Optimization on Reasonable Construction State for Cable-Stayed Bridge with Steel Box Girder Based on Multi-Objective Programming Algorithm
Abstract
:1. Introduction
2. Introduction to Optimized Method
2.1. Optimization Principles
2.2. Multi-Objective Programming Model for Cable Force Optimization
2.2.1. Design Variables
2.2.2. Optimization Objectives
2.2.3. Establishment of Optimization Model
2.3. Convert the Multi-Objective Model to an Unconstrained Quadratic Model Through Weighted Sum of Squares Method
2.4. Damped Newton Method for Solving Single-Objective Programming Model
2.4.1. Principles
2.4.2. Solving Steps
- (1)
- Provide the initial iterative values , a permissible error , and make .
- (2)
- Check if the formula is valid. If it is, set the optimal solution , and the iteration can be terminated; otherwise, go to step (3).
- (3)
- Calculate and use as the search direction for the Armjio one-dimensional search. Solve the optimal step size : .
- (4)
- Update , set , and return to step (2). Continue iterating until the error meets the requirements of precision. The iterative process of the damped Newton method is shown in Figure 2.
2.5. Optimization Process for the Reasonable Construction State of Cable-Stayed Bridge with Steel Girder
- (1)
- Establish the finite element model of the cable-stayed bridge with the steel box girder based on the forward-iteration method. Calculate the influence matrices for displacement and bending moment of the girder and pylon, and cable force under unit cable force according to the actual construction process.
- (2)
- Use the cable force under the reasonable completed state as initial iterative cable tension to conduct forward-iteration calculation and make k = 1; then, calculate vectors of bending moment , displacement of girder and pylon, and cable force under current completed state. The difference vector for each control parameters between the reasonable completed state and the current completed state can be determined.
- (3)
- Based on Equation (4), a multi-objective programming model can be established by taking as the optimization objective.
- (4)
- Convert the multi-objective programming model into an unconstrained single-objective programming model using the weighted sum of squares method.
- (5)
- Provide a permissible error . Using MATLAB and the damped Newton method, the adjustment amount for cable tension can be determined.
- (6)
- Use as the updated cable tension and perform the forward-iteration calculation. A new set of control parameters under the current state, along with the updated differences between the current state and the reasonable completed state can then be obtained.
- (7)
- Provide a permissible error and . Verify whether both formulas and are valid. If they are, terminate the iteration. The optimal cable tension during the construction process can be determined. At this stage, the reasonableness of the construction state should be evaluated based on the forward-iteration results. If the calculation results are deemed reasonable, the corresponding reasonable constructing state and reasonable completed state are obtained. If the results are not reasonable, adjust the objective functions or weight coefficients and return to step (3) to rebuild the optimization model and continue the iteration process. This procedure continues until the error meets the specified precision requirements. The implementation process is illustrated in Figure 3.
3. Optimization on Reasonable Constructing State for Cable-Stayed Bridge with Steel Box Girder
3.1. Engineering Profile
3.2. Finite Element Model and Construction Stages
3.3. Calculation of Influence Matrices During Construction Process
3.4. Setting Optimization Parameters
3.5. Analysis of Optimization Results During Construction Process
3.6. Analysis Results Under Dead Loads
4. Conclusions
- (1)
- Based on the structural characteristics of a steel box girder cable-stayed bridge, the problem of determining a reasonable construction state was formulated as a multi-objective programming model. The weighted sum of squares method was employed in the evaluation function, followed by the damped Newton method to solve the unconstrained single-objective model, and finite element analysis based on the forward-iteration method was applied sequentially to solve the problem.
- (2)
- For a steel box girder cable-stayed bridge constructed using the cantilever method, the optimization of the construction state, incorporating objective functions related to cable force and bending moment and combining multi-objective programming with finite element analysis based on the forward-iteration method, yields deformation and internal force distributions of both the girder and pylon that are within reasonable ranges during the construction process. These results exhibit minimal deviation from the completed state obtained from the optimized construction state. The selected objective functions and optimization algorithm effectively account for the deformation and internal forces of each component during cantilever construction, leading to a more reasonable construction state.
- (3)
- In selecting the appropriate objective functions for optimizing the reasonable construction state of a steel box girder cable-stayed bridge, the structural characteristics and construction methods must be considered. Simply selecting cable force as the sole objective function may overlook the deformation and internal forces of individual components. Additionally, excessive or ill-suited objective functions can hinder the convergence of the iteration process.
