Next Article in Journal
Volumetric Analysis of Aortic Changes after TEVAR Using Three-Dimensional Virtual Modeling
Previous Article in Journal
Identification, Evaluation, and Influencing Factors of Soundscapes in Public Open Spaces in High-Density Residential Areas
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Operationalisation of Building Inspections and Repair: Systematisation-Based Approach

CERIS, Instituto Superior Técnico, University of Lisbon, Av. Rovisco Pais, 1, 1049-001 Lisboa, Portugal
*
Author to whom correspondence should be addressed.
Appl. Sci. 2024, 14(16), 6947; https://doi.org/10.3390/app14166947
Submission received: 23 April 2024 / Revised: 22 June 2024 / Accepted: 22 July 2024 / Published: 8 August 2024

Abstract

:

Featured Application

This article applies to building maintenance and the life-cycle assessment of repair operations.

Abstract

The possibility of diagnosing and repairing specific sets of defects (those with more severe consequences and impact on the degradation of building components) with the same means is considered. It is important to optimise the planning and kick-off of building inspections by using, from the start, a predetermined set of equipment and to optimise the maintenance and rehabilitation of the building envelope in terms of funds invested and resources. An existing methodology is used to create inter-defect correlation matrices, taking into account an expert knowledge-based building inspection system. The main results include a set of essential diagnosis methods—crack measuring and monitoring; temperature and moisture measurement; infrared thermography; and water absorption tests—and the identification of the most transversal repair techniques—cleaning; protection coating; replacement/reapplication of claddings/glazing; re-application of finishing coats or more adequate claddings—which were also analysed in terms of resource consumption, as a preliminary approach to their life-cycle assessment. The main conclusions indicate that there is still a long path to cover in the field of life-cycle assessment of repair techniques, which can be extended to the application of diagnosis methods.

1. Introduction

Building maintenance, and specifically building inspection, is paramount to upkeeping the building stock, considering adequate levels of performance, thus contributing to sustainable development goals within the built environment—lower use of resources, improving habitability conditions of dwellers, promoting sustainable cities connected with their history, following SDGs 11 and 12. This study of building pathology contributes to that purpose and is not independent of diagnosis procedures and repair and refurbishment. In this paper, a new approach is presented regarding the connection between building defects and diagnosis methods and repair techniques.

1.1. Background

The building envelope, as the physical barrier separating the indoors from the outdoors, thus controlling heat, air, and moisture flows [1], has major importance in the overall performance of the building, as have its claddings.
There are several different inspection protocols defined in the context of building pathology and forensic engineering, all of them adapted to the purposes of research, like those developed by Ribeiro and Cóias e Silva [2], Juan et al. [3], Rojas and Songer [4], SEI and ASCE [5,6], Hegazy et al. [7], Linggar et al. [8], Matos et al. [9,10], and Bortolini and Forcada [11]. Those protocols should also be adapted to the inspected reality, considering the type of inspected building elements and aiming at unifying and standardising inspection procedures, regardless of building materials. This activity should have a holistic approach as long as the analysis of the inspection results and recommendations has specific references to the involved materials.
In the context of the research of Pereira [12], an inspection protocol for the non-structural building envelope was developed, and several auxiliary materials were made available, such as the classification lists of diagnosis methods (Table 1), repair techniques (Table 2) and defects (Table 3). Correlation matrices were also developed as the backbone of the inspection system, namely, defects–causes of defects, inter-defects (based on the defects–causes of defects correlation matrix), defects–diagnosis methods, and defects–repair techniques correlation matrices [13].

1.2. Scope and Objectives

The presented study is included within the scope of inspection of the envelope of current buildings as a support task to proactive and reactive maintenance strategies. Considering the categories roofs, façades and floorings, the research objectives are as follows (Figure 1):
  • understanding if and which defects can be diagnosed using the same means, considering visual observation as the base procedure and the use of tools and equipment as specific diagnosis methods;
  • understanding if and which defects can be repaired using the same techniques and the number of resources associated with those practices.
To achieve the mentioned objectives, the authors will develop two new inter-defects correlation matrices, this time based on the (i) defects–diagnosis methods and (ii) defects–repair techniques correlation matrices, which, until now, were excluded from previous research in the scope of the development of the inspection protocol for the non-structural building envelope [12,13,34]. Based on those two new matrices, an analysis of the most relevant and useful diagnosis methods and repair techniques for the building envelope is provided, taking the most common and severe defects into account.
The mentioned objectives are framed within an approach of considering building pathology from the surveyor’s perspective, preparing an inspection report with preventive recommendations, acting on the causes of the defects and aiming at cost-effective results.

2. Materials and Methods

2.1. Building New Inter-Defects Three-Dimensional Correlation Matrices

Garcia and de Brito [35] defined the methodology to create an inter-defects correlation matrix based on the defects–probable causes correlation matrix. In the context of expert knowledge-based inspection systems, the inter-defects correlation matrix shows the probability of the occurrence of a second defect when one defect is first detected. I.e., the inter-defects correlation matrix functions as an empirical tool to predict the conditioned probability of subsequent anomalies following the detection of an initial anomaly. Within the global inspection system for the non-structural building envelope [12], the harmonisation of the inter-defects correlation matrix followed the methodology determined by Garcia and de Brito [35], considering the harmonised defects–probable causes correlation matrix [13]. In that context, correlation matrices followed a three-dimensional model, with rows of defects, columns of probable causes, diagnosis methods or repair techniques (according to the type of matrix), and layers of building elements/materials. Three-dimensional inter-defect correlation matrices have rows of given defects, columns of second defects and layers of building elements/materials.
To build new inter-defects correlation matrices based on the correlation of defects with diagnosis methods (Table 4) or repair techniques (Table 5), a similar methodology was considered. The material used for this purpose was published by Pereira [12], created based on expert knowledge, validated by inspection data from significant samples [13], and then further validated (qualitatively) in more restricted inspection samples [34].
The algorithm to determine the theoretical percentage correlation index is as follows (considering the diagnosis methods for demonstration purposes) [35,36]:
  • For each detected defect (defect k), the corresponding row in the defects–diagnosis methods correlation matrix is read;
  • For each second defect (defect j), the corresponding row in the defects–diagnosis methods correlation matrix is read;
  • For each column, the product of the correlation indexes of both rows (for defects k and j) in the defects–diagnosis methods correlation matrix is calculated;
  • To obtain the correlation index for each defect CIkj, the products are summed up:
    C I k j = i = 1 N C k i C j i
    where N is the total number of diagnosis methods;
  • To obtain the maximum theoretical percentage correlation index IMk, for each detected defect k, the corresponding row in the defects–diagnosis methods correlation matrix is read; the correlation indexes of defect k with the diagnosis methods are multiplied by 2 (which is the maximum index of correlation in the correlation matrices used as a basis to apply the described algorith;. three indexes are available: 0 (no correlation), 1 (indirect correlation), and 2 (direct correlation)), and then, those products are summed up:
    I M k = i = 1 N C k i × 2
    where N is the total number of diagnosis methods;
  • To determine the theoretical percentage correlation index between defect k and defect j, CI%kj, the quotient between the correlation index CIkj and the maximum theoretical percentage correlation index IMk is calculated:
    C I % k j = C I k j I M k
Following the described procedure, one can obtain correlation indexes between defects according to the possibility of prescription of the same type of diagnosis methods for different defects (based on the defects–diagnosis methods correlation matrix; Table 6) and according to the possibility of recommendation of the same type of repair techniques for different defects (based on the defects–repair techniques correlation matrix; Table 7). As such, two new three-dimensional inter-defect correlation matrices were built.

2.2. Analysing the New Inter-Defects Three-Dimensional Correlation Matrices

The information provided by the new inter-defects three-dimensional matrices was further analysed considering the prescription of diagnosis methods or repair techniques for different types of building elements/materials in roofs, façades, and floorings.
For that purpose, the most relevant correlations in each layer of the new inter-defects three-dimensional correlation matrices had to be determined. With that goal in mind, hypothesis testing was applied [37]. The null hypothesis H0 was that by choosing threshold a, up to 35% of the most relevant correlations (b) would be obtained. The test may be summarised as follows:
H0: b ≥ 35%;
H1: b < 35%;
Statistic: X ¯ ;
Rule form: accept H0 if X ¯ c ;
Significance level:  α = 10 % ;
Result of threshold a: a = x ¯ + γ , where x ¯ is the average of correlations higher than 0 in each layer of the matrix, and γ is the respective standard deviation.
By applying the described methodology in each layer of the new three-dimensional inter-defects correlation matrices (selecting the most relevant correlations), an auxiliary matrix within each layer is built, indicating whether the correlation between the defects is higher than or equal to a. If it is higher, the cell in the intersection between the given and the second defect in the auxiliary matrix is filled with 1.
Then, the relevant correlations are compared according to the type of building component—roof claddings, façade elements/claddings, and floorings. Such a comparison is made by stacking the auxiliary matrices per layer category. That is, the layers of external claddings of pitched roofs and flat roofs are piled up (roof claddings); the layers of wall renders, ETICS, painted façades, architectural concrete surfaces, door and window frames, adhesive ceramic tiling, and natural stone claddings are piled up (façade elements/claddings); and the layers of wood floorings, epoxy resin industrial floor coatings, vinyl and linoleum floorings, adhesive ceramic tiling, and natural stone claddings are piled up (floorings). According to these categories, the comparable cells of each layer (representing a relevant correlation between the same types of defects) are summed up.
Out of the obtained sums, the highest are highlighted. That means that, for roof claddings (Table 8), only sums equal to 2 were considered. For façade elements/claddings (Table 9), only sums higher than or equal to 3 were considered. For floorings (Table 10), only sums higher than or equal to 2 were considered. This applies to both correlations based on diagnosis methods and repair techniques.
The described process allows us to select the most relevant correlations per category—roof claddings, façade elements/claddings, and floorings. But it is also necessary to understand the diagnosis methods or repair techniques (according to the base matrix used) that led to such relevance. For that purpose, a survey of the diagnosis methods/repair techniques associated with the relevant correlations was performed. Out of those, the diagnosis methods/repair techniques considered in both external claddings of pitched roofs and flat roofs were identified (for roof claddings). For façade elements/claddings and floorings, a similar process was performed, considering the presence in three or two more building elements/materials, respectively.
The materials and methods described in Section 2.1 and Section 2.2 are outlined in Figure 2.

2.3. Studying the Resources Associated with the Most Common Types of Repair Techniques

Considering some of the most common repair techniques that emerge from the analysis of results, a first approach to the resources needed to implement specific repair techniques was carried out. This narrow analysis can constitute the basis for the life-cycle assessment (LCA) of repair techniques in the future. In this case, the analysis was based on a cradle-to-gate approach of LCA [38]. The information about resources needed was collected from the CYPE Ingenieros S.A. website [39].

3. Results

3.1. Most Common Diagnosis Methods to Prepare an Inspection

Applying the methods described in Section 2.1 and Section 2.2, it is possible to identify (i) the most relevant inter-defects correlations based on the recommendation of diagnosis methods and (ii) the most common diagnosis methods useful in roof claddings, façade elements/claddings, and floorings.

3.1.1. Diagnosis Methods in Roof Claddings

In Table 11, the most relevant inter-defects correlations in roofs are identified, referring to different relationships between defects “A-A1 Leakage damp”, “A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, “A-C3 Fracture or splintering on the current surface”, “A-D1 Flaws in tail-end elements”, and “A-D12 Ponding/insufficient or excessive slope in roofs”. According to the data of Garcez et al. [40] adapted to the harmonisation of the classification of defects [33], none of these defects represent the top most detected defects in external claddings of pitched roofs (ECPR). Nevertheless, some are commonly found, such as “A-D12 Ponding/insufficient or excessive slope in roofs” (31.9%), “A-D1 Flaws in tail-end elements” (31.7%), and “A-A3 Dirt and accumulation of debris” (in 28.0% of inspected pitched roofs). As for flat roofs (FR), according to the data of Conceição et al. [41], adapted to the harmonisation of the classification of defects [33], defect “A-A3 Dirt and accumulation of debris” is the most detected (in 74.3% of inspected flat roofs). Other than that, the defect “A-D1 Flaws in tail-end elements” (40.0%) is also common.
As for the severity of the set of defects included in the most relevant correlations in roof claddings, data from service life prediction methodologies may be considered. In the case of external claddings of pitched roofs, the severity implicitly associated with the degradation levels for defects by Ramos et al. [42] may be used. Of the mentioned set of defects, these authors only take into account “A-A2 Surface moisture” and “A-A3 Dirt and accumulation of debris”, which comprise the defect “Staining, change in colour, or brightness of the tiles”. This defect is admitted to affect 20% or less of the total area of the pitched roof cladding when it is in good condition (Level 1). On the other hand, if it affects more than 50% of the total area of the pitched roof cladding, then it should be considered moderately degraded (Level 3). Ramos et al. [42] use a five-level scale from Level 0 (Very good) to Level 4 (Generalised degradation).
Ramos et al. [42] also take into account the defect “A-C3 Fracture or splintering on the current surface”, which is included in the defect “Cracking/fracture”. If such a defect affects 10% or less of the total area of the pitched roof claddings, it should be considered slight degradation (Level 2). On the other hand, if it affects more than 30% of that area, then the roof has generalised degradation.
From the data of Ramos et al. [42], it is found that defect A-C3 is considered more severe than A-A2 and A-A3. Nevertheless, it is important to highlight that a roof in very good condition (Level 0) should not have any signs of either of these defects.
As for flat roofs, the same kind of analysis cannot be performed. Still, some literature [43] highlights the importance of “A-A1 Leakage damp”, which may be associated with flashing details (between membranes) due to inadequate installation or improper detailing below the coping cap on parapet walls (where a moisture barrier is required). This cause is actually associated with the defect “A-D1 Flaws in tail-end elements”. Moreover, “A-D12 Ponding/insufficient or excessive slope in roofs” may also be a common problem in flat roofs, according to Madsen [43], associated with the incorrect design of the required slope to promote drainage of rainwater. In any case, drains must be checked to guarantee that they are not clogged.
Also in Table 11, the results referring to the diagnosis methods associated with the most relevant correlations are presented. It is found that, for roof claddings’ inspection, the most likely methods to be used, besides visual inspection, are “D-A3 Assessment of the slope, flatness, orthogonality, and alignments” and “D-C3 Infrared thermography”.
D-A3 has the main purpose of checking whether the minimum slope values for roofs are being respected, taking into account the type of cladding, exposure, slope length, location, and construction layout. Furthermore, through D-A3, surveyors can also assess the planimetry of claddings, taking specifications into account. The results of this diagnosis method can point out the causes of ponding, for instance. A spirit level may be used, as well as an inclinometer.
As for D-C3, it is a diagnosis method with several applications, although it requires experienced professionals to analyse the results. Whether in pitched or flat roofs, thermography is more useful in cases where no thermal insulation is used. Nevertheless, infrared thermography may be used indoors or outdoors to assess watertightness and the occurrence of humidity issues and to pinpoint discontinuities in thermal insulation. An infrared camera is required, as well as a regular camera, to compare thermograms with the visible area of claddings. The technique consists of taking advantage of the heating caused by solar radiation, observing the thermographic images (thermograms) obtained through the infrared camera, identifying the areas where voids, cracks, infiltrations, and other discontinuities that are not visible to the naked eye can be observed; video record the images taken for later interpretation and diagnosis; when interpreting the results, it should be borne in mind that the flaws are warmer than the rest of the coating during the day, revealing a more intense red colour, and are cooler at night, corresponding to a light blue colour.

