such recent technologies causes additional hurdles, with the young producers being disabled due to finance and awareness issues. This reinforces understanding of the particular problem and actions that may include interventions for upskilling and adopting innovative technologies locally.
Before performance evaluation, the primary task within the process is to combine an objective and subjective method of measuring those metrics. Success, client satisfaction, and quality indexes might behave in contradictory ways and deflect. Multiple stakeholder interests come on the stage and serve as a background for evaluation distortion. Thus, there may be inaccuracy in the evaluation of outcomes. The application of rules for criteria standardization is the main factor that supports trust and honesty in the industry.
Research in Kampala’s construction sector is facing challenges due to factors such as the restricted availability of researchers, economic status, and political situation. The shortage of expertise in the field also affects the credibility of the study results and hinders evidence-based decision making. Furthermore, researchers must navigate complex legal procedures, and inadequate infrastructure, such as an unstable communication system, makes obtaining reliable data difficult.
Despite these obstacles, solutions can be found by addressing regulatory and infrastructure barriers, improving access to skilled labor, encouraging technology adoption, and simplifying regulations. Collaboration among stakeholders is crucial for ensuring sustainable growth in Kampala’s construction sector. The industry can establish quality and efficiency benchmarks throughout Uganda by investing in strategic initiatives.

Author Contributions

Writing—original draft preparation, methodology, writing—review and editing, and resources by H.T.; conceptualization, supervision, writing—review and editing, and resources by Y.Y. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

Data is contained within the article.

Acknowledgments

The authors thank postgraduate students and academics at Liaoning Technical University who assisted during this article’s editing process. They also thank the editor and reviewers for their valuable time reviewing the manuscript.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Olawale, Y.A.; Sun, M. Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice. Constr. Manag. Econ. 2010, 28, 509–526. [Google Scholar] [CrossRef]
  2. Montes-Guerra, M.I.; Gimena, F.N.; Pérez-Ezcurdia, M.A.; Díez-Silva, H.M. The influence of monitoring and control on project management success. Int. J. Constr. Output Manag. 2014, 6, 2. [Google Scholar]
  3. Kerzner, H. Project management best practices. In Achieving Global Excellence; John Wiley & Sons: Hoboken, NJ, USA, 2018. [Google Scholar]
  4. Orumie Ukamaka, C. Implementation of Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM): A Comparative Study. Int. J. Ind. Oper. Res. 2020, 3. [Google Scholar] [CrossRef]
  5. Llach i Porcell, G. Optimization of the PERT/CPM Project Management Methodology by Implementing the Lean and Agile Philosophies. Master’s Thesis, Universtat de Barcelona, Barcelona, Spain, 2021. [Google Scholar]
  6. Doloi, H. Cost Overruns and Failure in Project Management: Understanding the Roles of Key Stakeholders in Construction Projects. J. Constr. Eng. Manag. 2013, 139, 267–279. [Google Scholar] [CrossRef]
  7. De Marco, A.; Narbaev, T. Earned value-based performance monitoring of facility construction projects. J. Facil. Manag. 2013, 11, 69–80. [Google Scholar] [CrossRef]