- (4)
- The multi-objective optimization algorithm demonstrated excellent stability and fast convergence, making it straightforward to obtain the global optimal solution. It is also easily programmable, enabling the structure’s deformation and internal forces to closely approximate the target of a reasonable completed state while ensuring construction safety. This method not only avoids the randomness associated with manual adjustments but also provides a quick and efficient means to achieve reasonable results. The optimization outcomes offer a theoretical foundation for construction control and error adjustment in the construction of steel box girder cable-stayed bridges.
- (5)
- For large-span cable-stayed bridges, the high-order matrices in the mathematical optimization models for final bridge cable forces can encounter singularity issues during computation, leading to local convergence problems. This limitation highlights the need for further optimization of the algorithms to enhance both efficiency and global convergence. Additionally, emerging intelligent optimization algorithms offer significant advantages and could be promising candidates for application in optimizing the final cable forces of cable-stayed bridges. Exploring these algorithms may lead to the development of more suitable methods or ensembles of algorithms specifically tailored for the optimization of cable forces in such structures.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Hassan, M.M.; EI Damatty, A.A.; Nassef, A.O. Database for the optimum design of semi-fan composite cable-stayed bridges based on genetic algorithms. Struct. Infrastruct. Eng. 2015, 11, 1054–1068. [Google Scholar] [CrossRef]
- Schlaich, M. Erection of cable-stayed bridges having composite decks with precast concrete slabs. J. Bridge Eng. 2001, 6, 333–339. [Google Scholar] [CrossRef]
- Zeng, Y.; Wang, Y.; Shi, Z.; Tan, H.; Gu, A. Experimental study on stability of long-span PC cable-stayed bridge during the construction periods. Adv. Civ. Eng. 2022, 2022, 8578684. [Google Scholar] [CrossRef]
- Sung-Wan, K.; Dong-Uk, P.; Jin-Soo, K.; Park, J.-B. Estimating tension of a prestressed concrete cable-stayed bridge under construction and traffic use conditions using a vision-based system. Structures 2023, 47, 299–312. [Google Scholar] [CrossRef]
- Janjic, D.; Pircher, M.; Pircher, H. Optimization of cable tensioning in cable-stayed bridges. J. Bridge Eng. 2003, 8, 131–137. [Google Scholar] [CrossRef]
- Song, C.; Xiao, R.; Sun, B.; Wang, Z.; Zhang, C. Cable force optimization of cable-stayed bridges: A surrogate model-assisted differential evolution method combined with B-Spline interpolation curves. Eng. Struct. 2023, 283, 115856. [Google Scholar] [CrossRef]
- Freire, A.M.S.; Negrao, J.H.O.; Lopes, A.V. Geometrical nonlinearities on the static analysis of highly flexible steel cable-stayed bridges. Comput. Struct. 2006, 84, 2128–2140. [Google Scholar] [CrossRef]
- Wang, L.; Xiao, Z.; Li, M.; Li, M.; Fu, N. Cable force optimization of cable-stayed bridge based on multi-objective particle swarm optimization algorithm with mutation operation and the influence matrix. Appl. Sci. 2023, 13, 2611. [Google Scholar] [CrossRef]
- Dai, J.; Qin, F.; Di, J.; Chen, Y. Review on cable force optimization method for cable-stayed bridge in completed bridge state. China J. Highw. Transp. 2019, 32, 17–37. (In China) [Google Scholar] [CrossRef]
- Wei, S.; Gong, W.; Wu, X.; Zhang, Z. Nonlinear stress-free-state forward analysis method of long-span cable-stayed bridges constructed in stages. Buildings 2023, 13, 1735. [Google Scholar] [CrossRef]
- Lozano-Galant, J.A.; Payá-Zaforteza, I.; Xu, D.; Turmo, J. Forward algorithm for the construction control of cable-stayed bridges built on temporary supports. Eng. Struct. 2012, 40, 119–130. [Google Scholar] [CrossRef]
- Granata, M.F.; Longo, G.; Recupero, A.; Arici, M. Construction sequence analysis of long-span cable-stayed bridges. Eng. Struct. 2018, 174, 267–281. [Google Scholar] [CrossRef]
- Chen, D.W.; Au, F.T.K.; Tham, L.G.; Lee, P.K.K. Determination of initial cable forces in prestressed concrete cable-stayed bridges for given design deck profiles using the force equilibrium method. Comput. Struct. 2000, 74, 1–9. [Google Scholar] [CrossRef]
- Fabbrocino, F.; Modano, M.; Farina, I.; Carpentieri, G.; Fraternali, F. Optimal prestress design of composite cable-stayed bridges. Compos. Struct. 2017, 169, 167–172. [Google Scholar] [CrossRef]
- Martins, A.M.B.; Simões, L.M.C.; Negrão, J.H.J.O. Cable stretching force optimization of concrete cable-stayed bridges including construction stages and time-dependent effects. Struct. Multidiscip. Optim. 2015, 51, 757–772. [Google Scholar] [CrossRef]
- Chen, Z.; Zhang, C.; Zhou, J.; Song, J.; Huang, C. Study of cable force of construction control and alignment control of main girders for long-span railway cable-stayed bridges. Mod. Appl. Sci. 2013, 7, 47. [Google Scholar] [CrossRef]
- Sung, Y.; Chang, D.; Teo, E. Optimum post-tensioning cable forces of Mau-Lo His cable-stayed bridge. Eng. Struct. 2006, 28, 1407–1417. [Google Scholar] [CrossRef]
- Baldomir, A.; Hernandez, S.; Nieto, F.; Jurado, J.A. Cable optimization of a long span cable stayed bridge in La Coruña (Spain). Adv. Eng. Softw. 2010, 41, 931–938. [Google Scholar] [CrossRef]
- Lonetti, P.; Pascuzzo, A. Optimum design analysis of hybrid cable-stayed suspension bridges. Adv. Eng. Softw. 2014, 73, 53–66. [Google Scholar] [CrossRef]
- Guo, J.; Guan, Z. Optimization of the cable forces of completed cable-stayed bridges with differential evolution method. Structures 2023, 47, 1416–1427. [Google Scholar] [CrossRef]
- Tian, Z.; Zhang, Z.; Ning, C.; Peng, T.; Guo, Y.; Cao, Z. Multi-objective optimization of cable force of arch bridge constructed by cable-stayed cantilever cast-in-situ method based on improved NSGA-II. Structures 2024, 59, 105782. [Google Scholar] [CrossRef]
- Guo, J.; Yuan, W.; Dang, X.; Alam, M.S. Cable force optimization of a curved cable-stayed bridge with combined simulated annealing method and cubic B-Spline interpolation curves. Eng. Struct. 2019, 201, 109813. [Google Scholar] [CrossRef]
- Li, J.X.; Qu, C.X.; Yi, T.H.; Li, H.-N.; Han, Q. Condition assessment of stay cables using normalized sequence of vehicle-induced cable force peaks of stay cables on same side. Eng. Struct. 2024, 309, 118123. [Google Scholar] [CrossRef]
- Matos, J.C.; Nicoletti, V.; Kralovanec, J.; Sousa, H.S.; Gara, F.; Moravcik, M.; Morais, M.J. Comparison of condition rating systems for bridges in three European countries. Appl. Sci. 2023, 13, 12343. [Google Scholar] [CrossRef]
- Madrazo-Aguirre, F.; Ruiz-Teran, A.M.; Wadee, M.A. Dynamic behaviour of steel–concrete composite under-deck cable-stayed bridges under the action of moving loads. Eng. Struct. 2015, 103, 260–274. [Google Scholar] [CrossRef]
- Madrazo-Aguirre, F.; Wadee, M.A.; Ruiz-Teran, A.M. Non-linear stability of under-deck cable-stayed bridge decks. Int. J. Non-Linear Mech. 2015, 77, 28–40. [Google Scholar] [CrossRef]
- Wu, K.; Wadee, M.A.; Gardner, L. Stability and ultimate behaviour of prestressed stayed beam-columns. Eng. Struct. 2019, 201, 109723. [Google Scholar] [CrossRef]
Material | Elastic Modulus (MPa) | Poisson’s Ratio | Density (kg/m3) | Linear Expansivity (°C) |
---|---|---|---|---|
Q345D steel | 206,000 | 0.3 | 7700 | 1.2 |
C50 concrete | 35,500 | 0.2 | 2300 | 1.2 |
Steel wires | 195,000 | 0.3 | 8284 | 1.2 |
Serial Number | Construction State | Serial Number | Construction State |
---|---|---|---|
1 | Construct the transition piers, auxiliary piers, and pylons | 58~72 | Install steel box girder Ai and Ji , then tension cables |
2 | Assemble the brackets near pylons | 73 | Deck derrick cranes move forward |
3 | Install steel box girder sections near pylons | 74 | Install steel box girder section AH2, complete the closure operation of side span |
4 | Consolidate girder and pylons | 75 | Construct the permanent weights of the second phase onto steel box girder section located on top of auxiliary piers and side span |
5 | Tension cables A1 and J1 | 76 | Dismantle deck derrick cranes of side span |
6 | Dismantle brackets near pylons | 77 | Install steel box girder section J23 |
7 | Assemble deck derrick cranes | 78 | Tension cables A22 and J22 |
8 | Install steel box girder sections A3 and J3 | 79 | Deck derrick cranes of mid span move forward |
9 | Tensioning cables A2 and J2 | 80 | Install steel box girder section JH, complete the closure operation of mid span |
10 | Deck derrick cranes move forward | 81 | Inspection cars move back to pylons and transition piers |
11~27 | Install steel box girder sections Ai and Ji , then tension cables Aj and Jj | 82 | Install permanent supports between girder and pylons |
28 | Construct temporary piers, deck derrick cranes move forward | 83 | Dismantle temporary consolidation between girder and pylon |
30~52 | Install steel box girder sections Ai and Ji , then tension cables Aj and Jj | 84 | Dismantle deck derrick cranes of mid span |
53 | Install steel box girder section A18 onto temporary supports near auxiliary piers | 85 | Dismantle temporary piers |
54 | Deck derrick cranes move forward | 86 | Dismantle horizontal braces of pylon |
55 | Install steel box girder section AH1, complete the closure operation of secondary side span | 87 | Install wind noses onto steel box girder |
56 | Dismantle temporary supports near auxiliary piers | 88 | Impose secondary dead loads |
57 | Construct the permanent weights of the first phase onto steel box girder section A18, which located on top of auxiliary piers |
Sequence Number | Objective Function |
---|---|
Function I | Cable force |
Function II | Cable force, bending moment, and displacement |
Function III | Cable force and bending moment |
Function IV | Cable force and displacement |
Objective Functions | Girder | Pylon | ||
---|---|---|---|---|
max | min | max | min | |
Function I | 82,212 | −77,877 | 67,746 | −571,413 |
Function II | 80,401 | −77,986 | 67,161 | −570,783 |
Function III | 77,369 | −77,753 | 67,564 | −569,642 |
Function IV | 29,802 | −82,146 | 83,489 | −525,403 |
Objective Functions | Transition Piers | Auxiliary Piers | ||
---|---|---|---|---|
Max | Min | Max | Min | |
Function I | 6385 | 809 | 10,059 | 0 |
Function II | 6385 | 809 | 9783 | 0 |
Function III | 6385 | 809 | 9783 | 0 |
Function IV | 6385 | 809 | 10,031 | 0 |
Objective Functions | Transition Piers | Auxiliary Piers |
---|---|---|
Function I | 4084 | 9931 |
Function II | 4163 | 9783 |
Function III | 4164 | 9782 |
Function IV | 4061 | 10,031 |
Reasonable completed state | 4153 | 9762 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
He, J.; Chai, W.; Hu, W.; Dai, J.; Di, J.; Qin, F. Optimization on Reasonable Construction State for Cable-Stayed Bridge with Steel Box Girder Based on Multi-Objective Programming Algorithm. Appl. Sci. 2025, 15, 91. https://doi.org/10.3390/app15010091
He J, Chai W, Hu W, Dai J, Di J, Qin F. Optimization on Reasonable Construction State for Cable-Stayed Bridge with Steel Box Girder Based on Multi-Objective Programming Algorithm. Applied Sciences. 2025; 15(1):91. https://doi.org/10.3390/app15010091
Chicago/Turabian StyleHe, Junbiao, Wenhao Chai, Weiming Hu, Jie Dai, Jin Di, and Fengjiang Qin. 2025. "Optimization on Reasonable Construction State for Cable-Stayed Bridge with Steel Box Girder Based on Multi-Objective Programming Algorithm" Applied Sciences 15, no. 1: 91. https://doi.org/10.3390/app15010091
APA StyleHe, J., Chai, W., Hu, W., Dai, J., Di, J., & Qin, F. (2025). Optimization on Reasonable Construction State for Cable-Stayed Bridge with Steel Box Girder Based on Multi-Objective Programming Algorithm. Applied Sciences, 15(1), 91. https://doi.org/10.3390/app15010091