3.1.2. Diagnosis Methods in Façade Elements/Claddings

In Table 12, the most relevant inter-defects correlations in façades are identified, referring to different relationships between defects “A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, “A-B1 Biodeterioration/biological growth”, “A-C1 Mapped cracking”, and “A-C2 Oriented cracking on the current surface”. According to the data of Santos et al. [44] adapted to the harmonisation of the classification of defects [33], defect A-B1 is the fourth most common in door and window frames (in 32.7% of inspected frames). Defect A-A3 is also common in door and window frames (24.1%). As for wall renders, according to the data of Sá et al. [45] adapted to the harmonisation of the classification of defects [33], defect “A-A3 Dirt and accumulation of debris” is the most detected (in 90% of inspected wall renders). Defect A-C1 is much less common (6%). Defects A-C2 (41%) and A-B1 (35%) have an average incidence in wall renders. According to the data of Amaro et al. [46], adapted to the harmonisation of the classification of defects [33], defect A-A2 is the most common in ETICS (in 59.4% of inspected surfaces). Defects A-A3 (24.4%), A-B1 (27.8%), and A-C2 (32.2%) are also common in ETICS, while defect A-C1 was only found in 7.5% of inspected surfaces. As for painted façades, according to the data of Pires et al. [47], adapted to the harmonisation of the classification of defects [33], defect “A-A3 Dirt and accumulation of debris” is by far the most detected (in 91.4% of inspected painted façades). Defects A-B1 (40.0%) and A-C1 (35.2%) have an average incidence in painted façades. According to the data of Silva et al. [48], adapted to the harmonisation of the classification of defects [33], defect A-C2 is the most common in architectural concrete surfaces (in 48.2% of inspected surfaces). Defects A-A2 (29.1%) and A-A3 (32.7%) are also common in architectural concrete surfaces, while defects A-B1 (11.8%) and A-C1 (12.7%) have a low incidence. As for adhesive ceramic tiling, according to the data of Silvestre et al. [49], adapted to the harmonisation of the classification of defects [33], defect “A-A3 Dirt and accumulation of debris” is one of the most detected (in 28% of inspected surfaces). Defect A-B1 (3%) has one of the lowest incidences. Defects A-C1 and A-C2, together, are present in 50% of inspected tiled surfaces. Finally, according to the data of Neto and de Brito [50] adapted to the harmonisation of the classification of defects [33], none of the identified defects are among the top most detected in natural stone claddings. Nevertheless, defects A-A3 (19.5%), A-B1 (7.8%), A-C1 17.6% and A-C2 17.6% have an average occurrence in natural stone claddings.
As for the severity of the set of defects included in the most relevant correlations in façade elements/claddings, data from service life prediction methodologies can also be considered. In the case of door and window frames, the severity implicitly associated with the degradation levels for defects by Fernandes et al. [51] may be used. Of the mentioned set of defects, these authors only take into account “A-A3 Dirt and accumulation of debris” and “A-B1 Biodeterioration/biological growth”, which comprise the defects “Accumulation of debris” and “Biological growth”, respectively. The accumulation of debris is admitted to affect 20% or more of the area of the element when it is in good condition (Level B). As for biological growth, if it affects up to 15% of the area of the element, it will be considered in Level C (slight degradation). On the other hand, if it affects between 15% and 30% of the total area of the element, then it should be considered moderately degraded (Level D). In case more than 30% of the area is affected, the element is considered to be under severe degradation (Level E). As such, biological growth is considered a severe defect in door and window frames. Fernandes et al. [51] use a five-level scale from Level A (Very good) to Level E (Severe degradation).
As for wall renders, the severity implicitly associated with the degradation levels for defects by Vieira et al. [52] may be used. Of the mentioned set of defects, these authors take all into account (“A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, “A-B1 Biodeterioration/biological growth”, “A-C1 Mapped cracking”, and “A-C2 Oriented cracking on the current surface”), which are mentioned as “damp”, “dirt”, microorganisms and algae”, and “cracking”, respectively. Damp is referred to in Level C of degradation (light degradation), as well as dirt. Microorganisms may eventually be present in Level B (good condition) and in dark patches (microorganisms and algae) in Level C. Cracking may occur in all levels of degradation, depending on the crack width to classify the level of degradation: in Level A (best condition), if the width is up to 0.1 mm; in Level B, if the width is between 0.25 mm and 1.0 mm, and in localised areas; in Level C, if the width is from 1.0 mm to 2.0 mm; and in Levels D (broad degradation) and E (worst condition), if the cracks have or are wider than 2 mm. Considering these data, cracking may be the most severe defect in this set of defects in wall renders. Vieira et al. [52] use a five-level scale from Level A (Best condition) to Level E (Worst condition).
In the case of ETICS, the severity implicitly associated with the degradation levels for defects by Ximenes et al. [53] may be used. Of the mentioned set of defects, these authors take into account “A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, and “A-B1 Biodeterioration/biological growth” under the defect “stains/colour changes”, and defects “A-C1 Mapped cracking” and “A-C2 Oriented cracking on the current surface”, considered as “loss of continuity/integrity defects”. None of these defects should be present in Level 0 (Unchanged). As for stains, in Level 1 (Good), only slight or few perceptible changes should be visible. In Level 2 (Slight degradation), they should be moderate or quite perceptible. In Level 3 (Moderate degradation), stains should be highly or strongly marked. In Level 4 (Generalised degradation), they should be very highly or quite strongly marked. As for cracking, in Level 1, cracks should be equal to or thinner than 0.2 mm and in a little or very little area of the cladding. In Level 2, they can be wider than 0.2 mm but only in a little or very little area or equal to or thinner than 0.2 mm in a moderate portion of the cladding. In Level 3, cracks can be wider than 0.2 mm but in a moderate portion of the cladding or equal to or thinner than 0.2 mm in a very large area. In Level 4, they can be wider than 0.2 mm in a very large area of the cladding. Both groups of defects can be present when severe degradation occurs in ETICS, depending on the intensity of the defects and the affected area. Ximenes et al. [53] use a five-level scale from Level 0 (Unchanged) to Level 4 (Generalised degradation).
As for painted façades, the severity implicitly associated with the degradation levels for defects by Chai et al. [54] may be used. Of the mentioned set of defects, these authors take into account “A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, and “A-B1 Biodeterioration/biological growth”, which are considered within the scope of “stains/colour change”. “A-C1 Mapped cracking” is also taken into account as “cracking”. Both for stains/colour changes and cracking, in Level 0, there should be no visible degradation. Stains/colour changes are classified from Level 0 to Level 4, considering the intensity of change and the type of visible signs of defects (Figure 3). So, in Level 1 (Good condition), only slight or little perceptible uniform surface dirt should be observed. In Level 2 (Slight degradation), moderate or quite perceptible uniform surface dirt may be observed. In Level 3 (Moderate degradation), moderate or quite perceptible humidity stains, biological growth, and localised surface dirt may be observed, or high or very perceptible uniform surface dirt may be observed. In Level 4 (Generalised degradation), high or very perceptible biological growth may be observed. Cracking is classified according to a visual scale of the density of cracks, from a small number of cracks (in Level 1) to a high number or density of cracks (in Level 4). Considering these data, biological growth and cracking may be the most severe defects in this set of defects in painted façades. Chai et al. [54] use a five-level scale from Level 0 (No visible degradation) to Level 4 (Generalised degradation).
In the case of architectural concrete surfaces, the severity implicitly associated with the degradation levels for defects by Serralheiro et al. [55] may be used. Of the mentioned set of defects, these authors take all into account. In Level A, there should be no visible degradation of any kind. In Level B (Good), dirt and moisture stains should account for less than 15% of the surface area and biological growth for less than 10%. In Level C (Slight degradation), dirt and moisture stains may affect 15–40% of the surface area and biological growth 10–30%. In Level C, oriented cracking (width up to 0.5 mm) cannot affect more than 20% of the surface. In Level D (Moderate degradation), dirt and moisture stains may affect more than 40% of the surface, while biological growth may be present in more than 30%. In Level D, mapped cracking may be present in less than 50% of the surface and oriented cracking with a width of 0.5–3 mm in 5% or more of the surface, while oriented cracking equal to or wider than 3 mm should only be found in less than 5% of the surface. In Level E (Generalised degradation), mapped cracking may be found in 50% or more of the surface, and oriented cracking equal to or wider than 3 mm may be found in 5% or more of the surface. As such, cracking is considered a more severe defect in architectural concrete surfaces. Serralheiro et al. [55] use a five-level scale from Level A (No visible degradation) to Level E (Generalised degradation).
As for adhesive ceramic tiling, the severity implicitly associated with the degradation levels for defects by Bordalo et al. [56] may be used. Of the mentioned set of defects, these authors take all into account. In Level 0, there should be no visible degradation. In Level 1 (Good), surface dirt and damp stains in 10% or less of the area of the surface are observed, while cracked glazing may be observed and markedly oriented cracking thinner than 0.2 mm without leakage may also be observed. In Level 2 (Slight deterioration), damp stains in 10–50% of the surface are present, as well as biological growth in 30% or less of the surface. Cracking with no predominant direction and markedly oriented cracking with 0.2 mm or wider is observed in 30% or less of the surface. In Level 3 (Moderate degradation), damp stains in more than 50% of the surface and biological growth in more than 30% of the surface are present. Cracking may occur with no predominant direction or markedly oriented cracking (wider than 1 mm) without leakage may occur in 30–50% of the surface. In Level 4 (Generalised degradation), cracking with no predominant direction and markedly oriented cracking wider than 5 mm may be observed in more than 50% of the surface. Considering these data, cracking is the most severe defect in this set of defects in adhesive ceramic tiling. Bordalo et al. [56] use a five-level scale from Level 0 (No visible degradation) to Level 4 (Generalised degradation).
In the case of natural stone claddings, the severity implicitly associated with the degradation levels for defects by Silva et al. [57] may be used. Of the mentioned set of defects, these authors take all into account. In Level 0, there should be no visible degradation of any kind. In Level 1 (Good), surface dirt may affect more than 10% of the surface; moisture and localised stains may affect up to 15% of the surface, and cracking of 1 mm or thinner may affect up to 20% of the surface. In Level 2 (Slight degradation), moisture and localised stains may affect more than 15% of the surface; moss, lichen, and algae growth may affect up to 30% of the surface; cracking of up to 1 mm wide may affect more than 20% of the surface, and cracking of 1–5 mm wide may affect up to 20% of the surface. In Level 3 (Moderate degradation), moss, lichen, and algae growth may affect more than 30% of the surface; cracking of 1–5 mm wide may affect more than 20% of the surface, and cracking of 5 mm wide or wider may affect up to 20% of the surface. In Level 4 (Generalised degradation), cracking wider than 5 mm may affect more than 20% of the surface. As such, cracking is considered a more severe defect, mainly when its width is larger, in natural stone claddings. Silva et al. [57] use a five-level scale from Level 0 (No visible degradation) to Level 4 (Generalised degradation).
To sum up, in general terms, in façade elements/claddings, and considering the variety of cladding types, cracking tends to be considered a more serious defect in more materials/elements, followed by biodeterioration/biological growth. It should be noted that, by using classification lists, not all materials are considered to be affected by detachment, as some are affected by loss of adhesion. In this way, cracking is a more transverse defect, which may also be associated with more severe mechanical issues in the building.
Also, in Table 12, the results referring to the diagnosis methods associated with the most relevant correlations are presented. It is found that for façade elements/claddings’ inspection, the most likely methods to be used, besides visual inspection, are “D-C1 Measurement of the ambient and/or surface temperature and humidity”, “D-C3 Infrared thermography”, and “D-F4 Initial surface absorption test (ISAT) and Karsten-tube”.
D-C3 was already described for roof claddings. In façades, it has the added advantage of enabling the detection of voids in the underlying layers of the cladding system.
D-C1 may be used to measure the ambient temperature close to the surface of the cladding, measure the relative humidity close to the surface of the cladding, measure the water content of claddings and measure the temperature on the cladding surface. For these purposes, a hygrometer or thermo-hygrometer, a portable moisture meter, a humidity and temperature sensor and an infrared thermometer may be necessary. To properly perform the required measurements, first, the reading points should be defined, considering the orientation of the cladding and the incidence of light, which can be assisted by designing a reference mesh for surface measurements. The equipment may require calibration. Then, the measuring equipment should be placed in the surroundings (ambient readings) or on (superficial readings) the cladding surface. The measurement equipment will show the reading values on its display. If the moisture meter values are presented as a percentage, it will correspond to the amount of water recognised by the device compared to the mass of material in a dry or wet state (varies according to the equipment, as defined in the user manual). The measurement should be performed at different points on the surface or in the surrounding environment.
The method “D-F4 Initial surface absorption test (ISAT) and Karsten-tube” may be used to assess the water permeability of the cladding and to determine the porosity degree of the surface. The ISAT will require a clear acrylic cell (100 mm diameter), a transparent container (connected to the entry of the cell), a graduated capillary tube (connected to the exit of the cell), and a valve (to close the container). First, the capillary tube should be calibrated so that the cross-sectional area can be determined. Next, the cell area should be measured to determine the scale factor for the cell/tube combination. Then, the cell is attached to the surface and sealed to ensure uniform pressure. After filling the cell with water, the container is closed, and flow measurements are taken along the capillary tube (readings at 10, 30, and 60 min) after the first wetting of the surface. As for the Karsten tube test, it will require three (minimum) Karsten tubes (glass tubes graduated from 0 to 4 cm3, shaped as pipes), silicone (or mastic, plasticine or putty) for fixing the tubes to the surface (included an application gun, if applicable), a water container, and nozzle. First, the surface is cleaned. Next, the edge of the tube is covered with silicone (or other adhesive material), and the tube is attached to the wall in the area to be tested, pressing it onto the wall. Silicone should dry for at least 20 min at room temperature. Then, the tubes are filled with water up to the maximum level (4 cm3). After 5 min, the first reading is taken on each of the three tubes, based on the lowering of the water level observed in the tubes. The reading should be repeated at 10, 15, 30, and 60 min, registering the water level drop. For each time interval, an average value is considered (using the three readings) and using these values, a graph may be drawn of the water level drop as a function of time. The slope of the line corresponds to the absorption coefficient of the cladding.

3.1.3. Diagnosis Methods in Floorings

In Table 13, the most relevant inter-defects correlations in floorings are identified, referring to different relationships between defects “A-B4 Blistering/bulging”, “A-C1 Mapped cracking”, “A-C2 Oriented cracking on the current surface”, “A-C3 Fracture or splintering on the current surface”, “A-C4 Cracking and/or splintering adjacent to joints/edges”, and “A-C10 Loss of adhesion”. According to the data of Silvestre et al. [49] adapted to the harmonisation of the classification of defects [33], defect A-C10 is the third most common in adhesive ceramic tiling (in 42% of inspected surfaces). As mentioned for façade claddings, defects A-C1 and A-C2 together were present in 50% of inspected adhesive ceramic tiled surfaces. Defect A-C4 (9%) has a low incidence on tiled surfaces. As for natural stone claddings, according to the data of Neto and de Brito [50], adapted to the harmonisation of the classification of defects [33], defects A-C1 (17.6%), A-C2 (17.6%), A-C4 (13.7%), A-C3 (10.2%), and A-C10 (6.3%) all have an average to low incidence in this type of flooring. According to the data of Delgado et al. [58], adapted to the harmonisation of the classification of defects [33], defect A-C4 has an average incidence in wood floorings (in 13.8% of inspected floorings). Defects A-C2 (6.7%) and A-C3 (7.2%) are not very common in wood floorings. As for epoxy resin industrial floor coatings, according to the data of Garcia [59] adapted to the harmonisation of the classification of defects [33], defect “A-C10 Loss of adhesion” is the most detected (in 51.7% of inspected floorings). Defects A-B4 (24.0%), A-C1, and A-C2 together (20.7%) have an average incidence in epoxy resin floorings. According to the data of Carvalho et al. [60], adapted to the harmonisation of the classification of defects [33]; defect A-C2 is the fourth most common in vinyl and linoleum floorings (in 38% of inspected floorings). Defects A-C10 (16%), A-B4 (10%) and A-C3 (10%) have an average to low incidence in this type of flooring.
As for the severity of the set of defects included in the most relevant correlations in façade elements/claddings, data from service life prediction methodologies can again be considered. Still, known studies refer only to wood floorings [61]. In this case, the weighting factor associated with each type of defect is considered. So, swelling is aggravated by a factor of 1.2 when calculating the severity of degradation, as well as cracking and broken or splintered elements. Subsequently, the defects considered in the observed correlations are all considered severe, as they aggravate the calculation of Sw.
Although the same kind of analysis cannot be performed for adhesive ceramic tiled floorings, the general literature about their defects can be analysed. Valente de Almeida [62] lists breaking, surface defects (dry spots, bumps and blisters), and crazing and cracks as some of the main problems in ceramic tiles. Son and Yuen [63] refer to similar problems, namely, arching, lifting, tile edge failure, and broken tiles, among others. In this sense, some of the defects considered in the correlations are among those most relevant in ceramic tiling floorings.
As for natural stone floorings, the specific literature is not abundant. Still, considering the general knowledge about the use of natural stone in buildings, the occurrence of cracking is highlighted as one of the consequences of frost attacks [64], which can result in the fragmentation of the stone slab. Additionally, freeze–thaw deterioration may cause a loss of bond between the bedding material and stone slabs [65]. In cold climates, when mortar is used as the bonding material, water may enter the system through the joints, and as it freezes, expands, and thaws, it causes a loss of adhesion in the flooring system. Debonding may also be caused by differential thermal movement between the stone material and the bedding [65].
In epoxy resin floorings, blistering is a serious concern. Osmotic blistering [66] may occur in the early stages of the service life of the flooring, which is a phenomenon not fully understood but mainly associated with design and execution measures.
Loss of adhesion can also be an issue in vinyl and linoleum floors, mainly associated with the presence of water in the bonding layer, which may break the bond [67], causing permanent damage.
Therefore, defects A-B4, A-C1, A-C2, A-C3, A-C4, and A-C10 affect varied types of floorings differently, but, in general terms, the defects that may result in some kind of flatness deficiencies are those considered more severe. All of these defects may have that effect.
Also, in Table 13, the results referring to the diagnosis methods associated with the most relevant correlations are presented. It is found that, for floorings inspection, the most likely methods to be used, besides visual inspection, are “D-A4 Tell-tale gauge and gypsum testimonies”, “D-A5 Crack width ruler and crack-measuring microscope”, and “D-A6 Mechanical strain gauge”. All these methods are useful for measuring cracks or joints and they complement each other.
Method D-A4 is used to quantify and/or monitor the width of cracks, assess the stability of cracks, determine the movement trend through the analysis of readings over time, and provide evidence for establishing cause–effect relationships according to the actions or occurrences to which the building is subjected. The tell-tale gauge is a small piece of equipment applied on the surface of floorings or claddings. First, the measuring points are defined with traces of about 20 cm, and each one is numbered. Next, to monitor displacements parallel to the test plane, the two acrylic glass plates that make up the tell-tale gauge are well attached to each side of the crack along the direction closest to the perpendicular direction to the crack so that the centre of the grid coincides with the centre of the crack and with the previously marked line. Then, the width of the crack is monitored by directly reading the displacement and observing the relative position of the crosshairs (reference traces, usually red) compared to the grid. Finally, the observed values are recorded, and the defect can be mapped using location and orientation data, as well as the progression information. As for gypsum testimonies, they help determine the degree of stabilisation of cracks through monitoring over time. For that purpose, a mortar of pure gypsum with 70% water is used to execute a patch centred on the crack and fixed to both sides. The patch should be detached from the crack itself using paper tape. Afterwards, periodic verification should check the occurrence of breakage in the patch, revealing the degree of activity of the crack.
“D-A5 Crack width ruler and crack-measuring microscope” refers to the use of these two instruments to quantify the width of cracks. The crack width ruler is used for direct readings of the width of cracks, placing the instrument over the building element and matching the lines with the crack under analysis, running the lines from smallest to largest until one matches the width of the crack, thus finding the corresponding value. After reading, the values should be recorded, and the crack can be mapped. The use of the crack measuring microscope is similar but for thinner cracks. The crack microscope is placed over the crack, peering through the eyeglass and focusing using the appropriate handle. As the lens is graduated, one can read the crack opening in millimetres. Then, the cracks observed can be mapped according to width values, location, orientation, and severity.
The mechanical strain gauge (D-A6) can assess, quantify, and monitor even small displacements in joints and cracks with high accuracy. To use this method, first, the locations for measurements need to be selected and marked. Then, the metal bases (5 mm diameter) are glued to the building element, where the gauge is placed. The values are registered during the monitoring period, and then the crack can be mapped.

3.2. Most Common Types of Repair Techniques

As performed for diagnosis methods, if the methods described in Section 2.1 and Section 2.2 are used, the most relevant inter-defects correlation based on the prescription of repair techniques are revealed, and the most common repair techniques used in roof claddings, façade elements/claddings, and floorings can be identified.

3.2.1. Repair Techniques in Roof Claddings

In Table 14, the most relevant inter-defects correlations in roofs are presented, namely, different relationships between defects “A-A1 Leakage damp”, “A-A3 Dirt and accumulation of debris”, “A-B1 Biodeterioration/biological growth”, “A-B2 Vegetation growth”, “A-C1 Mapped cracking”, “A-C2 Oriented cracking on the current surface”, “A-C3 Fracture or splintering on the current surface”, “A-D7 Absence/loss of filling material in connecting elements or current joints”, and “A-D9 Insufficient or excessive overlap of the claddings elements in roofs”. According to the data of Garcez et al. [40], adapted to the harmonisation of the classification of defects [33], defects A-B1 and A-B2, together, are the most common in external claddings of pitched roofs (in 72.5% of inspected roofs). Then, defects A-C1, A-C2, and A-C3, all together, also have a high incidence (46.4%). Defect A-A3 (28.0%), as highlighted in Section 3.1, moderately affects claddings of pitched roofs, and defects A-D7 (6.8%) and A-D9 (12.6%) only affect a few pitched roofs. As for flat roofs, according to the data of Conceição et al. [41], adapted to the harmonisation of the classification of defects [33], as mentioned in Section 3.1, defect “A-A3 Dirt and accumulation of debris” is the most detected (in 74.3% of inspected flat roofs). Defects A-C1, A-C2, and A-D7, all together, have a median incidence in flat roofs (21.9%). Then, defects A-D9 (13.3%), A-C3 (11.0%), and A-A1 (9.5%) only affect a small number of inspected roofs.
As for the severity of the set of defects included in the most relevant correlations in roof claddings, data from service life prediction methodologies may be considered. In the case of external claddings of pitched roofs, the severity implicitly associated with the degradation levels for defects by Ramos et al. [42] may be used. Out of the nine mentioned defects, these authors only take into account “A-A3 Dirt and accumulation of debris”, “A-B1 Biodeterioration/biological growth”, “A-B2 Vegetation growth”, “A-C1 Mapped cracking”, “A-C2 Oriented cracking on the current surface”, and “A-C3 Fracture or splintering on the current surface”, which comprise the defects “Staining, change in colour or of brightness of the tiles”, “Development of parasitic vegetation/biological colonisation”, and “Cracking/fracture”. The first one was already considered in Section 3.1.1, and it is considered to affect moderately degraded roof claddings. Biological colonisation and vegetation growth, together, are admitted to affect up to 10% of the total area of the cladding when it is in good condition (Level 1). On the other hand, if they affect more than 50% of the pitched roof cladding, then it should be considered moderately degraded (Level 3). Cracking/fracture was also considered in Section 3.1.1, and it affects roofs from slight degradation (Level 2) to generalised degradation (Level 4). Ramos et al. [42] use a five-level scale from Level 0 (Very good) to Level 4 (Generalised degradation). From this data, defects A-C1, A-C2, and A-C3 are the most severe.
As for flat roofs, the same kind of analysis cannot be performed. Still, as mentioned in Section 3.1.1, the importance of “A-A1 Leakage damp” is highlighted in the literature [43].
Also, in Table 14, the results referring to the repair techniques associated with the most relevant correlations are presented. It is found that, for the repair of roof claddings, the most likely technique to be used is “R-A1 Cleaning”. It is actually common knowledge that, together with the biannual inspections of roofs, cleaning procedures should be carried out (checking the drainage system for clogging and cleaning any debris).
Furthermore, given the future assessment of the life cycle of repair techniques, a superficial analysis of the resources associated with each repair technique can be performed. This is a seminal approach to the topic.
In the case of Table 15, “R-A1 Cleaning” refers to (i) in external claddings of pitched roofs, cleaning gutters manually (removal of any accumulated dirt, including debris, nests and leaves), and cleaning ceramic roof tiles manually and applying an adequate cleaning agent for the removal of mould, fungus and grease stains; (ii) in flat roofs, using a blower to remove debris from the current surface and gutters, manually removing any vegetation, using a water jet to wet the surface, brushing the roof surface and rinsing the surface thoroughly with running water.

3.2.2. Repair Techniques in Façade Elements/Claddings

In Table 16, the most relevant inter-defects correlations in façades are identified, referring to different relationships between defects “A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, “A-A4 Colour changes”, “A-A6 Cohesion loss/disaggregation and chalking”, “A-B1 Biodeterioration/biological growth”, “A-B2 Vegetation growth”, “A-B3 Efflorescence/cryptoflorescence and carbonation”, “A-C1 Mapped cracking”, and “A-C2 Oriented cracking on the current surface”. According to the data of Santos et al. [44], adapted to the harmonisation of the classification of defects [33], defects A-B1 (32.7%) and A-A3 (24.1%) are common in door and window frames, while A-A4 (8.6%) and A-A2 (2.7%) only occur sparsely.
As for wall renders, according to the data of Sá et al. [45], adapted to the harmonisation of the classification of defects [33], defect “A-A3 Dirt and accumulation of debris” is the most detected (in 90% of inspected wall renders). Defects A-A4 (46%), A-C2 (41%) and A-B1 (35%) have an average incidence in wall renders, while defects A-A2 (15%), A-B3 (9%), A-C1 (6%), A-A6 (4%), and A-B2 (3%) are not very common.
According to the data of Amaro et al. [46], adapted to the harmonisation of the classification of defects [33], defect A-A2 is the most common in ETICS (in 59.4% of inspected surfaces). Defects A-C2 (32.2%), A-B1 (27.8%), A-B2 (27.8%), A-A3 (24.4%), and A-A4 (20.3%) are also common in ETICS, while defects A-C1 (7.5%) and A-B3 (1.4%) are rare.
As for painted façades, according to the data of Pires et al. [47], adapted to the harmonisation of the classification of defects [33], “A-A3 Dirt and accumulation of debris” is by far the most detected (in 91.4% of inspected painted façades). Defects A-A4 (47.6%) and A-B1 (40.0%) are also common, while A-C1 (35.2%) has an average incidence in painted façades. Defects A-B3 (8.6%) and A-A6 (5.7%) occur sparsely.
According to the data of Silva et al. [48], adapted to the harmonisation of the classification of defects [33], defect A-C2 is the most common in architectural concrete surfaces (in 48.2% of inspected surfaces). Defects A-A3 (32.7%), A-A2 (29.1%), and A-A4 (29.1%) are also common in architectural concrete surfaces, while defects A-C1 (12.7%), A-B1 (11.8%), A-B3 (7.3%), and A-A6 (0.9%) have a low to very low incidence.
As for adhesive ceramic tiling, according to the data of Silvestre et al. [49], adapted to the harmonisation of the classification of defects [33], defect “A-B3 Efflorescence/cryptoflorescence and carbonation” is one of the most detected (in 40% of inspected surfaces). Defects A-B1 and A-B2, together (5%), have one of the lowest incidences. Defects A-A3 and A-A4, together (55%), are commonly detected in this type of cladding. Defects A-C1 and A-C2, together, are present in 50% of inspected tiled surfaces.
Finally, according to the data of Neto and de Brito [50], adapted to the harmonisation of the classification of defects [33], defect “A-A4 Colour changes” is the most common in natural stone claddings (in 93.0% of inspected surfaces); the remaining defects have an average to low incidence in natural stone claddings—A-A3 (19.5%), A-C1 (17.6%), A-C2 (17.6%), A-B3 (12.5%), A-B1 (7.8%), A-A6 (5.5%), A-B2 (3.1%).
As for the severity of the set of defects included in the most relevant correlations in façade elements/claddings, data from service life prediction methodologies can also be considered in the case of window frames [61]. The severity implicitly associated with the degradation levels for defects by Fernandes et al. [51] may be used. Of the mentioned set of nine defects, these authors only take into account “A-A3 Dirt and accumulation of debris”, “A-A4 Colour changes”, “A-B1 Biodeterioration/biological growth”, and “A-C1 Mapped cracking”. The accumulation of debris may affect more than 20% of the elements in Level B (Good). There can be colour changes in the element coating in up to 10% of the element in Level B (Good), but if it affects more than 50% of the area, then the element is in Level D (Moderate degradation). Biological growth can affect up to 15% of the element in Level C (Slight degradation), but in Level E (Severe degradation), biodeterioration needs only to affect 10% or more of the door/window frame. As for mapped cracking, it may affect up to 10% of the element coating in Level B (Good) and more than 50% in Level D (Moderate degradation). In this case, biodeterioration is considered the most severe defect in door and window frames. Fernandes et al. [51] use a five-level scale from Level A (Very good) to Level E (Severe degradation).
As for wall renders, the severity implicitly associated with the degradation levels for defects by Vieira et al. [52] may be used. Of the mentioned set of defects, these authors take the following into account: “A-A2 Surface moisture”; “A-A3 Dirt and accumulation of debris”; “A-A4 Colour changes”; “A-B1 Biodeterioration/biological growth”; “A-C1 Mapped cracking”; and “A-C2 Oriented cracking on the current surface”. They are mentioned as “damp”, “dirt”, “changes in the colour of the surface”, “microorganisms and algae”, and “cracking”, respectively. Damp and dirt are referred to in Level C (light degradation). Colour changes may be visible in Level B (good condition). Microorganisms may be present in Level B (good condition) and dark patches (microorganisms and algae) in Level C (light degradation). Cracking may occur at all levels of degradation, depending on the crack width. In Level A (best condition), cracks may be up to 0.1 mm wide. In Level E (worst condition), cracks may be 2 mm or wider. Considering these data, cracking may be the most severe defect in this set of defects in wall renders. Vieira et al. [52] use a five-level scale from Level A (Best condition) to Level E (Worst condition).
In the case of ETICS, the severity implicitly associated with the degradation levels for defects by Ximenes et al. [53] may be used. Of the mentioned set of defects, these authors take into account “A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, “A-A4 Colour changes”, “A-B1 Biodeterioration/biological growth”, and “A-B3 Efflorescence/cryptoflorescence and carbonation” under the defect “stains/colour changes”, and defects “A-C1 Mapped cracking” and “A-C2 Oriented cracking on the current surface”, considered as “loss of continuity/integrity defects”. The severity of these defects has already been detailed in Section 3.1.2, finding that both groups of defects can represent severe degradation in ETICS depending on the intensity and affected area.
As for painted façades, the severity implicitly associated with the degradation levels for defects by Chai et al. [54] may be used. Of the mentioned set of defects, these authors take into account “A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, “A-A4 Colour changes”, “A-B1 Biodeterioration/biological growth”, and “A-B3 Efflorescence/cryptoflorescence and carbonation”, which are considered within the scope of “stains/colour change”. “A-C1 Mapped cracking” is also taken into account as “cracking”. The severity of these defects has already been detailed in Section 3.1.2, determining that biological growth and cracking may be the most severe defects within this set in painted façades.
In the case of architectural concrete surfaces, the severity implicitly associated with the degradation levels for defects by Serralheiro et al. [55] may be used. Of the mentioned set of defects, these authors take into account “A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, “A-A6 Cohesion loss/disaggregation and chalking”, “A-B1 Biodeterioration/biological growth”, “A-B3 Efflorescence/cryptoflorescence and carbonation”, “A-C1 Mapped cracking”, and “A-C2 Oriented cracking on the current surface”. The severity of most of these defects has already been discussed in Section 3.1.2, but for A-A6 and A-B3, it is missing. Disaggregation may be present in less than 10% of surfaces with slight degradation (Level C). If the surface has generalised degradation (Level E), then disaggregation may be present in more than 30% of its area. As for efflorescence, it may be present in less than 10% of a surface in good condition (Level B), while if it takes up more than 30% of the surface, it may be considered with moderate degradation (Level D). Although disaggregation is a severe defect, cracking of more than 0.5 mm wide is still more severe in architectural concrete surfaces. Serralheiro et al. [55] use a five-level scale from Level A (No visible degradation) to Level E (Generalised degradation).
As for adhesive ceramic tiling, the severity implicitly associated with the degradation levels for defects by Bordalo et al. [56] may be used. Of the mentioned set of defects, these authors take into account “A-A2 Surface moisture”, “A-A3 Dirt and accumulation of debris”, “A-A4 Colour changes”, “A-B1 Biodeterioration/biological growth”, “A-C1 Mapped cracking”, and “A-C2 Oriented cracking on the current surface”. Out of these, only the severity of A-A4 has not been discussed in Section 3.1.2. The change in colour may occur in up to 10% of tiled surfaces in good condition (Level 1). If it affects more than 50% of the area, then the surface is under moderate degradation (Level 3). So, cracking is still the most severe defect in this set of defects in adhesive ceramic tiling. Bordalo et al. [56] use a five-level scale from Level 0 (No visible degradation) to Level 4 (Generalised degradation).
In the case of natural stone claddings, the severity implicitly associated with the degradation levels for defects by Silva et al. [57] may be used. Of the mentioned set of defects, these authors take all into account. The severity of A-A2, A-A3, A-B1, A-C1, and A-C2 was discussed in Section 3.1.2. As for “A-A4 Colour changes”, it may occur in up to 15% of the area of the stone cladding in good conditions (Level 1), but if it affects more than that area, then the surface is considered with slight degradation (Level 2). As for “A-A6 Cohesion loss/disaggregation and chalking”, it is classified according to the thickness of the stone slab that is affected. Material degradation in up to 1% of the thickness may occur in claddings in good conditions (Level 1), regardless of the affected area. But material degradation in up to 10% of the thickness of the stone slab is limited to 20% of the area of the stone claddings for it to be considered in good condition (Level 1). In cladding under generalised degradation (Level 4), material degradation may affect more than 30% of the thickness of the stone slabs in more than 20% of the surface of the stone cladding. In the case of “A-B2 Vegetation growth”, it may be observed in claddings with slight degradation (Level 2) in up to 30% of the surface. If it is more than that, then the surface is considered moderately degraded (Level 3). Efflorescence (A-B3) follows the same criteria as A-B2. Cracking is the most severe defect in the set, according to its width, closely followed by disaggregation. Silva et al. [57] use a five-level scale from Level 0 (No visible degradation) to Level 4 (Generalised degradation).
Also, in Table 16, the results referring to the repair techniques associated with the most relevant correlations are presented. It is found that for the repair of façade elements/claddings, the techniques that may solve a broader number of types of defects are “R-A1 Cleaning”, “R-A2 Application of a protective coat (paint, varnish, water-repellent, antifungal, biocide)”, “R-A11 Replacement or reapplication of the cladding/glazing (partially or completely)”, “R-A12 Application of a new (adequate) cladding/finishing coat over the existent/replacement”, “R-A14 Treatment of cracks or other holes in the cladding”, and “R-D16 Correction of geometrical construction details”. These repair techniques tend to have very broad designations, and the particular works that are involved for each building material may be quite different.
Concerning the resources used, two repair techniques are analysed, namely, R-A1 and R-A2. In the case of Table 17, “R-A1 Cleaning” in façade claddings refers to manual cleaning of the surface with mould stains or dampness through the application of water and bleach solution at 10% and rinsing with abundant clean water.
In the case of Table 18, “R-A2 Application of a protective coat (paint, varnish, water-repellent, antifungal, biocide)” in natural stone claddings refers to a water-repellent surface treatment for natural stone façades, using colourless water-repellent and oil-repellent impregnation applied in successive coats until the element is saturated.

3.2.3. Repair Techniques in Floorings

In Table 19, the most relevant inter-defects correlations in floorings are presented, namely, between defects “A-A3 Dirt and accumulation of debris”, “A-A4 Colour changes”, “A-A5 Spalling/peeling/exfoliation and pop-outs“, “A-A6 Cohesion loss/disaggregation and chalking“, “A-C1 Mapped cracking”, “A-C2 Oriented cracking on the current surface“, “A-C4 Cracking and/or splintering adjacent to joints/edges”, “A-C6 Scratches/grooves and deep wear”, “A-C9 Detachment“, “A-D6 Degradation of the filling material of current joints”, and “A-D7 Absence/loss of filling material in connecting elements or current joints“. According to the data of Silvestre and de Brito [49], adapted to the harmonisation of the classification of defects [33], defect A-D6 is the most common in adhesive ceramic tiling (in 57% of inspected elements). Then, defects A-A3 and A-A4 (55%), together, represent the second most common occurrence (staining, change in colour or brightness). Moreover, cracking (A-C1 and A-C2) is present in about 50% of inspected surfaces. As for natural stone claddings, according to the data of Neto and de Brito [50], adapted to the harmonisation of the classification of defects [33], by far, defect A-A4 (93%) is the most common in the inspected surfaces. Defects A-C1 and A-C2 (36%), together, also have a significant incidence in this type of flooring, as well as A-A3 (32%). According to the data of Delgado et al. [58], adapted to the harmonisation of the classification of defects [33], defect A-C6 (85%) is by far the most relevant one in wood floorings. As for epoxy resin industrial floor coatings, according to the data of Garcia [59], adapted to the harmonisation of the classification of defects [33], defects “A-A4 Colour changes” (31%) and “A-C6 Scratches/grooves and deep wear” (31%) are within those most common. According to the data of Carvalho et al. [60], adapted to the harmonisation of the classification of defects [33], defect A-C6 (in 75% of inspected surfaces) is the most common in vinyl and linoleum floorings. Defects A-D6 and A-D7 together (54%) and A-A4 (43%) are also relevant in this type of flooring.
As for the severity of the set of defects included in the most relevant correlations in floorings, data from service life prediction methodologies can also be considered. In the case of wood floorings, the severity implicitly associated with the degradation levels for defects by Coelho et al. [61] may be used. These authors take into account the complete set of nine defects considered by Delgado et al. [68]. The one considered more severe is the loss of wood elements (detachment), whose degradation starts at level 3 (slight degradation), even if the area affected is low (0–30%). As for weighting factors associated with each defect to calculate the flooring’s Sw, all functional defects are aggravated with a factor of 1.2, including “A-A6 Cohesion loss/disaggregation and chalking”, “A-C2 Oriented cracking on the current surface“, “A-C4 Cracking and/or splintering adjacent to joints/edges”, and “A-D7 Absence/loss of filling material in connecting elements or current joints”. So, most of the defects considered in Table 19 are considered severe in wood floorings.
The same analysis cannot be carried out for the other types of floorings, but the general literature about their typical pathology can be analysed. Ventura et al. [69] identify cracking, detachment, crushing and chipping, wear and/or scratching, swelling, colour loss, blistering, staining, fungi, and xylophagous organisms as the most recurrent in floorings. Of this group, only swelling, blistering, and fungi and xylophagous organisms are not in Table 19. Furthermore, Valente de Almeida [62] lists “A-A5 Spalling/peeling/exfoliation and pop-outs“ (surface defects), “A-C1 Mapped cracking”, “A-C2 Oriented cracking on the current surface” (crazing and cracks), and “A-C4 Cracking and/or splintering adjacent to joints/edges” (breaking) as some of the main problems in ceramic tiles. Although the specific literature on natural stone floorings is scarce, the general knowledge refers to the effects of pollutants in staining and the risks of design, specification, and construction errors, which may lead to cracking, general decay, and more rapid decay. For instance, in public areas paved with natural stone elements, the design issues are critical to avoid cracking and premature end-of-life [65]. Cracking is also a major concern in epoxy resin floorings, mainly associated with the substrate conditions (screeds or concrete slabs) depending on the layers of the epoxy coating system [70]. In vinyl and linoleum floorings, joint defects (A-D7, mainly) may assume larger proportions if not corrected, as they are prone to water leakages, which, in place, may lead to the detachment of the flooring system.
To sum up, A-A3, A-A4, A-A5, A-A6, A-C1, A-C2, A-C4, A-C6, A-C9, A-D6, and A-D7 affect several types of floorings in various manners, but those more severe are associated with mechanical causes. Nevertheless, depending on the level of requirements, visual defects (e.g., stains) may also obtain graver proportions if not tackled in the earlier stages.
Table 19 also presents the results referring to the repair techniques associated with the most relevant correlations. It is found that for floorings rehabilitation, the most likely techniques to be used are “R-A11 Replacement or reapplication of the cladding/glazing (partially or completely)”, “R-A12 Application of a new (adequate) cladding/finishing coat over the existent/replacement”, and “R-A14 Complete/partial removal of the existing coat in painted façades”. R-A11 is the most relevant and is considered next to identify the resources for its execution.
In the case of Table 20, “R-A11 Replacement or reapplication of the cladding/glazing (partially or completely)” refers to the following: (i) in adhesive ceramic floorings, outdoor glazed porcelain stoneware mosaic flooring, polished finish, with 25 × 25 × 5 mm tiles mounted on a mesh, medium range, water absorption capacity E < 0.5%, group BIa, according to NP EN 14411, with slip resistance greater than 45 according to ENV 12633, the substrate consisting of cement mortar, filling with a thin layer with cementitious adhesive, C1 TE, according to NP EN 12004, with reduced slip and extended setting time, and joint filling with improved cementitious grout, with reduced water absorption and high resistance to abrasion type CG 2 W A, white colour, in 2 mm thick joints; (ii) in wood floorings, outdoor deck flooring, made up of 21 × 95 × 1600/2400 mm Swedish pine solid wood boards, fixed using the hidden fixing system on 65 × 38 mm autoclave-treated Pinus pinaster wood clapboards, risk class 4 according to NP EN 335, 40 cm apart and resting on adjustable polyolefin supports with a flat round base, for heights between 30 mm and 50 mm; brushing and subsequent application of two coats of quick-drying water-based interior and exterior floor polish, Pino colour, satin finish, yield of 0.083 L/m2 each coat as a protective and decorative treatment, including stainless steel clips and screws for fixing the boards to the battens and special pieces.

4. Discussion

4.1. Most Common Diagnosis Methods to Prepare an Inspection

Section 3.1 establishes separately the relevant diagnosis methods to be used while inspecting roof claddings, façade elements/claddings, and floorings. In roof claddings, “D-C3 Infrared thermography“ is helpful in the detection of several defects, with the added advantages of (i) not requiring direct access to the roof, provided the angle of inspection is within limits mentioned in the literature [71] and (ii) also allowing for the inspection of the top area of the façades, where eventual leakages or water runoff (from the roof) can be detected. In façade elements/claddings, “D-C1 Measurement of the ambient and/or surface temperature and humidity”, “D-C3 Infrared thermography”, and “D-F4 Initial surface absorption test (ISAT) and Karsten-tube” seem to be more useful, considering the high relevance of humidity-related defects (superficial moisture, dirt, biological colonisation). As for floorings, “D-A4 Tell-tale gauge and gypsum testimonies”, “D-A5 Crack width ruler and crack-measuring microscope”, and “D-A6 Mechanical strain gauge” are the highlighted methods, as mechanical defects have a higher prevalence (cracking, fracture and splintering). Given these results, an essential kit to inspect the building envelope could involve these six diagnosis methods (D-A4, D-A5, D-A6, D-C1, D-C3, D-F4), given that they are useful for elements, and even more in specific building elements/materials.
Other authors also advise the use of an electronic moisture-reading meter or an electronic hygrometer (included in D-C1) and thermography (D-C3) in long lists of useful equipment for professionals dedicated to building surveys [5,72,73]. It should be noted that surprisingly, in the case of Douglas and Noy [72], testing equipment for crack assessment is not advised to prepare for the inspection. On the other hand, the Structural Engineering Institute and the American Society of Civil Engineers [5] highlight the importance of testing cracks in the context of air infiltration and long-term testing of movements in the building envelope. Wilson [73] also highlights the advantages of properly measuring cracks, as they are a relevant indicator of structural issues. Son and Yuen [63] also include crack-measuring equipment (callipers and gauges) in the set of basic equipment for building inspections, as well as electrical resistance meters for measuring moisture content. These authors consider thermography a specialised test. In 1993, with different equipment costs (higher), that could be justifiable, but not nowadays.

4.2. Most Common Types of Repair Techniques

Section 3.2 establishes separately significant repair techniques to prescribe while rehabilitating roof claddings, façade elements/claddings and floorings. In roof claddings, “R-A1 Cleaning” is relevant for many common defects, mainly associated with dirt accumulation and biological growth, both on the current surface and drainage system, which are very frequent and of paramount importance for the good performance of the building envelope. In façade elements/claddings, “R-A1 Cleaning”, “R-A2 Application of a protective coat (paint, varnish, water-repellent, antifungal, biocide)”, “R-A11 Replacement or reapplication of the cladding/glazing (partially or completely)”, and “R-A12 Application of a new (adequate) cladding/finishing coat over the existent/replacement” were identified as the most transversal repair techniques, all mostly referring to the outer layers of the cladding system, considering the prevalence of superficial defects (moisture, dirt, disaggregation, cracking, biological colonisation, vegetation growth, efflorescence/cryptoflorescence). As for floorings, “R-A11 Replacement or reapplication of the cladding/glazing (partially or completely)” is highlighted, particularly because it can solve a large span of common defects in these elements/materials.
Given these results, it is worth noting that repair techniques have specific needs in terms of materials, workload, and process of application depending on the building element/material. Nevertheless, given the categorisation of Pereira et al. [32], some repair techniques seem to heal a lot of the most frequent defects. Those techniques are cleaning (R-A1), application of a protective coat (R-A2), partial or complete replacement/reapplication of the cladding/flooring (R-A11), and replacement or application of a more suitable cladding/flooring (R-A12).
Furthermore, the specificity of repair techniques according to building elements/materials makes it more complex to perform a full analysis of the use of involved resources. To perform a preliminary framework for that kind of analysis, the application procedures for some materials were analysed according to freely available data [39]. These data were adapted to an LCA-based cradle-to-gate approach [38]. This is the first analysis of the kind in the literature, since usually, LCA uses standard data about the service life of materials, not specifically considering the maintenance procedures involved. The relevance of such an analysis is attested by some of the results presented in Section 3.2.3. For instance, to properly clean a flat roof, 10 L/m2 must be used, which, in larger buildings, may refer to an annual expenditure of more than 70,000 L of water (a rough estimate based on the size of Portugal’s largest hospital). Besides the expenditure of water, its eventual contamination during cleaning procedures should be considered, as well as methods to prevent it from reaching public mains. Additionally, the cost of cleaning a roof may also be high, taking into account that such a procedure should preferably be performed bi-annually (for the drainage system) and yearly (for the whole roof) in a proactive preventive approach [74]. If the same example is considered, but with a metallic pitched roof, the cost would have to comply with 191 h of labour of construction workers to clean gutters (EUR 4202), plus 910 l (EUR 23,831) of cleaning agent, plus 3829 h of labour of construction workers to clean the current surface of roof tiles (EUR 84,238) (costs based on data from CYPE Ingenieros S.A: [27] and retail prices in Portugal in April 2024). An annual cost of more than (not all costs are considered) EUR 8404 to clean gutters and EUR 112,271 to clean the whole roof are impactful in the service life cost of a building, thus affecting the economic component of life-cycle assessment.
In different orders of magnitude, cleaning procedures are also impactful in terms of cost and resource use per intervention in façades. Still, façade cleaning does not require annual implementation, and the most reasonable approach (proactive predictive) is to clean when inspection data advise that procedure. Consequently, depending on the performance requirements defined by the owners and users, cleaning may be performed in 5, 10, or 30-year intervals [75]. Still, according to the height of the building, the area to be cleaned can be much larger than that of flat or pitched roofs. Additionally, protective coatings should be applied after cleaning to prevent the severity of graffiti or other aggressive agents, which increases both the use of resources and costs.
In floorings, the replacement of materials is considered. The operations are more complex, including several types of products and stages of application. Even the application of a renewable material like wood decking boards implies the use of non-renewable materials like adjustable supports in polyolefin (700 units), stainless steel omega-shaped clips and screws (2500), and floor polish based on hybrid acrylic resins and polyurethane copolymers (166 L) (numbers for a 100 m² wood deck, which is relatively small). Even though one could argue that the replacement of floorings may occur only every 38 years (estimated service life of a wood flooring system exposed to moisture) [61], if non-functional factors are taken into account to determine when to replace the flooring, this interval can be drastically lower.
In this sense, in the future, LCA should consider the requirements in terms of the performance of claddings because that is very relevant to determining the periodicity of maintenance and repair operations, thus affecting the number of resources used and costs. Performance levels during the service life should be part of LCA’s functional unit.
Moreover, some costs and resources are not specified in Table 15, Table 17, Table 18 and Table 20, namely, energy costs, which are impactful in some procedures using electric tools, as well as due to transportation, depending on the source of materials used.
Nevertheless, it is the authors’ conviction that a detailed LCA of maintenance and repair operations would highlight their advantages when compared with a total refurbishment of buildings, not considering functional adaptations due to changes in use.

5. Conclusions

This study introduces a novel approach by applying an established methodology to a parallel context, creating inter-defect correlation matrices based on diagnosis methods and repair techniques within the domain of building pathology research. This approach is based on fieldwork data complemented by expert knowledge [34], while the literature generally presents information only based on the experts’ professional opinions. Furthermore, the research process had the purpose of performing an analysis of defects that could be investigated or solved by using the same means—diagnosis methods or repair techniques, respectively. In the first case, an essential kit of equipment/procedures for the diagnosis of claddings of the building envelope was determined, while, in the second case, the analysis went a little further, scrutinising the resources used to carry out some of the most transversal repair techniques in the building envelope. Such an analysis may be the starting point for a more extensive line of research regarding LCA of maintenance and repair operations in buildings, even more if the LCA of diagnosis methods is also dealt with.
The diagnosis methods considered in the referred essential kit are “D-A4 Tell-tale gauge and gypsum testimonies”, “D-A5 Crack width ruler and crack-measuring microscope”, “D-A6 Mechanical strain gauge”, “D-C1 Measurement of the ambient and/or surface temperature and humidity”, “D-C3 Infrared thermography”, and “D-F4 Initial surface absorption test (ISAT) and Karsten-tube”. They are all applicable to several materials and building elements and focus on some of the most common defects and causes of defects in the claddings of the building envelope.
As for repair techniques, those more transversal to several building elements/materials are “R-A1 Cleaning”, “R A2 Application of a protective coat (paint, varnish, water-repellent, antifungal, biocide)”, “R-A11 Replacement or reapplication of the cladding/glazing (partially or completely)”, and “R-A12 application of a new (adequate) cladding/finishing coat over the existent/replacement”. This set of techniques comprises procedures mostly applicable to the surface of the cladding, but if applied timely, they may avoid further deterioration of the underlying layers of the cladding system, as well as the substrate and bearing structure.
Although the authors dedicated all their efforts to base their conclusions on unbiased and reliable data, some limitations should be mentioned. The expert knowledge that led to the creation of the inter-defect data is mainly based on Portuguese construction methods and samples of Portuguese buildings. Although some of those methods are very common in the Western world, some regional specificities may affect the results. Furthermore, the dimensions, typologies, and use of buildings and cities in the Portuguese context require adequate caution when transposing the results to other contexts.
In any case, the provided information may be useful to researchers in the fields of LCA and LCC. In more general terms, this study is important for any practitioner in the field of architecture, engineering, and construction, but specifically for architects, engineers, and contractors dedicated to the rehabilitation of the building stock.

Author Contributions

Conceptualization, C.P.; methodology, C.P. and A.S.; validation, C.P. and A.S.; formal analysis, C.P. and A.S.; investigation, C.P.; data curation, C.P.; writing—original draft preparation, C.P.; writing—review and editing, A.S.; visualisation, C.P. All authors have read and agreed to the published version of this manuscript.

Funding

This research was funded by Fundação para a Ciência e a Tecnologia (FCT), grant number UIDB/04625/2020 from the research unit CERIS (DOI: 10.54499/UIDB/04625/2020), FCT-funded project CITIESTWINS (2022.15504.MIT), and A. Silva individual project CEECIND/01337/2017.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The raw data supporting the conclusions of this article will be made available by the authors upon request.

Acknowledgments

The authors gratefully acknowledge the support of the research unit Civil Engineering Research and Innovation for Sustainability (CERIS) and Fundação para a Ciência e a Tecnologia (FCT), who funded this research in the framework of project UIDB/04625/2020. The authors also acknowledge FCT’s funding of the project CITIESTWINS: A digital framework to merge durability data, maintenance models and energy retrofitting decisions (2022.15504.MIT). A. Silva acknowledges the support of FCT through the individual project CEECIND/01337/2017.

Conflicts of Interest

The authors declare no conflicts of interest. The funders had no role in the design of this study, in the collection, analyses, or interpretation of data, in the writing of this manuscript, or in the decision to publish the results.