  8. Bagshaw, K.B. NEW PERT and CPM in Project Management with Practical Examples. Am. J. Oper. Res. 2021, 11, 215–226. [Google Scholar] [CrossRef]
  9. Turner, R.; Zolin, R. Forecasting Success on Large Projects: Developing Reliable Scales to Predict Multiple Perspectives by Multiple Stakeholders over Multiple Time Frames. Proj. Manag. J. 2012, 43, 87–99. [Google Scholar] [CrossRef]
  10. Ramanathan, C.; Narayanan, S.P.; Idrus, A.B. Construction delays causing risks on time and cost—A critical review. Constr. Econ. Build. 2012, 12, 37–57. [Google Scholar] [CrossRef]
  11. Love, P.E.D.; Smith, J.; Ackermann, F.; Irani, Z. Making sense of rework and its unintended consequence in projects: The emergence of uncomfortable knowledge. Int. J. Proj. Manag. 2019, 37, 501–516. [Google Scholar] [CrossRef]
  12. Doumbouya, L.; Gao, G.; Guan, C. Adoption of the Building Information Modeling (BIM) for construction project effectiveness: The review of BIM benefits. Am. J. Civ. Eng. Archit. 2016, 4, 74–79. [Google Scholar]
  13. Aibinu, A.A.; Jagboro, G.O. The effects of construction delays on project delivery in Nigerian construction industry. Int. J. Proj. Manag. 2002, 20, 593–599. [Google Scholar] [CrossRef]
  14. Meyer, N.; Auriacombe, C. Good Urban Governance and City Resilience: An Afrocentric Approach to Sustainable Development. Sustainability 2019, 11, 5514. [Google Scholar] [CrossRef]
  15. Khumbo, K.; Bernard, T.; Edward, C.; Adamson, T.; Grant, K. Comparative risk of pit latrine sludge from unplanned settlements and wastewater in Mzuzu City, Malawi. Afr. J. Environ. Sci. Tech. 2018, 12, 150–157. [Google Scholar] [CrossRef]
  16. Magumba, M. Key Aspects of Infrastructure Development in Uganda. J. Econ. Sustain. Dev. 2020, 11, 116–120. [Google Scholar] [CrossRef]
  17. Wali, K.I.; Othman, S.A. Comparison and assessment of using Primavera and Microsoft projects in construction projects in Erbil City. Zanco J. Pure Appl. Sci. 2019, 31, 285–291. [Google Scholar]
  18. Muhwezi, L.; Acai, J.; Otim, G. An Assessment of the Factors Causing Delays on Building Construction Projects in Uganda. Int. J. Constr. Eng. Manag. 2014, 3, 13–23. [Google Scholar] [CrossRef]
  19. Loosemore, M.; Lim, B.T.H. Linking corporate social responsibility and organizational performance in the construction industry. Constr. Manag. Econ. 2017, 35, 90–105. [Google Scholar] [CrossRef]
  20. Linkov, I.; Satterstrom, F.K.; Kiker, G.; Batchelor, C.; Bridges, T.; Ferguson, E. From comparative risk assessment to multi-criteria decision analysis and adaptive management: Recent developments and applications. Environ. Int. 2006, 32, 1072–1093. [Google Scholar] [CrossRef] [PubMed]
  21. Kivilä, J.; Martinsuo, M.; Vuorinen, L. Sustainable project management through project control in infrastructure projects. Int. J. Proj. Manag. 2017, 35, 1167–1183. [Google Scholar] [CrossRef]
  22. Khalife, S.; Hamzeh, F. A Framework for Understanding the Dynamic Nature of Value in Design and Construction. In Proceedings of the 27th Annual Conference of the International Group for Lean Construction (IGLC), Dublin, Ireland, 1–7 July 2019; pp. 617–628. [Google Scholar] [CrossRef]
  23. Kerzner, H. Project Management: A Systems Approach to Planning, Scheduling, and Controlling; John Wiley & Sons: Hoboken, NJ, USA, 2017. [Google Scholar]
  24. Klein, C.; Lester, J.; Rangwala, H.; Johri, A. Technological barriers and incentives to learning analytics adoption in higher education: Insights from users. J. Comput. High. Educ. 2019, 31, 604–625. [Google Scholar] [CrossRef]
  25. De Jong, G.; Van Witteloostuijn, A. Regulatory Red Tape and Private Firm Performance. Public. Adm. 2015, 93, 34–51. [Google Scholar] [CrossRef]
  26. Kaming, P.F.; Olomolaiye, O.C. Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Constr. Manag. Econ. 1997, 15, 83–94. [Google Scholar] [CrossRef]
  27. Faniran, O.O.; Love, P.; Smith, J. Effective front-end project management—A key element in achieving project success in developing countries. In Proceedings of the Construction Development Conference, Las Vegas, NV, USA, 21–23 January 2020. [Google Scholar]
  28. Pimchangthong, D.; Boonjing, V. Effects of Risk Management Practices on IT Project Success. Manag. Prod. Eng. Rev. 2017, 8, 30–37. [Google Scholar] [CrossRef]
  29. Umar, T. Key factors influencing the implementation of three-dimensional printing in construction. Proc. Inst. Civ. Eng.—Manag. Procure. Law 2021, 174, 104–117. [Google Scholar] [CrossRef]
  30. Alinaitwe, H.; Ayesiga, R. Success Factors for the Implementation of Public-Private Partnerships in the Construction Industry in Uganda. J. Constr. Dev. Ctries. 2013, 18, 1–14. [Google Scholar]
  31. Taherdoost, H. What are Different Research Approaches? Comprehensive Review of Qualitative, Quantitative, and Mixed Method Research, Their Applications, Types, and Limitations. J. Manag. Sci. Eng. Res. 2022, 5, 53–63. [Google Scholar] [CrossRef]
  32. Zou, P.X.W.; Sunindijo, R.Y.; Dainty, A.R.J. A mixed methods research design for bridging the gap between research and practice in construction safety. Saf Sci 2014, 70, 316–326. [Google Scholar] [CrossRef]
  33. Darusi, D.M.; Makokha, E.N. Determinants of public participation in the sustainability of county government project in Uasin Gishu County. Int. J. Recent Res. Soc. Sci. Humanit. 2018, 5, 285–293. [Google Scholar]
  34. Dixit, S. Analyzing Enabling Factors Affecting the On-site Productivity in Indian Construction Industry. Period. Polytech. Archit. 2018, 49, 185–193. [Google Scholar] [CrossRef]
  35. Castillo, T.; Alarcón, L.F.; Pellicer, E. Finding Differences among Construction Companies’ Management Practices and Their Relation to Project Performance. J. Manag. Eng. 2018, 34, 1–13. [Google Scholar] [CrossRef]
  36. world cities. World population. Retrieved from. 2023. Available online: https://worldpopulationreview.com (accessed on 25 July 2023).
  37. Twinomuhangi, R.; Sseviiri, H.; Mulinde, C.; Mukwaya, P.I.; Nimusiima, A.; Kato, A.M. Perceptions and vulnerability to climate change among the urban poor in Kampala City, Uganda. Reg Env. Chang. 2021, 21, 39. [Google Scholar] [CrossRef]
  38. Pehčevo Weather Forecast. Retrieved from Current Temperature & Conditions. 2023. Available online: https://NearWeather.com (accessed on 3 August 2023).
  39. Awange, J.L.; Ong’ang’a, O. Kampala Serves as Uganda’s National and Commercial Capital and Borders Lake Victoria, the Largest Lake in Africa; Springer Science & Business Media: Berlin/Heidelberg, Germany, 2006; Volume 354. [Google Scholar]
  40. Martins, C.L.; Pato, M.V. Supply chain sustainability: A tertiary literature review. J. Clean. Prod. 2019, 225, 995–1016. [Google Scholar] [CrossRef]
  41. Bryman, A. Quantitative and qualitative research: Further reflections on their integration. In Mixing Methods: Qualitative and quantitative research; Routledge: London, UK, 2017; pp. 57–78. [Google Scholar] [CrossRef]
  42. Lak, A.; Ramezani, M.; Aghamolaei, R. Reviving the lost spaces under urban highways and bridges: An empirical study. J. Place Manag. Dev. 2019, 12, 469–484. [Google Scholar] [CrossRef]
  43. Ametepey, O.; Aigbavboa, C.; Ansah, K. Barriers to Successful Implementation of Sustainable Construction in the Ghanaian Construction Industry. Procedia Manuf. 2015, 3, 1682–1689. [Google Scholar] [CrossRef]
  44. Emerson, R.W. Convenience Sampling, Random Sampling, and Snowball Sampling: How Does Sampling Affect the Validity of Research. J. Vis. Impair. Blind. 2015, 109, 164–168. [Google Scholar] [CrossRef]
  45. Gambo, N. A conceptual framework for improving cost and building contractor performances in developing countries. In Proceedings of the 7th International Real Estate Research Symposium (IRERS) 2014, National Institute of Valuation (INSPEN), Selangor, Malaysia, 29–30 April 2014. [Google Scholar]
  46. Abowitz, D.A.; Toole, T.M. Mixed Method Research: Fundamental Issues of Design, Validity, and Reliability in Construction Research. J. Constr. Eng. Manag. 2010, 136, 108–116. [Google Scholar] [CrossRef]
  47. Dey, P.K. Managing projects in fast track—A case of public sector organization in India. Int. J. Public Sect. Manag. 2000, 13, 588–609. [Google Scholar] [CrossRef]
  48. Olawale, Y.; Sun, M. Construction project control in the UK: Current practice, existing problems, and recommendations for future improvement. Int. J. Proj. Manag. 2015, 33, 623–637. [Google Scholar] [CrossRef]
  49. Ahmadu, B. An empirical survey on production planning practice of Nigeria’s small and medium-sized construction firms. Int. J. Eng. Res. Technol. IJERT 2014, 3. Available online: http://repository.futminna.edu.ng:8080/jspui/handle/123456789/10596 (accessed on 10 March 2024).
  50. Coakes, S.J.; Steed, L.G. Multiple responses and multiple dichotomy analysis. In SPSS: Analysis without anguish: Version 11.0 for Windows; Wiley: Hoboken, NJ, USA, 2003. [Google Scholar]
  51. Hair, J.F.; Black, W.; Babin, B.J.; Anderson, R.E. Multivariate Data Analysis: A Global Perspective, 7th ed.; Pearson. 2010. Available online: https://www.researchgate.net/publication/237009923_Multivariate_Data_Analysis_A_Global_Perspective (accessed on 10 March 2024).
  52. Alzubi, K.M.; Alkhateeb, A.M.; Hiyassat, M.A. Factors affecting the job satisfaction of construction engineers: Evidence from Jordan. Int. J. Constr. Manag. 2023, 23, 319–328. [Google Scholar] [CrossRef]
  53. Tayeh, B.A.; Aisheh, Y.I.A.; Abuzuhri, I.O. Factors Affecting Sustainability Performance during the Construction Stage in Building Projects-Consultants’ Perspective. Open Constr. Build. Technol. J. 2020, 14, 17–26. [Google Scholar] [CrossRef]
  54. Pallant, J. SPSS Survival Manual: A Step by Step Guide to Data Analysis Using IBM SPSS; Routledge: London, UK, 2020. [Google Scholar] [CrossRef]
  55. Welsch, R.; Kuh, E. Linear Regression Diagnostics; National Bureau of Economic Research: Cambridge, MA, USA, 1977. [Google Scholar] [CrossRef]
  56. Milosevic, D.; Patanakul, P. Standardized project management may increase development projects success. Int. J. Proj. Manag. 2005, 23, 181–192. [Google Scholar] [CrossRef]
Figure 1. Research area map.
Figure 1. Research area map.
Buildings 14 01818 g001
Table 1. Selection technique, targeted, sampled population, and sample size.
Table 1. Selection technique, targeted, sampled population, and sample size.
ProfessionCompaniesFrequency/PopulationSize SampledPercentageSampling Technique
Consultancy CompaniesMaintenance CompaniesEstate DeveloperBuilding and Construction
Civil Engineer44623374523.1Purposive sampling
Quantity Surveyors64725425026.2Simple random sampling
Masons22324314019.4Purposive sampling
Architects541325475029.4Purposive sampling
Valuers1--203051.9Simple random sampling
Total18142999160190100
Table 2. Demographic details regarding the respondents.
Table 2. Demographic details regarding the respondents.
VariablesCategorizationFrequencyPercentage
Quantity Surveyors4226.2
ProfessionArchitects4729.4
Masons 3119.4
Civil Engineers3723.1
Valuers31.9
Total160100.0
National Diploma 7245.0
Education levelBachelor’s Degree6138.1
Master’s Degree2415.0
Doctorate31.9
Total160100.0
Local8955.6
Company typeInternational2616.3
Joint Venture/Combined4528.1
Total160100.0
<5 million2113.1
Company yearly revenue5–50 million2616.2
51–235 million4729.4
236–500 million4025.0
501 million–2 billion159.4
Above 2 billion116.9
Total160100.0
Table 3. Descriptive statistics on the level of planning control practices.
Table 3. Descriptive statistics on the level of planning control practices.
Control Practices for PlanningMeanStd. DeviationRank
Formulation of project schedule8.883.09091
Project feasibility validation8.861.92352
Key project route definition8.811.76764
Setting realistic targets for projects8.501.70298
Consultation from subcontractors8.741.96776
Smooth tender transition facilitation8.652.12437
Team awareness of the budget8.771.86765
Budgeting for each activity8.841.62393
Merging time budget considerations7.572.09719
Table 4. Descriptive statistics on the level of control practices for monitoring.
Table 4. Descriptive statistics on the level of control practices for monitoring.
Monitoring Control PracticesMeanStd. DeviationRank
Periodic monitoring protocol/routine inspection8.702.04931
Time wondering along the critical path7.751.93654
Real-time monitoring for design adjustments/changes8.292.02413
Project cost and time output definition5.121.44679
Ongoing tracking of key checkpoints6.755.24406
Subcontractors’ cost validation system implementation5.131.51018
Monitoring tender allocation for procurement compliance7.492.23595
Office-based regular monitoring8.382.16522
Educating the site team about control5.811.74567
Table 5. Descriptive statistics on the level of control practice for reporting.
Table 5. Descriptive statistics on the level of control practice for reporting.
Reporting Control PracticesMeanStd. DeviationRank
Reporting cost and time data verification8.061.15734
Verifying report accuracy and honesty8.482.53972
Periodic reporting on cost and time6.252.07025
Exact data capture8.572.36781
Building an honest and open report with management8.312.22833
Report representation using quantitative tools4.752.07028
Choosing simplicity in reporting technology5.041.00846
Integrating qualitative findings into quantitative4.971.64517
Table 6. Descriptive statistics on the level of control practice for analysis.
Table 6. Descriptive statistics on the level of control practice for analysis.
Analyzing Control PracticesMeanStd. DeviationRank
Staff employment for resource evaluation 6.572.37191
Time and cost analysis prediction at project completion5.071.25955
Timely access to information and encouragement4.552.37257
Cost and time integration in the analytical process5.502.39054
Evaluating performance with the use of S-curves4.322.21638
Cost value comparison application during analysis4.762.07076
Workforce efficiency emphasis on project time and cost6.061.15732
Establishing costs for the period and earned value5.252.07023
Table 7. The descriptive statistics level of relevance of control practices.
Table 7. The descriptive statistics level of relevance of control practices.
RaftsProgramControl PracticeMeanStd. DeviationRank
C211Formulation of project schedule8.883.09091
CPPC212Project feasibility validation8.861.92352
C213Key project route definition8.811.76764
C214Setting realistic targets for projects8.501.702910
C215Consultation from subcontractors8.741.96776
C216Smooth tender transition facilitation8.652.12438
C217Team awareness of the budget8.771.86765
C218Budgeting for each activity8.841.62393
C219Merging time budget considerations7.572.097117
C311Periodic monitoring protocol/routine inspection8.702.04937
CPMC312Time wondering along the critical path7.751.936516
C313Real-time monitoring for design adjustments/changes8.292.024114
C314Project cost and time output definition5.121.446727
C316Ongoing tracking of key checkpoints6.755.244019
C318Subcontractors’ cost validation system implementation5.131.510126
C3110Monitoring tender allocation for procurement compliance7.492.235918
C3112Office-based regular monitoring8.382.165212
C3113Educating the site team about control5.811.745623
CPRC411Reporting cost and time data verification8.061.157315
C412Verifying report accuracy and honesty8.482.539711
C413Periodic reporting on cost and time6.252.070221
C414Exact data capture8.572.36789
C415Building an honest and open report with management8.312.228313
C417Report representation using quantitative tools4.752.070232
C418Choosing simplicity in reporting technology5.041.008429
C419Integrating qualitative findings into quantitative4.971.645130
C511Staff employment for resource evaluation 6.572.371920
CPAC512Time and cost analysis prediction at project completion5.071.259528
C513Timely access to information and encouragement4.552.372533
C514Cost and time integration in the analytical process5.502.390524
C515Evaluating performance with the use of S-curves4.322.216334
C516Cost value comparison application during analysis4.762.070731
C517Workforce efficiency emphasis on project time and cost6.061.157322
C518Establishing costs for the period and earned value5.252.070225
CPP—control practice for planning → C211–C219; CPM—control practice for monitoring C311–C3113; CPR—control practice for recording → C411–C419; CPA—control practice for analyzing → C511–C518.
Table 8. KMO and Bartlett’s test for the effect of control practice on performance.
Table 8. KMO and Bartlett’s test for the effect of control practice on performance.
KMO and Bartlett’s Test
Kaiser–Meyer–Olkin Measure of Sampling Adequacy0.778
Bartlett’s Test of SphericityApprox. Chi-Square1135.181
Df36
Sig.0.000
Table 9. Total Variance Explained (TVE) for project control.
Table 9. Total Variance Explained (TVE) for project control.
ComponentInitial EigenvaluesExtraction Sums of Squared LoadingsRotation Sums of Squared Loadings
Total% of VarianceCumulative %Total% of VarianceCumulative %Total
15.11363.90863.9085.11363.90863.9084.786
21.54019.25683.1641.54019.25683.1642.910
30.81410.17693.340
40.2262.82796.166
50.1371.70697.873
60.0921.14699.019
70.0790.981100.000
Table 10. Pattern matrix of variables.
Table 10. Pattern matrix of variables.
Factor Loading Component12
Planning control practices 0.812
Monitoring control practices 0.791
Reporting control practices 0.861
Analyzing control practices 0.866
Financial ability 0.623
Management skills 0.873
Cronbach’s Alpha (reliability test)0.8960.702
Table 11. The regression model summary.
Table 11. The regression model summary.
ModelRR SquareAdjusted R SquareSign’
Control practices0.435 a0.1860.1840.001
“a” shows that the correlation coefficient (R) of 0.435 is statistically significant.
Table 12. Regression model coefficients.
Table 12. Regression model coefficients.
ModelUnstandardized CoefficientsStandardized CoefficientsTSig.
BStd. ErrorBeta
1(Constant)1.780 × 10−160.621 0.0001.00
Control practices 0.4060.0950.4357.620.000
Table 13. The Analysis of Variance (ANOVA).
Table 13. The Analysis of Variance (ANOVA).
ModelSum of SquaresdfMean SquareFSig.
1Regression31.678431.67849.5980.00 b
Residual159.2381030.420
Total160.917107
“b” indicates that the p-value is extremely small, likely less than the standard significance level of 0.05.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Tukundane, H.; Yang, Y. Effect of Project Control Practices on the Performance of Building Construction Companies in Uganda: A Case Study of the City of Kampala. Buildings 2024, 14, 1818. https://doi.org/10.3390/buildings14061818

AMA Style

Tukundane H, Yang Y. Effect of Project Control Practices on the Performance of Building Construction Companies in Uganda: A Case Study of the City of Kampala. Buildings. 2024; 14(6):1818. https://doi.org/10.3390/buildings14061818

Chicago/Turabian Style

Tukundane, Hillary, and Yu Yang. 2024. "Effect of Project Control Practices on the Performance of Building Construction Companies in Uganda: A Case Study of the City of Kampala" Buildings 14, no. 6: 1818. https://doi.org/10.3390/buildings14061818

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop