1. Introduction
Monitoring of the impact of works on the environment is one of the most important elements enabling the safe implementation of investment projects in urban development [
1,
2]. Due to the fact that works are carried out near existing buildings, including high-rise buildings, various types of observations and measurements must be carried out, on the basis of corrections in the field of works technology (e.g., reducing the amplitudes of vibrations, using a different type of driving element in the ground, changing the frequency of soil compaction, etc.) as well as suitable safety measures that can be introduced [
3]. Currently, due to the increasingly scarce availability of land for development, investors are often forced to carry out construction works near other facilities [
4] (with a risk of damaging adjacent buildings) and on poor grounds [
5] (e.g., anthropogenic embankments with a high variability of granulometric composition and state of compaction, organic soils, etc.). Effective methods of ground improvement as well as technologies which allow the introduction of structural elements constituting an intermediate foundation or protection of scarps or excavation walls use shocks or vibrations [
6]. They are usually destructive to nearby structures and can cause various types of damage, breakdowns, or even construction disasters. In addition, due to the need to optimize spatial development, it is often necessary to make deep excavations, which may also pose a threat to existing buildings [
7,
8,
9,
10].
Properly implemented monitoring should comprise a comprehensive program of continuous observation, which would enable a fast reaction in the event of a threat [
11,
12]. Such a program must be properly planned at the design stage and properly implemented during construction works. Sometimes, measurements and observations during the operation stage are also provided for, as harmful influences may also occur during this period [
13,
14].
One of the most destructive impacts of dense urban development involves deep excavation works. Very often, the level of the trench bottom is lower than the foundation level of the neighboring objects, and the works are carried out in close contact with another building. Often, the neighboring structures are in bad technical condition, or their structures are very sensitive to additional horizontal displacements and settlements resulting from the works being carried out, and hence very strict restrictions in this respect are imposed [
15,
16]. A separate problem is to ensure the stability of high scarps or walls of the excavations under high ground load. Another type of harmful effect involves a temporary lowering of the groundwater level during the excavation works [
17]. Such a lowering may be from a few to a dozen or so meters and can cause additional settlements of up to several cm [
18]. Especially in the case of complex ground conditions, uneven settlement may be the cause of various types of structural damage. Despite the increase in the value of mean stresses in the subsoil, which generally increases the subsoil bearing capacity, accompanying settlements under existing buildings is almost always a danger.
Particularly, destructive effects occurring during the execution of construction works are shocks and the result of vibrations propagating in the soil medium [
19]. Since typical building structures, located in non-seismic areas, are not resistant to such influences, we can frequently observe damage or failures effected by dynamic influences. Some of the applied ground strengthening technologies, such as, for example, dynamic consolidation, making stone columns, or driving prefabricated piers or elements of sheet piling, may cause similar damage, as in the case of seismic or paraseismic tremors (e.g., mining tremors). Harmful vibrations can also occur during the transport of materials or other types of movement of heavy vehicles or construction machinery.
In the south of Poland, where the monitored investments described in the article were implemented, mining deformations are a significant problem accompanying construction sites. They are manifested by a lowering of the surface area, and additionally, inclinations, curvature of the surface area, and horizontal deformations. Mining deformations also adversely affect buildings and infrastructure elements within the impact range, sometimes causing damage. Sometimes, different kinds of influences overlap with the final deformation of the surface area, which translates into settlement and horizontal displacement of buildings. Hence, there is a need to take into account all factors that may affect the course of the monitored process [
20,
21,
22]. Only in this case can the results of monitoring be reliable and contribute to the protection of endangered objects.
Due to the nature of the impacts caused by construction works on neighboring facilities, the standards in force in Poland impose very strict requirements in terms of permissible values (displacements and vibration amplitudes), which often prevents the use of some very effective technologies, and sometimes also puts into question the realization of some investments in dense building developments. On the other hand, predictions often differ from later observations. Additionally, the technical condition of the structures subjected to hazard or ground conditions in the place where the works are carried out has a great influence. Hence, monitoring of the impact is very often a prerequisite for safe implementation of an investment project. The aim of the article is to present the experience gained during the implementation of the monitoring ring, using the examples of two large investments in Silesia. Possible measurement techniques were tried, which can be applied in practice for many larger building investments.
2. Materials and Methods
The following part of the article presents the monitoring of two large investments carried out in Katowice in the south of Poland (
Figure 1). The first one is the construction of a tunnel under the roundabout along an intercity route through the city center. The second one is the construction of a large housing estate. Both projects were carried out in the vicinity of other buildings, hence many facilities were within the range of impact of the realized construction works.
The first element involving the monitoring of the impact of works on the structural condition of objects is the inventory of the state of objects at risk of the impact. The scope of observation and, above all, the requirements involving permissible impacts, should depend on the type of structure and its technical condition. For new structures in good condition, slightly higher impacts may be allowed. Yet, when the inventory reveals the presence of excessive damage, it may necessitate a change in the execution technology of works, or the use of additional reinforcements or protections. When assessing the technical condition of objects before starting monitoring, special attention should be paid to visible cracks, in particular on reinforced concrete and masonry structures (
Figure 2b). Cracks on finishing elements (plaster, glaze, etc.) do not constitute any threat to the safety of use of the object, yet they indicate the occurrence of accelerated wear of the object and are the first sign of the object’s lower resistance to future impacts.
The monitoring should be carried out on the basis of an appropriate design project. Detailed arrangements regarding the types and frequency of observations, as well as the procedures to be followed in the event of excessive impacts, should take into account the technology used for the execution of works, the relevant safeguards, and the conclusions from the inventory of technical conditions. An appropriate monitoring program should optimize the number of tests and observations to be carried out, the frequency, and costs. It must not be forgotten that some tests may be burdensome for the contractor. Nowadays, increasingly complex automatic measurement systems are used, which enable quick detection of the risk of unfavorable impacts on objects [
23,
24].
A particularly important aspect of the presented monitoring involves the observation of the development of cracks noticed during the inventory. A plexiglass plate is glued to existing cracks (
Figure 2b), which enables the observation of the development of cracks during the execution of works, in particular the growth of their openings. Modern monitoring and diagnostic programs of structures use crackmeters for measurements [
25]. Additionally, the observation should take into account the development of a new cracks or other damage. The above observations are the most significant data to be applied for expert assessments involving the harmfulness of the impacts on a given object.
The first of the presented types of research is observation of the groundwater level, which is lowered at the stage of excavation and construction of underground elements. To determine the extent of lowering, piezometers made beforehand in the subsoil are used. They consist of a perforated pipe covered with sand. Inside it, the groundwater stabilizes on an ordinate consistent with its piezometric level in the surrounding ground. The measurement of this level is carried out by a device inserted inside the pipe into the water collected inside it. The measurement can be carried out in a traditional way with the use of devices emitting an acoustic signal when contacted with the water surface, or in an electronic way. In modern systems, we can also measure water temperature, direction, and speed of filtration, and we can monitor the quality of water and its degree of contamination [
26].
It is particularly important in the applied monitoring to perform geodetic measurements of settlement and displacements in the horizontal plane. Measurements of this type have been used for a long time, and they have been now innovated by the introduction of automation in measurements, which allows for faster responses when the permissible values are exceeded [
27,
28]. Reports on geodetic measurements enable to analyze the impact of works on neighboring buildings at any time. The implementation of geodetic measurements requires prior installation of benchmarks (for the measurements of settlements) and measurement points (for monitoring displacements), which make up the measurement matrix (
Figure 2a). The design of such a control system should be based on the assessment of the range of anticipated impacts and the inventory of damage identified before the commencement of works.
Finally, the last of the discussed methods involves measurements of vibrations generated on the structures of objects which are within the range of impact. Most often, accelerometers (
Figure 3a) are used to measure accelerations in the structural elements of objects [
29,
30]. Less frequently, the amplitudes of displacements or velocities are measured. To be able to realistically assess the destructive impact, in addition to the amplitude values, it is also important to know the corresponding frequencies. The frequency range most dangerous for building structures is 5–25 Hz (
Figure 3b). In some countries, appropriate monograms have been developed to assess the vibration risk level for certain types of buildings. In general, the permissible values should be determined on the basis of structure type and the technical conditions of a given building. Vibration monitoring is particularly helpful in verifying the safety measures used during the works.
While discussing various types of measurements carried out in-situ with sensors installed on the structures of monitored buildings, the accuracy of the measurements must not be overlooked. The accuracy of geodetic measurements (both settlements and deflections of objects) can reach ± 1 mm. Currently used measuring instruments can offer greater precision of measurement, however, for the purposes of monitoring, such accuracy is sufficient. In the case of groundwater level measurements in piezometers, an accuracy of ± 0.1 m is completely sufficient. It allows for a sufficiently precise assessment of the influence on the behavior of nearby objects. On the other hand, vibration measurements should already be carried out with greater accuracy. It is easiest to carry out the acceleration measurements, where most of the commonly used equipment ensures a measurement accuracy of ±1 mm/s
2. Such accuracy allows the use of various types of scales (
Figure 3b) developed to assess the impact of dynamic influences. In Polish standards, the basic quantity at which the impact of vibrations on structures is assessed is the acceleration amplitude, although in many other countries such a quantity is the velocity amplitude. Measurements of velocity and displacements of vibration would require using equipment that guarantees a much greater precision of measurements, hence such measurements are less often used in practice.
It is of great importance when designing a monitoring system to be able to define the frequency of the measurements carried out. During the realization of earthworks and geoengineering works, the intervals between measurements should be short enough to react duly to a possible threat to the safety of neighboring buildings. These intervals can be slightly extended right after the completion of the works (their effects may remain in the structures for some time). Frequently, monitoring is also carried out during the operation of the finished object, when the frequency of measurements is even lower. Sometimes the dates of tests are selected based on weather conditions (season of year). In the past, due to costs, it was necessary to limit the number of measurements and the time of monitoring. Currently, with the introduced automation of measurement, registration processes, archiving, and even automatic responses, the costs of monitoring are much lower, hence the growing popularity of its use. The monitoring system fits perfectly into the BIM system, which is becoming standard in the implementation of larger investments [
31].
4. Discussion
The monitoring results presented above in both examples (the construction of a tunnel under the roundabout and the “Oak Terraces” housing estate in Katowice), clearly indicate the considerable impact of the carried-out works on adjacent buildings. There is a visible time-based relationship between the dates of work execution and the formation of settlements or inclinations identified about 1–2 months later (see plots in
Section 3, where the types of technology with the resulting displacements can be compared). The resulting additional settlements can reach even more than 40 mm, which in the case of tall objects that exert considerable pressure through the foundations on the ground, may already be regarded as a potential risk of failure. The above value of settlement is approximately equal to the value allowed by the serviceability limit state, therefore creating additional settlements of this value is often dangerous for the structure (and risk reaching the ultimate limit state). In general, it is not possible to define strict boundaries, as the safety of a specific object depends on many factors (e.g., technical condition of the building, type of structure, ground conditions, etc.). In the case of tall objects, the inclination can also be considerable; in extreme cases it can even reach 150 mm. The vast majority of settlements and inclinations remain permanent—after finishing of the works, the object does not return to its original position. Moreover, the lowering of the groundwater level has a meaningful impact on subsidence. Currently, efforts are made to prevent the depression crater from extending beyond the plot on which the investment project is being carried out. In situations where geotechnical conditions do not allow it (e.g., non-cohesive soils at great depth), observation of changes in the water level is a particularly important element of monitoring. In some objects, significantly lower settlements and displacements were found (
Figure 13 and
Figure 15), which may indicate that these buildings are less endangered by the impacts caused by construction works. This may be due to the greater distance of the building from the place of works (e.g., buildings at Sokolska Street or the skyscrapers in the “Stars” estate, which are further away from the construction site, have low pressure on the ground (e.g., commercial pavilions) or a compact and rigid solid of the facility (e.g., the bank building)). Settlement is also often influenced by ground conditions, causing less deformation of the area around buildings and a better technical condition of the building’s structure.
There is a noticeable coincidence in the time of construction works with the occurrence of settlements and deflection of objects within the range. It can be concluded that most often deformations measured on neighboring buildings appear about 2 months after excavation, lowering the water level or other types of works that have a large impact on the neighborhood.
It was feared that excessive and uneven settlement of buildings could damage the structure of buildings, leading to building failures. These damages are manifested in the appearance of cracks in masonry or concrete structures [
34]. An example of a crack on the structure is shown in
Figure 2b and
Figure 20. Hence, the need for monitoring, which allows for a quick response, consisting in changing the technology of works, execution of security or ad hoc repairs. Results of the monitoring results will also allow to determine the real impact of the works on specific damages. In the case of the two presented realizations, only a slight increase in the opening or enlargement of some cracks was found, which in no case led to a failure. Of course, there was a need to make a few repairs, but the cost of this was negligible in relation to the investment value.
In the case of smaller objects (e.g., single family houses), additional settlements and inclinations, regardless of the measured values, are not too much of a problem. This is due to the compact and rigid building structure and lower requirements (compared to large buildings) in terms of the serviceability limit state. Yet, the problem may involve the deterioration of the technical conditions of such buildings as a result of impacts from the construction site. Hence, it is essential to measure the vibration amplitudes, which in such cases are the decisive factor. It is also essential to observe the development of cracks and damage, which can be extremely helpful when choosing the technology of work execution. A detailed report on the rise of damage may also be helpful in resolving claims for compensation. It is important to have the inventory of damages prior to the commencement of works, so that the investor is not forced to pay for the damage incurred prior to the commencement of works.
The results of the monitoring presented above indicate that in the case of earthworks, in particular those carried out below the groundwater level, it is essential to measure the current water level with piezometers. It can be roughly assumed that the reduction of water level by 1 m can result in additional settlements of about 1 mm (assuming an active depth of 5 m and an average modulus of elasticity of the subsoil 50 MPa, the above value may be slightly different depending on the type of soil). With the lowering of up to a few meters, this is not a big problem for the condition of the building structure, but when the lowering is larger, additional settlements may contribute to a failure. In the case of the construction of the roundabout in Katowice, the change in ground water level did not exceed 2 m, because of the proper operation of the diaphragm walls, although they were not brought to impermeable soil.
The frequency of measurements (see
Table 1) was adjusted to the work schedule. In the periods of higher intensity of construction works, measurements were carried out more often, while at the time when the impact of these works on the resulting settlement was smaller, measurements were carried out less often. Generally, in the case of large construction investments with typical soils in Poland, there is no need for measurements more frequent than once every 2 weeks. It should not be forgotten that more frequent measurements are more expensive, which can be a problem in some countries. The accuracy of the measurements of displacements (including settlements), as well as the amplitudes and frequencies of vibrations mentioned in
Section 2, turned out to be sufficient to assess the impact of the works on the neighborhood.
In the case of the construction of the tunnel under the roundabout, the greatest concern was the fall of the groundwater level, which was predicted over a large area. Deep excavations could also be dangerous, but they were secured by diaphragm walls. The monitoring results showed that although some settlements and horizontal displacements were found, there was no greater threat to the safety of the structures of adjacent buildings. It also turned out to be beneficial that no mining deformation occurred during the construction works, which would constitute an additional risk of failure. The location of the investment (the center of a large city) was essential here, because there is no mining activity causing large deformations of the land surface, as well as the final phase of coal extraction in Upper Silesia in Poland.
In the case of the construction of the Dębowe Tarasy estate, the main problem was vibrations and their destructive impact on the neighborhood. The vibrations caused by use of the heavy ramming method to soil improvement. Fears were intensified by the poor technical condition of the adjacent buildings. Monitoring carried out in some places indicated the need to reduce the energy of ramming, which allowed the destructive influence of the works on the neighborhood to be minimized.
5. Conclusions
The monitoring of impacts is particularly important in the context of the influence exerted by an investment project on its neighborhood, which was demonstrated with the examples included in the article. With less and less access to investment areas, contractors often have to face the problem of limiting the impact on nearby facilities. In extreme cases, these influences may cause failure and sometimes even destruction of objects. The main objective of monitoring is to develop a capability for making quick adjustments to the applied work execution technology or to introduce additional safety measures. Nowadays, monitoring is becoming an indispensable element of the realization of larger building investment projects. The realization of monitoring begins at the design stage, when the inventory of objects within the impact range should be made. The most important aspect of the monitoring involves measurement and observation during works, when the impact on the neighborhood is the highest. Frequently, the realization of monitoring also extends to the period after the completion of construction works when the operation of the newly built facility starts. We can also indicate here such investment projects as the A1 motorway running through Piekary Śląskie, where there is a risk of significant mining deformations. In such situations, the monitoring system is inextricably linked to the operation of this motorway and is a prerequisite for users’ safety.
The implementation of monitoring fits perfectly into the observation method of simultaneous design and realization of investments. This method has been included in the current Eurocode 7 standard. Monitoring, based on the two presented examples, allowed for the efficient performance of works without worrying about the safety of neighboring objects. Only a small amount of minor damage was found, which, however, is unavoidable with such large investments. It turned out that the noise from the construction site as well as dust or dirt on the roads were a greater nuisance for the residents and users of the monitored facilities. The vibrations were also annoying, but they lasted for a relatively short time. On the other hand, the carried-out monitoring of the impacts made it possible to determine that there was no threat to the condition of building structures of nearby facilities.
On the basis of the analyzes presented in the article, it is possible to present “good practices” in the field of monitoring investments carried out in urban areas or near other facilities. These principles are summarized in the below
Table 2.