References

  1. Di Giuseppe, E. Nearly Zero Energy Buildings and Proliferation of Microorganisms. A Current Issue for Highly Insulated and Airtight Building Envelopes; SpringerBriefs in Applied Sciences and Technology; Springer: Dordrecht, The Netherlands, 2013; ISBN 9783319023557. [Google Scholar]
  2. Ribeiro, T.; Cóias e Silva, V. Anomalies in Buildings—“Construdoctor’s Case Studies.”. In Proceedings of the 2.o Simpósio Internacional sobre Patologia, Durabilidade e Reabilitação dos Edifícios. “Aprendendo com os Erros e Defeitos da Construção”, Lisbon, Portugal, 6–8 November 2003; Laboratório Nacional de Engenharia Civil (LNEC): Lisbon, Portugal, 2003; pp. 221–230. [Google Scholar]
  3. Juan, Y.-K.; Kim, J.H.; Roper, K.; Castro-Lacouture, D. GA-Based Decision Support System for Housing Condition Assessment and Refurbishment Strategies. Autom. Constr. 2009, 18, 394–401. [Google Scholar] [CrossRef]
  4. Rojas, E.M.; Songer, A.D. Computer-Aided Facilities Inspection. J. Infrastruct. Syst. 1999, 5, 79–85. [Google Scholar] [CrossRef]
  5. SEI/ASCE 30-00; Guideline for Condition Assessment of the Building Envelope. Structural Engineering Institute, American Society of Civil Engineers: Reston, VA, USA, 2000; ISBN 0784404836.
  6. ASCE/SEI 30-14; Guideline for Condition Assessment of the Building Envelope. Structural Engineering Institute, American Society of Civil Engineers: Reston, VA, USA, 2014; ISBN 9780784413258.
  7. Hegazy, T.; Elhakeem, A.; Ahluwalia, S.S.; Attalla, M. MOST-FIT: Support Techniques for Inspection and Life Cycle Optimization in Building Asset Management. Comput. Civ. Infrastruct. Eng. 2012, 27, 130–142. [Google Scholar] [CrossRef]
  8. Linggar, S.; Aminullah, A.; Triwiyono, A. Analysis of Building and Its Components Condition Assessment Case Study of Dormitory Buildings. MATEC Web Conf. 2019, 258, 03003. [Google Scholar] [CrossRef]
  9. Matos, R.V.; Rodrigues, F.S.; Rodrigues, H.F.; Costa, A.G. Strategies to Support Facility Management Resourcing Building Information Modelling. In Proceedings of the XV International Conference on Durability of Building Materials and Components, Barcelona, Spain, 20–23 October 2020; Serrat, C., Casas, J.R., Gibert, V., Eds.; International Center for Numerical Methods in Engineering (CIMNE): Barcelona, Spain, 2020; pp. 1759–1766. [Google Scholar]
  10. Matos, R.; Rodrigues, F.; Rodrigues, H.; Costa, A. Building Condition Assessment Supported by Building Information Modelling. J. Build. Eng. 2021, 38, 102186. [Google Scholar] [CrossRef]
  11. Bortolini, R.; Forcada, N. A Probabilistic Performance Evaluation for Buildings and Constructed Assets. Build. Res. Inf. 2020, 48, 838–855. [Google Scholar] [CrossRef]
  12. Pereira, C.I.F. Sistema Global de Inspeção, Diagnóstico e Reabilitação de Elementos Construtivos Não-Estruturais Da Envolvente de Edifícios; Instituto Superior Técnico, Universidade de Lisboa: Lisboa, Portugal, 2022. [Google Scholar]
  13. Pereira, C.; de Brito, J.; Silvestre, J.D. Harmonising Correlation Matrices within a Global Building Expert Knowledge-Based Inspection System. Constr. Build. Mater. 2021, 272, 121655. [Google Scholar] [CrossRef]
  14. Pereira, C.; de Brito, J.; Silvestre, J.D. Harmonising the Classification of Diagnosis Methods within a Global Building Inspection System: Proposed Methodology and Analysis of Fieldwork Data. Eng. Fail. Anal. 2020, 115, 104627. [Google Scholar] [CrossRef]
  15. EN ISO 4628-4:2016; Paints and Varnishes—Evaluation of Degradation of Coatings—Designation of Quantity and Size of Defects, and of Intensity of Uniform Changes in Appearance—Part 4: Assessment of Degree of Cracking. European Committee for Standardization: Brussels, Belgium, 2016.
  16. EN ISO 4628-2:2016; Paints and Varnishes—Evaluation of Degradation of Coatings—Designation of Quantity and Size of Defects, and of Intensity of Uniform Changes in Appearance—Part 2: Assessment of Degree of Blistering. European Committee for Standardization: Brussels, Belgium, 2016.
  17. EN ISO 2808:2019; Paints and Varnishes—Determination of Film Thickness. European Committee for Standardization: Brussels, Belgium, 2019.
  18. ASTM E2884-17; Standard Guide for Eddy Current Testing of Electrically Conducting Materials Using Conformable Sensor Arrays. ASTM International: West Conshohocken, PA, USA, 2017.
  19. ASTM D8231-19; Standard Practice for the Use of a Low Voltage Electronic Scanning System for Detecting and Locating Breaches in Roofing and Waterproofing Membranes. ASTM International: West Conshohocken, PA, USA, 2019.
  20. ASTM D7877-14; Standard Guide for Electronic Methods for Detecting and Locating Leaks in Waterproof Membranes. ASTM International: West Conshohocken, PA, USA, 2014.
  21. ASTM C876-15; Standard Test Method for Corrosion Potentials of Uncoated Reinforcing Steel in Concrete. ASTM International: West Conshohocken, PA, USA, 2015.
  22. ISO 18251-1:2017; Non-Destructive Testing—Infrared Thermography—Part 1: Characteristics of System and Equipment. International Organization for Standardization: Geneva, Switzerland, 2017.
  23. EN ISO 15184:2020; Paints and Varnishes—Determination of Film Hardness by Pencil Test. European Committee for Standardization: Brussels, Belgium, 2020.
  24. ASTM D4541-17; Standard Test Method for Pull-off Strength of Coatings Using Portable Adhesion Testers. ASTM International: West Conshohocken, PA, USA, 2017.
  25. ASTM D7234-19; Standard Test Method for Pull-off Adhesion Strength of Coatings on Concrete Using Portable Pull-Off Adhesion Testers. ASTM International: West Conshohocken, PA, USA, 2019.
  26. EN ISO 2409:2013; Paints and Varnishes—Cross-Cut Test. European Committee for Standardization: Brussels, Belgium, 2013.
  27. ASTM D6677-18; Standard Test Method for Evaluating Adhesion by Knife. ASTM International: West Conshohocken, PA, USA, 2018.
  28. EN ISO 4628-6:2011; Paints and Varnishes—Evaluation of Degradation of Coatings—Designation of Quantity and Size of Defects, and of Intensity of Uniform Changes in Appearance—Part 6: Assessment of Degree of Chalking by Tape Method. European Committee for Standardization: Brussels, Belgium, 2011.
  29. ASTM E741-11(2017); Standard Test Method for Determining Air Change in a Single Zone by Means of a Tracer Gas Dilution. ASTM International: West Conshohocken, PA, USA, 2017.
  30. ASTM D1535-14(2018); Standard Practice for Specifying Color by the Munsell System. ASTM International: West Conshohocken, PA, USA, 2018.
  31. ASTM E2970-15; Standard Practice for Specifying Color by the Natural Colour System (NCS). ASTM International: West Conshohocken, PA, USA, 2015.
  32. Pereira, C.; de Brito, J.; Silvestre, J.D. Harmonized Classification of Repair Techniques in a Global Inspection System: Proposed Methodology and Analysis of Fieldwork Data. J. Perform. Constr. Facil. 2021, 35, 04020122. [Google Scholar] [CrossRef]
  33. Pereira, C.; Silva, A.; de Brito, J.; Silvestre, J.D. Urgency of Repair of Building Elements: Prediction and Influencing Factors in Façade Renders. Constr. Build. Mater. 2020, 249, 118743. [Google Scholar] [CrossRef]
  34. de Brito, J.; Pereira, C.; Silvestre, J.D.; Flores-Colen, I. Expert Knowledge-Based Inspection Systems. In Inspection, Diagnosis and Repair of the Building Envelope; Springer: Cham, Switzerland, 2020; ISBN 9783030424459. [Google Scholar]
  35. Garcia, J.; de Brito, J. Inspection and Diagnosis of Epoxy Resin Industrial Floor Coatings. J. Mater. Civ. Eng. 2008, 20, 128–136. [Google Scholar] [CrossRef]
  36. Silvestre, J.D.; de Brito, J. Ceramic Tiling Inspection System. Constr. Build. Mater. 2009, 23, 653–668. [Google Scholar] [CrossRef]
  37. Benjamin, J.R.; Cornell, C.A. Probability, Statistics, and Decision for Civil Engineers; Dover Publications, Inc.: Mineola, NY, USA, 2016; ISBN 978-0-486-78072-6. [Google Scholar]
  38. Silvestre, J.D.; De Brito, J.; Pinheiro, M.D. Environmental Impacts and Benefits of the End-of-Life of Building Materials—Calculation Rules, Results and Contribution to a “Cradle to Cradle” Life Cycle. J. Clean. Prod. 2014, 66, 37–45. [Google Scholar] [CrossRef]
  39. CYPE Ingenieros, S.A. Gerador de Preços Para Construção Civil. Portugal. Available online: http://www.geradordeprecos.info/reabilitacao/ (accessed on 17 October 2023).
  40. Garcez, N.; Lopes, N.; de Brito, J.; Sá, G. Pathology, Diagnosis and Repair of Pitched Roofs with Ceramic Tiles: Statistical Characterisation and Lessons Learned from Inspections. Constr. Build. Mater. 2012, 36, 807–819. [Google Scholar] [CrossRef]
  41. Conceição, J.; Poça, B.; de Brito, J.; Flores-Colen, I.; Castelo, A. Data Analysis of Inspection, Diagnosis, and Rehabilitation of Flat Roofs. J. Perform. Constr. Facil. 2019, 33, 04018100. [Google Scholar] [CrossRef]
  42. Ramos, R.; Silva, A.; de Brito, J.; Gaspar, P.L. Methodology for the Service Life Prediction of Ceramic Claddings in Pitched Roofs. Constr. Build. Mater. 2018, 166, 386–399. [Google Scholar] [CrossRef]
  43. Madsen, J. The Top 10 Most Common Roof Problems. Available online: http://jeffersonmatters.org/wp-content/uploads/2012/09/Roof-top10roofproblemns.pdf (accessed on 28 August 2018).
  44. Santos, A.; Vicente, M.; de Brito, J.; Flores-Colen, I.; Castelo, A. Analysis of the Inspection, Diagnosis, and Repair of External Door and Window Frames. J. Perform. Constr. Facil. 2017, 31, 04017098. [Google Scholar] [CrossRef]
  45. Sá, G.; Sá, J.; de Brito, J.; Amaro, B. Statistical Survey on Inspection, Diagnosis and Repair of Wall Renderings. J. Civ. Eng. Manag. 2015, 21, 623–636. [Google Scholar] [CrossRef]
  46. Amaro, B.; Saraiva, D.; de Brito, J.; Flores-Colen, I. Statistical Survey of the Pathology, Diagnosis and Rehabilitation of ETICS in Walls. J. Civ. Eng. Manag. 2014, 20, 511–526. [Google Scholar] [CrossRef]
  47. Pires, R.; de Brito, J.; Amaro, B. Statistical Survey of the Inspection, Diagnosis and Repair of Painted Rendered Façades. Struct. Infrastruct. Eng. 2015, 11, 605–618. [Google Scholar] [CrossRef]
  48. da Silva, C.; Coelho, F.; de Brito, J.; Silvestre, J.; Pereira, C. Statistical Survey on Inspection, Diagnosis and Repair of Architectural Concrete Surfaces. J. Perform. Constr. Facil. 2017, 31, 04017097. [Google Scholar] [CrossRef]
  49. Silvestre, J.D.; de Brito, J. Ceramic Tiling in Building Façades: Inspection and Pathological Characterization Using an Expert System. Constr. Build. Mater. 2011, 25, 1560–1571. [Google Scholar] [CrossRef]
  50. Neto, N.; de Brito, J. Validation of an Inspection and Diagnosis System for Anomalies in Natural Stone Cladding (NSC). Constr. Build. Mater. 2012, 30, 224–236. [Google Scholar] [CrossRef]
  51. Fernandes, D.; de Brito, J.; Silva, A. Methodology for Service Life Prediction of Window Frames. Can. J. Civ. Eng. 2019, 46, 1010–1020. [Google Scholar] [CrossRef]
  52. Vieira, S.M.; Silva, A.; Sousa, J.M.C.; De Brito, J.; Gaspar, P.L. Modelling the Service Life of Rendered Facades Using Fuzzy Systems. Autom. Constr. 2015, 51, 1–7. [Google Scholar] [CrossRef]
  53. Ximenes, S.; de Brito, J.; Gaspar, P.L.; Silva, A. Modelling the Degradation and Service Life of ETICS in External Walls. Mater. Struct. 2015, 48, 2235–2249. [Google Scholar] [CrossRef]
  54. Chai, C.; de Brito, J.; Gaspar, P.L.; Silva, A. Predicting the Service Life of Exterior Wall Painting: Techno-Economic Analysis of Alternative Maintenance Strategies. J. Constr. Eng. Manag. 2014, 140, 04013057. [Google Scholar] [CrossRef]
  55. Serralheiro, M.I.; de Brito, J.; Silva, A. Methodology for Service Life Prediction of Architectural Concrete Facades. Constr. Build. Mater. 2017, 133, 261–274. [Google Scholar] [CrossRef]
  56. Bordalo, R.; de Brito, J.; Gaspar, P.L.; Silva, A. Service Life Prediction Modelling of Adhesive Ceramic Tiling Systems. Build. Res. Inf. 2011, 39, 66–78. [Google Scholar] [CrossRef]
  57. Silva, A.; de Brito, J.; Gaspar, P.L. Service Life Prediction Model Applied to Natural Stone Wall Claddings (Directly Adhered to the Substrate). Constr. Build. Mater. 2011, 25, 3674–3684. [Google Scholar] [CrossRef]
  58. Delgado, A.; Pereira, C.; de Brito, J.; Silvestre, J.D. Defect Characterization, Diagnosis and Repair of Wood Flooring Based on a Field Survey. Mater. Construcción 2018, 68, e149. [Google Scholar] [CrossRef]
  59. Garcia, J.M.L.B.M. Sistema de Inspecção e Diagnóstico de Revestimentos Epóxidos Em Pisos Industriais; Universidade Técnica de Lisboa, Instituto Superior Técnico: Lisboa, Portugal, 2006. [Google Scholar]
  60. Carvalho, C.; de Brito, J.; Flores-Colen, I.; Pereira, C. Pathology and Rehabilitation of Vinyl and Linoleum Floorings in Health Infrastructures: Statistical Survey. Buildings 2019, 9, 116. [Google Scholar] [CrossRef]
  61. Coelho, P.; Silva, A.; de Brito, J. How Long Can a Wood Flooring System Last? Buildings 2021, 11, 23. [Google Scholar] [CrossRef]
  62. Valente de Almeida, J. Ceramics. In Materials for Construction and Civil Engineering: Science, Processing, and Design; Gonçalves, M.C., Margarido, F., Eds.; Springer: Cham, Switzerland, 2015; pp. 303–334. ISBN 978-3-319-08236-3. [Google Scholar]
  63. Son, L.H.; Yuen, G.C.S. Building Maintenance Technology; Macmillan Building and Surveying Series; Macmillan: London, UK, 1993; ISBN 978-1-349-23150-8. [Google Scholar]
  64. Honeyborne, D.B. Weathering and Decay of Masonry. In Conservation of Building and Decorative Stone; Ashurst, J., Dimes, F.G., Eds.; Butterworth-Heinemann: Oxford, UK, 1998; pp. 153–184. ISBN 9780750638982. [Google Scholar]
  65. Gerns, E.A.; Wonneberger, B.; Scheffler, M.J. Design and Selection of Exterior Granite Pavers. In Dimension Stone Cladding: Design, Construction, Evaluation, and Repair ASTM STP 1394; Hoigard, K.R., Ed.; ASTM: Wet Conshohocken, PA, USA, 2000; pp. 109–120. ISBN 0-8031-2875-4. [Google Scholar]
  66. The Resin Flooring Association. Guide to the Specification and Application of Synthetic Resin Flooring, 7th ed.; The Resin Flooring Association (FeRFA): Staffordshire, UK, 2016; ISBN 0-9538020-1-9. [Google Scholar]
  67. Polyfloor Floor Care & Maintenance. In Polyfloor General Maintenance Guide; Polyfloor: Mississauga, ON, Canada; Available online: https://www.polyflor.ca/usercontent//FloorcareMaintenance.pdf (accessed on 17 November 2020).
  68. Delgado, A.; de Brito, J.; Silvestre, J.D. Inspection and Diagnosis System for Wood Flooring. J. Perform. Constr. Facil. 2013, 27, 564–574. [Google Scholar] [CrossRef]
  69. Ventura, M.; Dias, I.S.; Flores-Colen, I.; Silva, A. Pathology and Proactive Maintenance of Floor Finishes. Int. J. Build. Pathol. Adapt. 2022, 41, 588–605. [Google Scholar] [CrossRef]
  70. Sika Services AG. Flooring. Sika Technology and Concepts for Flooring and Coating; Sika Services AG: Zurich, Switzerland, 2009. [Google Scholar]
  71. Edis, E.; Flores-Colen, I.; de Brito, J. Passive Thermographic Detection of Moisture Problems in Façades with Adhered Ceramic Cladding. Constr. Build. Mater. 2014, 51, 187–197. [Google Scholar] [CrossRef]
  72. Douglas, J.; Noy, E.A. Building Surveys and Reports, 4th ed.; Wiley-Blackwell: Chichester, UK, 2011; ISBN 1405121475. [Google Scholar]
  73. Wilson, F. Building Materials Evaluation Handbook; Van Nostrand Reinhold Company: New York, NY, USA, 1984; ISBN 9781468466522. [Google Scholar]
  74. Morgado, J.; Flores-Colen, I.; de Brito, J.; Silva, A. Maintenance Planning of Pitched Roofs in Current Buildings. J. Constr. Eng. Manag. 2017, 143, 05017010. [Google Scholar] [CrossRef]
  75. Ferreira, C.; Neves, L.C.; Silva, A.; de Brito, J. Stochastic Maintenance Models for Ceramic Claddings. Struct. Infrastruct. Eng. 2020, 16, 247–265. [Google Scholar] [CrossRef]
Figure 1. Diagram of the scope and objectives of the present research.
Figure 1. Diagram of the scope and objectives of the present research.
Applsci 14 06947 g001
Figure 2. Methodology followed to build and analyse correlation matrices to reach the proposed goals (considering the information of Garcia and de Brito [35] and Pereira et al. [13]).
Figure 2. Methodology followed to build and analyse correlation matrices to reach the proposed goals (considering the information of Garcia and de Brito [35] and Pereira et al. [13]).
Applsci 14 06947 g002
Figure 3. Levels of severity of stains/colour changes in painted façades: (a) Level 0; (b) Level 1; (c) Level 2; (d) Level 3; (e) Level 4.
Figure 3. Levels of severity of stains/colour changes in painted façades: (a) Level 0; (b) Level 1; (c) Level 2; (d) Level 3; (e) Level 4.
Applsci 14 06947 g003
Table 1. Classification list of diagnosis methods within a global inspection system for the non-structural building envelope [14].
Table 1. Classification list of diagnosis methods within a global inspection system for the non-structural building envelope [14].
CodeCategoryCodeDiagnosis Method
D-AAssisted sensory analysisD-A1Endoscopy (NDT)
D-A2Analysis by touch (NDT)
D-A3Assessment of the slope, flatness, orthogonality, and alignments (NDT)
D-A4Tell-tale gauge and gypsum testimonies (NDT)
D-A5Crack width ruler and crack-measuring microscope (NDT)
D-A6Mechanical strain gauge (NDT)
D-A7Assessment of the cracking and blistering level (standards EN ISO 4628-4:2016 [15] and EN ISO 4628-2:2016 [16]) (NDT)
D-A8Polyethylene film (NDT)
D-A9Thickness measurement by depth gauging and difference in thickness (standard EN ISO 2808:2019 [17]) (DT)
D-BElectrical methodsD-B1Eddy currents (standard ASTM E2884-17 [18]) (NDT)
D-B2Leakage electrical detection (standards ASTM D8231-19 [19] and ASTM D7877-14 [20]) (NDT)
D-B3Electrical capacitance test (NDT)
D-B4Magnetometry (NDT)
D-B5Conductivity meter (NDT)
D-B6Galvanic half-cell (standard ASTM C876-15 [21]) (DT)
D-CThermo-hygrometric methodsD-C1Measurement of the ambient and/or surface temperature and humidity (NDT)
D-C2Measurement of the in-depth humidity (DT)
D-C3Infrared thermography (standard ISO 18251-1:2017 [22]) (NDT)
D-DSound and acoustic methodsD-D1Ultrasound (NDT)
D-D2Percussion (NDT)
D-D3Assessment of acoustic insulation (NDT)
D-ENuclear methodsD-E1Nuclear method (NDT)
D-FHydric methodsD-F1Watertightness test (NDT)
D-F2Water jet (NDT)
D-F3Submersion of the base of window frames (NDT)
D-F4Initial surface absorption test (ISAT) and Karsten-tube (NDT)
D-GMechanical methodsD-G1Sphere impact, grid cutting, scratching and abrasion tests (Martinet Baronnie) (DT)
D-G2Pencil method (standard EN ISO 15184:2020 [23]) (DT)
D-G3Surface hardness and pendulum rebound hammer (NDT)
D-G4Metal blade (NDT)
D-G5Micro-perforation (DT)
D-G6Controlled penetration and perforation test (DT)
D-G7Pull-off test (standards ASTM D4541-17 [24] and ASTM D7234-19 [25]) (DT)
D-G8Coring (DT)
D-G9Adhesion assessment by grid and knife tests (standards EN ISO 2409:2013 [26] and ASTM D6677-18 [27]) (DT)
D-G10Adhesive tape method (standard EN ISO 4628-6:2011 [28]) (NDT)
D-HPressure methodsD-H1Ventilator test (standard ASTM E741-11(2017) [29]) (NDT)
D-IColour methodsD-I1Colour-meter (NDT)
D-I2Munsell system or NCS scale colour specification (standards ASTM D1535-14(2018) [30] and ASTM E2970-15 [31]) (NDT)
D-JChemical methodsD-J1Speedy moisture test (DT)
D-J2Test strips and field kit (NDT)t
D-J3Phenolphthalein indicator (NDT)
Note: NDT = non-destructive test; DT = destructive test.
Table 2. Classification list of repair techniques within a global inspection system for the non-structural building envelope [32].
Table 2. Classification list of repair techniques within a global inspection system for the non-structural building envelope [32].
CodeCategoryCodeRepair Technique
R-ASurface of the claddingR-A1Cleaning (cr, pr, pmw)
R-A2Application of a protective coat (paint, varnish, water-repellent, antifungal, biocide) (cr, pr, pmw)
R-A3Corrosion removal and re-establishment of the anti-corrosion protection in metallic elements (cr)
R-A4Surface rehabilitation of the plastic external claddings of pitched roofs (cr)
R-A5Repair/execution of supplementary watertightness measures in pitched roofs (cr, pr)
R-A6Creation of pathways (pr)
R-A7Application of ventilation systems/accessories (cr, pr)
R-A8Encapsulation of asbestos–cement external claddings of pitched roofs (pr)
R-A9Application of spray polyurethane foam (SPF) on the external surface of pitched roofs (cr, pr)
R-A10Glazing repair in door and window frames (cr)
R-A11Replacement or reapplication of the cladding/glazing (partially or completely) (cr, pr)
R-A12Application of a new (adequate) cladding/finishing coat over the existent/replacement (cr, pr, pmw)
R-A13Application of another type of cladding (not epoxy) (cr)
R-A14Treatment of cracks or other holes in the cladding (cr)
R-A15Treatment of biodegradation in wood floorings (cr)
R-A16Complete/partial removal of the existing coat in painted façades (cr)
R-A17Correction of surface irregularities or evening an architectural concrete surface with mortar (cr)
R-BCladding systemR-B1Application of underlayment in pitched roofs (pr)
R-B2Flocage in metallic claddings of pitched roofs (pr)
R-B3Application of spray polyurethane foam (SPF) on the interior surface of pitched roofs (cr, pr)
R-B4Application/repair/replacement of the vapour barrier (cr, pr, pmw)
R-B5Application/repair/replacement of the thermal insulation (cr, pr)
R-B6Application/repair/replacement of the waterproofing system or separation layer in flat roofs (cr, pr)
R-B7Injection of filling resins (bedding material) (cr)
R-B8Reinforcement of the bedding layer in localised areas (cr, pr)
R-B9Reinforcement with metallic elements or composite materials in wood floorings (cr)
R-B10Consolidation with concrete in wood floorings (cr)
R-B11Execution of prostheses or application of reinforcement profiles in door and window frames (cr, pr)
R-B12Deformation repair (distortion/shrinkage/warpage/expansion) in door and window frames (cr)
R-B13Change/replacement/repair of the fastening system or correction of holes in plates or substrate (cr, pr)
R-B14Application of a higher performance render (cr, pr)
R-B15Perforation/gap filling in ETICS (cr)
R-B16Repair of corroded reinforcement/concrete cover spalling in architectural concrete surfaces (cr)
R-B17Application of an additional concrete layer in architectural concrete surfaces (cr, pr)
R-CChange in the bearing structure/substrateR-C1Execution of a roof slab in pitched roofs (cr)
R-C2Repair/reinforcement/replacement of the bearing structure in pitched roofs (cr, pr)
R-C3Application/replacement of the shaping or levelling layer (cr)
R-C4Repair of dead cracks in the substrate and reapplication of the cladding (cr, pr)
R-C5Pavement levelling in epoxy resin floor coatings (cr, pr)
R-DSingularitiesR-D1Application/repair/replacement of expansion joints (cr, pr, pmw)
R-D2Replacement/repair of current joints’ filling material and/or joints cleaning (cr, pr, pmw)
R-D3Application of fungicide, biocide, or herbicide in joints (cr, pr)
R-D4Joint thickness increase or joint insertion (cr, pr)
R-D5Repair/application of tail-ends and associated protection elements (cr, pr, pmw)
R-D6Application/repair/replacement/cleaning of drainage systems/plumbing (cr, pr)
R-D7Removal of corroded or damaged metallic elements, with hole and notch filling (if applicable) (cr, pr, pmw)
R-D8Repair of water penetration spots (cr, pr)
R-D9Protecting or smoothing of protruding corners or edges (cr, pr)
R-D10Cleaning of façade’s horizontal areas in adhesive ceramic tiling (pr, pmw)
R-D11Repair, insertion, or replacement of sealants or insulation mastics in door and window frames (cr, pr)
R-D12Replacement of degraded or missing elements in door and window frames (cr, pr)
R-D13Adjustment, replacement, or additional installation of hardware (hinges/locks/span-frame connections) in door and window frames (cr, pr)
R-D14Lowering of the tail-end area in epoxy resin floor coatings (cr, pr, pmw)
R-D15Execution of coves in epoxy resin floor coatings (cr, pr, pmw)
R-D16Correction of geometrical construction details (pr)
Note: cr = curative repair; pr = preventive repair; pmw = planned maintenance works.
Table 3. Classification list of defects within a global inspection system for the non-structural building envelope [33].
Table 3. Classification list of defects within a global inspection system for the non-structural building envelope [33].
CodeCategoryCodeDefect
A-ADefects of physical natureA-A1Leakage damp
A-A2Surface moisture
A-A3Dirt and accumulation of debris
A-A4Colour changes
A-A5Spalling/peeling/exfoliation and pop-outs
A-A6Cohesion loss/disaggregation and chalking
A-BDefects of chemical natureA-B1Biodeterioration/biological growth
A-B2Vegetation growth
A-B3Efflorescence/cryptoflorescence and carbonation
A-B4Blistering/bulging
A-B5Corrosion on the current surface
A-B6Corrosion in metallic fastening or tail-end elements
A-CDefects of mechanical natureA-C1Mapped cracking
A-C2Oriented cracking on the current surface
A-C3Fracture or splintering on the current surface
A-C4Cracking and/or splintering adjacent to joints/edges
A-C5Wear or scaling of the finishing coat
A-C6Scratches/grooves and deep wear
A-C7Warpage, swelling, deformation, and other flatness deficiencies
A-C8Material gap/puncture
A-C9Detachment
A-C10Loss of adhesion
A-C11Bending and rupture of metallic fastening elements
A-DOther defectsA-D1Flaws in tail-end elements
A-D2Misalignment of cladding elements
A-D3Finishing defects/discontinuities in architectural concrete surfaces
A-D4Finishing colour flaws in painted façades
A-D5Finishing texture flaws in painted façades
A-D6Degradation of the filling material of current joints
A-D7Absence/loss of filling material in connecting elements or current joints
A-D8Inadequate operation of expansion joints in flat roofs
A-D9Insufficient or excessive overlap of the cladding elements in roofs
A-D10Clearances/gaps in door and window frames
A-D11Absent or damaged hinges or locks in door and window frames
A-D12Ponding/insufficient or excessive slope in roofs
A-D13Inadequate operation of elements of the rainwater drainage system
A-D14Deficient capping adjacent to flat roofs
A-D15Incorrect or deficient interventions in claddings of pitched roofs
Table 4. Excerpt of the door and window frames’ layer of the defects–diagnosis methods correlation matrix from the global inspection system developed by Pereira [12].
Table 4. Excerpt of the door and window frames’ layer of the defects–diagnosis methods correlation matrix from the global inspection system developed by Pereira [12].
Diagnosis Methods
DefectsD-C1D-C2D-C3D-D1D-D2D-D3
A-A1101001
A-A2201000
A-A3100000
A-A4000000
A-A5000000
A-A6000000
Note: refer to Table 3 and Table 1 for the designation of each defect and diagnosis method, respectively.
Table 5. Excerpt of the door and window frames’ layer of the defects–repair techniques correlation matrix from the global inspection system developed by Pereira [12].
Table 5. Excerpt of the door and window frames’ layer of the defects–repair techniques correlation matrix from the global inspection system developed by Pereira [12].
Repair Techniques
DefectsR-A1R-A2R-A3R-A4R-A5R-A6R-A7R-A8R-A9R-A10R-A11R-A12R-A13R-A14
A-A111100010001001
A-A200000020000000
A-A322000000000101
A-A400000000000102
A-A500000000000000
A-A600000000000000
Note: refer to Table 3 and Table 2 for the designation of each defect and repair technique, respectively.
Table 6. Excerpt of the door and window frames’ layer of the new inter-defects correlation matrix based on the defects–diagnosis methods correlation matrix from the global inspection system developed by Pereira [12].
Table 6. Excerpt of the door and window frames’ layer of the new inter-defects correlation matrix based on the defects–diagnosis methods correlation matrix from the global inspection system developed by Pereira [12].
Defects
DefectsA-A1A-A2A-A3A-A4A-A5A-A6
A-A1-13%8%0%0%0%
A-A250%-33%0%0%0%
A-A350%50%-0%0%0%
A-A40%0%0%-0%0%
A-A50%0%0%0%-0%
A-A60%0%0%0%0%-
Note: refer to Table 3 for the designation of each defect.
Table 7. Excerpt of the door and window frames’ layer of the new inter-defects correlation matrix based on the defects–repair techniques correlation matrix from the global inspection system developed by Pereira [12].
Table 7. Excerpt of the door and window frames’ layer of the new inter-defects correlation matrix based on the defects–repair techniques correlation matrix from the global inspection system developed by Pereira [12].
Defects
DefectsA-A1A-A2A-A3A-A4A-A5A-A6
A-A1-17%37%30%0%0%
A-A250%-10%0%0%0%
A-A361%6%-28%0%0%
A-A456%0%31%-0%0%
A-A50%0%0%0%-0%
A-A60%0%0%0%0%-
Note: refer to Table 3 for the designation of each defect.
Table 8. Excerpt of the roof claddings’ sums matrix to highlight the most relevant correlations regarding diagnosis methods.
Table 8. Excerpt of the roof claddings’ sums matrix to highlight the most relevant correlations regarding diagnosis methods.
Defects
DefectsA-A1A-A2A-A3A-A4A-A5A-A6
A-C1110000
A-C2110000
A-C3220000
A-C4110000
A-C5000000
A-C6000000
A-C7000000
A-C8110000
A-C9001000
A-C10001000
A-C11000000
Note: refer to Table 3 for the designation of each defect.
Table 9. Excerpt of the façade elements/claddings’ sums matrix to highlight the most relevant correlations regarding repair techniques.
Table 9. Excerpt of the façade elements/claddings’ sums matrix to highlight the most relevant correlations regarding repair techniques.
Defects
DefectsA-A1A-A2A-A3A-A4A-A5A-A6
A-B1234200
A-B2122100
A-B3132311
A-B4110011
A-B5100000
A-B6000000
Note: refer to Table 3 for the designation of each defect.
Table 10. Excerpt of the floorings sums matrix to highlight the most relevant correlations regarding diagnosis methods.
Table 10. Excerpt of the floorings sums matrix to highlight the most relevant correlations regarding diagnosis methods.
Defects
DefectsA-C1A-C2A-C3A-C4A-C5A-C6A-C7A-C8A-C9A-C10A-C11
A-C103100000000
A-C230110000000
A-C312010001010
A-C412100000000
A-C500000000000
A-C601000001000
A-C711000100010
A-C800000010010
A-C900000010000
A-C1000000000000
A-C1100000010000
Note: refer to Table 3 for the designation of each defect.
Table 11. Analysis of the results for claddings of roofs based on the new inter-defects correlation matrix considering diagnosis methods.
Table 11. Analysis of the results for claddings of roofs based on the new inter-defects correlation matrix considering diagnosis methods.
Building Element
/Material
Defects That Can Be Diagnosed by the Same MethodsDiagnosis Methods Used in ECPRDiagnosis Methods Used in FRDiagnosis Methods Used in Both
Roof claddings—external claddings of pitched roofs (ECPR); flat roofs (FR)A-A2 and A-A1D-C1, D-C3D-B2, D-B3, D-C3, D-E1, D-F1D-C3
A-A3 and A-D12D-A3D-A3D-A3
A-C3 and A-A1D-C3D-B2, D-B3, D-C3, D-E1, D-F1D-C3
A-C3 and A-A2D-C3D-B2, D-B3, D-C3, D-E1, D-F1D-C3
A-D1 and A-A1D-C3D-B2, D-C3, D-F1D-C3
A-D1 and A-A2D-C3D-B2, D-C3, D-F1D-C3
A-D1 and A-C3D-C3D-B2, D-C3, D-F1D-C3
Note: refer to Table 3 and Table 1 for the designation of each defect and diagnosis method, respectively.
Table 12. Analysis of the results for façade elements/claddings based on the new inter-defects correlation matrix considering diagnosis methods.
Table 12. Analysis of the results for façade elements/claddings based on the new inter-defects correlation matrix considering diagnosis methods.
Building Element/
Material
Defects That Can Be Diagnosed by the Same MethodsDiagnosis Methods Used in DWFDiagnosis Methods Used in WRDiagnosis Methods Used in ETICSDiagnosis Methods Used in PFDiagnosis Methods Used in ACSDiagnosis Methods Used in ACTDiagnosis Methods Used in NSCDiagnosis Methods for 3 or More Materials
Façade elements and façade claddings—door and window frames (DWF); wall renders (WR); external thermal insulation composite systems (ETICS); painted façades (PF); architectural concrete surfaces (ACS); adhesive ceramic tiling (ACT); natural stone claddings (NSC)A-A2 and A-B1D-C1D-C1, D-C3, D-F4, D-J1D-C1, D-C3, D-F4-D-C1, D-C3, D-F4--D-C1, D-C3, D-F4,
A-A3 and A-B1/
A-B1 and A-A3
D-A3, D-C1D-C1, D-C3, D-F4, D-J1D-C1, D-C3, D-F4D-A2, D-B5, D-C1, D-C2D-C1, D-C3, D-F4-D-C2D-C1, D-C3, D-F4
A-C1 and A-C2/
A-C2 and A-C1
-D-A5, D-C1, D-D1, D-F4D-A4, D-A5, D-C1, D-C3-D-A5, D-B4, D-J3D-A4, D-A5, D-D2, D-G1D-A4, D-A5, D-A6, D-D1D-A4, D-A5
Note: refer to Table 3 and Table 1 for the designation of each defect and diagnosis method, respectively.
Table 13. Analysis of the results for floorings based on the new inter-defects correlation matrix considering diagnosis methods.
Table 13. Analysis of the results for floorings based on the new inter-defects correlation matrix considering diagnosis methods.
Building Element/
Material
Defects That Can Be Diagnosed by the Same MethodsDiagnosis Methods Used in ACTDiagnosis Methods Used in NSCDiagnosis Methods Used in WFDiagnosis Methods Used in ERIFCDiagnosis Methods Used in VLFDiagnosis Methods for 2 or More Materials
Floorings—adhesive ceramic tiling (ACT); natural stone claddings (NSC); wood floorings (WF); epoxy resin industrial floor coatings (ERIFC); vinyl and linoleum floorings (VLF)A-B4 and A-C10---D-A3, D-A8, D-C1, D-C2, D-G7, D-G8, D-G9D-C1, D-C3, D-D2, D-G1, D-G7, D-J1D-C1, D-G7
A-C1 and A-C2/
A-C2 and A-C1
D-A4, D-A5, D-D2, D-G1D-A4, D-A5, D-A6, D-D1-D-A3, D-A5, D-A6, D-G7, D-G8-D-A4, D-A5, D-A6
A-C3 and A-C2-D-A4, D-A5, D-A6, D-D1D-A5, D-A6, D-C1, D-G7-D-C3D-A5, D-A6
A-C4 and A-C2D-A4, D-A5, D-D2D-A4, D-A5, D-A6D-A5, D-A6, D-C1, D-G1, D-G7--D-A4, D-A5, D-A6
Note: refer to Table 3 and Table 1 for the designation of each defect and diagnosis method, respectively.
Table 14. Analysis of the results for claddings of roofs based on the new inter-defects correlation matrix considering repair techniques.
Table 14. Analysis of the results for claddings of roofs based on the new inter-defects correlation matrix considering repair techniques.
Building Element/
Material
Defects Associated with the Same Repair TechniqueRepair Techniques Considered in ECPRRepair Techniques Considered in FRRepair Techniques Considered for Both
Roof claddings—external claddings of pitched roofs (ECPR); flat roofs (FR)A-A3 and A-B1R-A1R-A1R-A1
A-A3 and A-B2R-A1R-A1R-A1
A-B1 and A-B2/
A-B2 and A-B1
R-A1, R-A2, R-A7R-A1R-A1
A-C1 and A-C2/
A-C2 and A-C1
R-A2, R-A3, R-A4, R-A6, R-A7, R-A8, R-A9, R-A11R-B6-
A-C1 and A-C3/
A-C3 and A-C1
R-A2, R-A3, R-A4, R-A6, R-A7, R-A8, R-A9, R-A11R-B6-
A-C2 and A-C3 /
A-C3 and A-C2
R-A2, R-A3, R-A4, R-A6, R-A7, R-A8, R-A9, R-A11R-B6-
A-D7 and A-D9R-A5, R-C2R-B6-
A-D9 and A-A1R-A5, R-A11, R-B13, R-C2R-B6-
Note: refer to Table 3 and Table 2 for the designation of each defect and repair technique, respectively.
Table 15. Resources involved in the use of repair technique “R-A1 Cleaning” from category “R-A Surface of the cladding” in the scope of roof claddings—an approach based on a cradle-to-gate approach of LCA [38]; resources data from CYPE Ingenieros S.A: [39].
Table 15. Resources involved in the use of repair technique “R-A1 Cleaning” from category “R-A Surface of the cladding” in the scope of roof claddings—an approach based on a cradle-to-gate approach of LCA [38]; resources data from CYPE Ingenieros S.A: [39].
Life-Cycle StageExternal Claddings of Pitched RoofsFlat Roofs
Applicable?ResourceAmountApplicable?ResourceAmount
Raw material extraction and processing, processing of secondary material inputGutters: No--No--
Ceramic roof tiles: YesDepends on the ingredients of the cleaning agentDepends on the formula of the cleaning agent
Transport to the manufacturerGutters: No--No--
Ceramic roof tiles: YesTransportation using a vehicle and the respective energyDepends on the location of the ingredients and the factory
ManufacturingGutters: No--No--
Ceramic roof tiles: YesProcessed raw materials, energy, and auxiliary materials to produce the cleaning agentDepends on the formula of the cleaning agent
Transport to the building siteGutters: YesTransportation of construction workersDepends on the location of the construction siteYesTransportation of construction workers and cleaning equipmentDepends on the location of the construction site
Ceramic roof tiles: YesTransportation of construction workers and the cleaning agentDepends on the location of the construction site
Installation into the buildingGutters: YesLabour of construction workers0.274 h/mYesEnergy for the blower and water jetDepends on the efficiency of the equipment
Ceramic roof tiles: YesCleaning agent for the removal of mould, fungus, and grease stains0.130 L/m2Water10 L/m2
Labour of construction workers0.547 h/m2Labour of construction workers0.547 h/m2
Table 16. Analysis of the results for façade elements/claddings based on the new inter-defects correlation matrix considering repair techniques.
Table 16. Analysis of the results for façade elements/claddings based on the new inter-defects correlation matrix considering repair techniques.
Building Element/
Material
Defects Associated with the Same Repair TechniqueRepair Techniques Considered in DWFRepair Techniques Considered in WRRepair Techniques Considered in ETICSRepair Techniques Considered in PFRepair Techniques Considered in ACSRepair Techniques Considered in ACTRepair Techniques Considered in NSCRepair Techniques Considered for 3 or More Materials
Façade elements and façade claddings—door and window frames (DWF); wall renders (WR); external thermal insulation composite systems (ETICS); painted façades (PF); architectural concrete surfaces (ACS); adhesive ceramic tiling (ACT); natural stone claddings (NSC)A-A2 and A-A3/
A-A3 and A-A2
R-D11R-A1, R-A2, R-B14, R-D16R-A1, R-A2, R-A12-R-A1, R-A2, R-A11, R-D1, R-D16--R-A1, R-A2
A-A6 and A-C1-R-A11, R-A12, R-B14-R-A12R-A11-R-A11, R-A14, R-D9R-A11
A-B1 and A-A2R-D11R-A1, R-A2, R-A11, R-A12, R-D16R-A1, R-A2, R-A12, R-D16-R-A1, R-A2, R-D16--R-A1, R-A2, R-D16
A-B1 and A-A3R-A1, R-A2, R-A12, R-A14, R-D6, R-D11, R-D12R-A1, R-A2, R-A12, R-D16R-A1, R-A2, R-A12R-A1, R-A12R-A1, R-A2, R-D16R-A1, R-D6R-A1, R-A2, R-D8R-A1, R-A2, R-A12,
A-B1 and A-B2/
A-B2 and A-B1
-R-A1, R-A2, R-A11, R-A12, R-D16R-A1, R-A2, R-A12, R-D16--R-A1, R-D2, R-D3, R-D6R-D3, R-D8R-A1
A-B3 and A-A2-R-A1, R-A11, R-A12, R-B14R-A1, R-A12-R-A1, R-A2--R-A1
A-B3 and A-A4-R-A1, R-A11, R-A12R-A1, R-A12R-A1, R-A12, R-A16R-A1, R-A2R-D6R-A11R-A1, R-A12
A-B3 and A-B1-R-A1, R-A11, R-A12R-A1, R-A12R-A1, R-A12R-A1, R-A2R-A1, R-D2, R-D6-R-A1, R-A12
A-C1 and A-C2-R-A11, R-A12, R-A14R-A12, R-A14, R-D2-R-A2, R-A11R-A11, R-A12, R-B8, R-C4, R-D4, R-D7, R-D9R-A11, R-A14, R-D4, R-D9R-A11, R-A12, R-A14
Note: refer to Table 3 and Table 2 for the designation of each defect and repair technique, respectively.
Table 17. Resources involved in the use of repair technique “R-A1 Cleaning” from category “R-A Surface of the cladding” in the scope of façade elements/claddings—an approach based on a cradle-to-gate approach of LCA [38]; resource data from CYPE Ingenieros S.A: [39].
Table 17. Resources involved in the use of repair technique “R-A1 Cleaning” from category “R-A Surface of the cladding” in the scope of façade elements/claddings—an approach based on a cradle-to-gate approach of LCA [38]; resource data from CYPE Ingenieros S.A: [39].
Life-Cycle StageFaçade Claddings
Applicable?ResourceAmount
Raw material extraction and processing, processing of secondary material inputYesSodium hypochlorite0.0025 L/m2
Transport to the manufacturerYesTransportation using a vehicle and the respective energy-
ManufacturingYesBleach0.1 L/m2
Transport to the building siteYesTransportation of construction workers and bleachDepends on the location of the construction site
Installation into the buildingYesWater and bleach solution at 10%0.3 L/m2
Water1 L/m2
Construction worker 10.055 h/m2
Construction worker 20.055 h/m2
Table 18. Resources involved in the use of repair technique “R-A2 Application of a protective coat (…, water-repellent, …)” from category “R-A Surface of the cladding” in the scope of façade elements/claddings—an approach based on a cradle-to-gate approach of LCA [38]; resources data from CYPE Ingenieros S.A: [39].
Table 18. Resources involved in the use of repair technique “R-A2 Application of a protective coat (…, water-repellent, …)” from category “R-A Surface of the cladding” in the scope of façade elements/claddings—an approach based on a cradle-to-gate approach of LCA [38]; resources data from CYPE Ingenieros S.A: [39].
Life-Cycle StageNatural Stone Claddings
Applicable?ResourceAmount
Raw material extraction and processing, processing of secondary material inputYesDepends on the ingredients of the colourless water and oil repellentDepends on the formula of the colourless water and oil repellent
Transport to the manufacturerYesTransportation using a vehicle and the respective energy-
ManufacturingYesColourless water and oil repellentDepends on the formula of the colourless water and oil repellent
Transport to the building siteYesTransportation of construction workers and the colourless water and oil repellentDepends on the location of the construction site
Installation into the buildingYesWater-repellent, colourless, water-based alkyl alkoxysilane impregnation, without solvents, with an average penetration depth of 6.8 mm, repellent to water and dirt, with thixotropic properties, permeable to water vapour, anti-bark and anti-green, with efflorescence prevention effect and resistant to UV rays and alkalis.0.2 L/m2
Painter0.197 h/m2
Table 19. Analysis of the results for floorings based on the new inter-defects correlation matrix considering repair techniques.
Table 19. Analysis of the results for floorings based on the new inter-defects correlation matrix considering repair techniques.
Building Element/
Material
Defects Associated with the Same Repair TechniqueRepair Techniques Considered in ACTRepair Techniques Considered in NSCRepair Techniques Considered in WFRepair Techniques Considered in ERIFCRepair Techniques Considered in VLFRepair Techniques Considered for 2 or More Materials
Floorings—adhesive ceramic tiling (ACT); natural stone claddings (NSC); wood floorings (WF); epoxy resin industrial floor coatings (ERIFC); vinyl and linoleum floorings (VLF)A-A3 and A-A4R-A2, R-A11, R-A12, R-D6R-A1, R-A11, R-D8R-A2, R-A11, R-A12, R-D6, R-D8-R-A1, R-A2, R-A11, R-A12R-A2, R-A11, R-A12, R-D6, R-D8
A-A4 and A-C6/
A-C6 and A-A4
R-A11, R-A12R-A11R-A11, R-A12, R-B9R-A12, R-A13R-A1, R-A2, R-A11, R-A12R-A2, R-A11, R-A12
A-A5 and A-C1R-A11, R-A12R-A11, R-A14, R-D9---R-A11
A-A5 and A-C2R-A11, R-A12R-A11, R-A14, R-D9---R-A11
A-A5 and A-C6/
A-C6 and A-A5
R-A11, R-A12R-A11, R-A14, R-D9---R-A11
A-A6 and A-C6/
A-C6 and A-A6
-R-A11, R-A14, R-D9R-A11, R-A12, R-B9--R-A11
A-C1 and A-C2/
A-C2 and A-C1
R-A11, R-A12, R-B8, R-C4, R-D4, R-D7, R-D9R-A11, R-A14, R-D4, R-D9-R-A11, R-A13, R-A14-R-A11, R-A14, R-D4, R-D9
A-C1 and A-C6/
A-C6 and A-C1
R-A11, R-A12R-A11, R-A14, R-D9-R-A11, R-A13, R-A14-R-A11, R-A14
A-C2 and A-C6/
A-C6 and A-C2
R-A11, R-A12R-A11, R-A14, R-D9R-A11, R-A12, R-B9R-A11, R-A13, R-A14R-A2, R-A11R-A11, R-A12. R-A14
A-C6 and A-A3R-A11, R-A12R-A11R-A11, R-A12-R-A1, R-A2, R-A11, R-A12R-A11, R-A12
A-C6 and A-C4R-A11, R-A12R-A11R-A11, R-A12, R-B9--R-A11, R-A12
A-C9 and A-C4-R-A11, R-D7, R-D8R-A11, R-B7, R-B8--R-A11
A-D7 and A-D6R-D2, R-D7R-D2R-D2-R-A2, R-A11, R-D5R-D2
Note: refer to Table 3 and Table 2 for the designation of each defect and repair technique, respectively.
Table 20. Resources involved in the use of repair technique “R-A11 Replacement or reapplication of the cladding/glazing (partially or completely)” from category “R-A Surface of the cladding” in the scope of floorings—approach based on a cradle-to-gate approach of LCA [38]; resources data from CYPE Ingenieros S.A: [39].
Table 20. Resources involved in the use of repair technique “R-A11 Replacement or reapplication of the cladding/glazing (partially or completely)” from category “R-A Surface of the cladding” in the scope of floorings—approach based on a cradle-to-gate approach of LCA [38]; resources data from CYPE Ingenieros S.A: [39].
Life-Cycle StageAdhesive Ceramic TilingWood Floorings
Applicable?ResourceAmountApplicable?ResourceAmount
Raw material extraction and processing, processing of secondary material inputYesRaw materials for the production of cementitious adhesive, ceramic tiles, and groutingDepends on product formulaYesPinus pinaster woodDepends on log radius
Swedish pine wood
Raw materials for the production of adjustable supports, fastening elements, and wood washDepends on product formula
Transport to the manufacturerYesTransportation using a vehicle and the respective energyDepends on ingredients and factories’ locationYesTransportation using a vehicle and the respective energyDepends on ingredients and factories’ location
ManufacturingYesCementitious adhesiveDepends on product formulaYesClapboard of Pinus pinaster woodDepends on product formula
Ceramic tilesAdjustable support
Solid Swedish pine wood boards
GroutingFastening elements in stainless steel
Quick-drying water-based floor polish
Transport to the building siteYesTransportation of construction workers, cementitious adhesive, ceramic tiles, and groutingDepends on construction site locationYesTransportation of construction workers, clapboards, adjustable supports, wood boards, fastening elements, and floor polishDepends on construction site location
Installation into the buildingYesCementitious adhesive, C1 TE (NP EN 12004), with reduced slip and extended laying time, white, based on high-strength cement, selected aggregates, additives and synthetic resins, for laying all types of ceramic tiles in a thin layer on exterior floors4 kg/m2YesClapboard with a section of 65 × 38 mm, made from Pinus pinaster wood, autoclave-treated, risk class 4, according to NP EN 335, brushed finish, with humidity of less than 20%.2.6 m/m2
Glazed porcelain stoneware mosaic, with 25 × 25 × 5 mm tiles mounted on a mesh, with a 2 mm separation joint between tiles, medium range, water absorption capacity E < 0.5%, group BIa, according to NP EN 14411, with slip resistance greater than 45 according to ENV 126331.05 m2/m2Adjustable support, made of polyolefin, with added mineral filler, in black colour, with 750 kg mechanical compression capacity and flat round base, for heights between 30 and 50 mm; thermal stability from −25 °C to 110 °C; imputrescible, resistant to ageing and weathering7 units/m2
Kit of PVC crosses to guarantee a joint thickness between tiles of 2 mm in ceramic flooring.3.2 units/m2Solid Swedish pine wood boards, 21 × 95 × 1600/2400 mm, untreated, for brushing and application of a protective and decorative treatment on site, with assembly accessories. According to EN 13810-1 and EN 143421.05 m2/m2
Assembly kit for decking, comprising a stainless-steel omega-shaped clip for assembly of the boards and a stainless steel screw for fixing the clip to the slat25 units/m2
Improved cementitious grout, with reduced water absorption and high resistance to abrasion, type CG2 W A, according to EN 13888, white colour, for joints of 2 mm, based on high-strength cement, quartz, special additives, pigments and synthetic resins, for filling joints in all types of ceramic tiles1.34 kg/m2Quick-drying water-based floor polish for interior/exterior use, Pino colour, satin finish, based on hybrid acrylic resins and polyurethane copolymers, with a biocide agent, against blue stain fungi and moulds, weather-resistant, applicable by brush, roller or spray gun to exterior wooden floors (protective and decorative treatment)0.166 L/m2
Sanding machine for wooden floors, equipped with sanding rollers and suction system0.174 h/m2
Construction worker 10.496 h/m2Construction worker 1 (installation of flooring)0.594 h/m2
Construction worker 1 (installation of flooring)0.594 h/m2
Construction worker 20.248 h/m2Painter 10.356 h/m2
Painter 20.059 h/m2
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Pereira, C.; Silva, A. Operationalisation of Building Inspections and Repair: Systematisation-Based Approach. Appl. Sci. 2024, 14, 6947. https://doi.org/10.3390/app14166947

AMA Style

Pereira C, Silva A. Operationalisation of Building Inspections and Repair: Systematisation-Based Approach. Applied Sciences. 2024; 14(16):6947. https://doi.org/10.3390/app14166947

Chicago/Turabian Style

Pereira, Clara, and Ana Silva. 2024. "Operationalisation of Building Inspections and Repair: Systematisation-Based Approach" Applied Sciences 14, no. 16: 6947. https://doi.org/10.3390/app14166947

APA Style

Pereira, C., & Silva, A. (2024). Operationalisation of Building Inspections and Repair: Systematisation-Based Approach. Applied Sciences, 14(16), 6947. https://doi.org/10.3390/app14166947

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop