Integration of Cost and Work Breakdown Structures in the Management of Construction Projects
Abstract
:1. Introduction
2. Literature Review
2.1. Work Breakdown Structure (WBS)
2.1.1. WBS in the International PM Standards
2.1.2. WBS in the Construction Industry
- The decomposition criteria, grouping activities into construction units assigned to the different contractors, and/or subcontractors involved in the execution of the project.
- The degree of work complexity and level of detail that identifies the sequence and other relations between the activities in a logical flow of execution.
- The criticality of the tasks, being defined in terms of units of work, according to their importance to avoid activity preemption.
- Organizational unit’s fixed responsibility.
- Clear deliverable.
- Exact scope of work.
- Reliable schedule estimation.
- Specific risk resolution.
- Reliable cost estimation.
- Specific organizational guideline.
2.2. CBS
2.2.1. Costs Based on Activities
2.2.2. Coding Systems in the Construction Industry
- Consistency (single classification principle).
- Mutual exclusivity of categories.
- Exhaustiveness.
- Identify the final result (or deliverable) to achieve the objectives.
- Review the scope to ensure consistency between requirements and the WBS elements.
- Define the chapters (first level of decomposition) in a way that facilitates the understanding by dividing them into clearly differentiated blocks.
- Continue to break down each chapter to an appropriate level of detail.
- Break down the chapters to the final level of detail (construction unit), where both the cost and the schedule are reliable, allowing efficient project monitoring and control.
- Review and refine the WBS until main stakeholders agree on the planning and execution.
2.3. Integration of WBS and CBS
2.4. BIM in the Construction Industry
3. Methodology
- CSCAE (Higher Council of the Colleges of Architects of Spain).
- CGATE (Spanish General Council of Technical Architecture).
- CCIP (College of Civil Engineering, Channels and Ports of Spain).
- CITOP (College of Technical Engineers in Public Works of Spain).
- CGCOII (Higher Council of Colleges of Industrial Engineers of Spain).
- COGITI (Spanish General Council of Technical Industrial Engineering).
- AEIPRO (Spanish Project Management and Engineering Association).
- PMA (Project Managers Association of Andalusia).
- PMI (Chapters of Andalusia, Balearic Islands, Barcelona, Madrid and Valencia).
- AECMA (Spanish Association of Construction Management).
- AEGC (Spanish Construction Management Association).
- B&M (Building and Management).
- AEPDP (Spanish Association of Project Management Practitioners).
- CCPM (Construction Certified Project Managers PMP).
- CMAS (Construction Management Association of Spain).
- DIP (Integrated Project Management).
- DP (Building and Infrastructure Project Managers and Professionals).
- IAC (Engineering, Architecture and Construction).
- ISO 21500 (Project Management).
- Search&Drive (Architecture and Engineering Professionals).
- TL (Architecture, Construction and Engineering Technicians).
4. Results
- The age and experience in the construction industry of both groups is quite similar.
- Technician practitioners (CIT sample) mostly work in smaller companies, whereas construction managers (CIM sample), while still work more for small companies, also work in companies with other sizes.
- The project duration and cost size tends to be higher in the projects where construction managers participate.
- The knowledge and training of PM methodologies (e.g., ISO 21500, PMI PMBOK, IPMA ICB, etc.) is almost null in the case of technicians, and fairly high in the case of construction managers.
- PM certification is much more common among construction managers too (probably an expected outcome).
4.1. Hypotheses
4.2. Confirmatory Factor Analysis (CFA)
4.2.1. Principal Components
- (F1) Scope design (which involves the project managers and key stakeholders agreeing on the requirements, defining the scope and deliverables characteristics, specifications and acceptance criteria).
- (F2) Scope development (which involves the project managers and their management team, breaking down the work to be done, avoiding tasks omission, and identifying the project activities).
- (C1) Project success (which includes the constraints performance, the stakeholders’ satisfaction, and the outcomes usability).
- (C2) Organization success (which includes the strategic objectives compliance, market positioning, and the business profit generation).
4.2.2. Validity
- The total variance explained by the principal components, was greater than 50%.
- The model applicability, by the Bartlett’s sphericity test [151], discarded a lack of correlation between items, as it presented a high Chi-square and a significance lower than 5%.
4.3. Structural Equation Model (SEM)
- Define a model explaining a complete set of (significant) relationships.
- Uncover unobserved (indirect) relationships between variables.
- Estimate multiple and interrelated dependence relationships.
- Consider measurement errors in the estimations.
- Test the model where a structure can be imposed and assessed as to fit of the data.
- Reliability:By the Cronbach’s alpha and composite reliability.
- Validity:By the standardized regression weights and squared multiple correlations, as well as the average extracted variance.
- Goodness of fit:By absolute, incremental, and parsimonious fit measures.
4.3.1. Reliability
- Cα > 0.9 as excellent.
- 0.9 > Cα > 0.8 as good.
- 0.8 > Cα > 0.7 as acceptable.
- 0.7 > Cα > 0.6 as questionable.
- 0.6 > Cα > 0.5 as poor.
- 0.5 > Cα as unacceptable.
4.3.2. Validity
4.3.3. Goodness of Fit
- Absolute fit measures (AFMs).
- Incremental fit measures (IFMs).
- Parsimonious fit measures (PFMs).
4.3.4. Indirect Effects
4.3.5. Direct Effects
5. Discussion
6. Conclusions
- The WBS involves structuring the project scope in a hierarchical manner. It is oriented to the deliverables, and avoids both duplication and omission of tasks.
- As the project work is defined more clearly, project roles and responsibilities can be assigned to subcontractors and organizational units more easily. This, in turn, also allows to define more representative project schedules and budgets.
Author Contributions
Funding
Conflicts of Interest
References
- PwC. When Will You Think Differently about Programme Delivery; PwC: London, UK, 2014. [Google Scholar]
- Project Management Institute. The High Cost of Low Performance. How Will You Improve Business Results; Project Management Institute: Newtown Square, PA, USA, 2016. [Google Scholar]
- Fortune, J.; White, D.; Jugdev, K.; Walker, D. Looking again at current practice in project management. Int. J. Manag. Proj. Bus. 2011, 4, 553–572. [Google Scholar] [CrossRef] [Green Version]
- Davis, K. Different stakeholder groups and their perceptions of project success. Int. J. Proj. Manag. 2014, 32, 189–201. [Google Scholar] [CrossRef]
- KPMG International. Climbing the Curve; KPMG International: Amstelveen, The Netherlands, 2015. [Google Scholar]
- Demirkesen, S.; Ozorhon, B. Measuring Project Management Performance: Case of Construction Industry. Eng. Manag. J. 2017, 29, 258–277. [Google Scholar] [CrossRef]
- Heywood, C.; Smith, J. Integrating stakeholders during community FM’s early project phases. Facilities 2006, 24, 300–313. [Google Scholar] [CrossRef]
- International Project Management Association. Individual Competence Baseline for Project, Programme & Portfolio Management, 4th ed.; IPMA: Zurich, Switzerland, 2015; ISBN 978-9492338013. [Google Scholar]
- Project Management Institute. A Guide to the Project Management Body of Knowledge. PMBOK Guide, 6th ed.; PMI: Newtown Square, PA, USA, 2017; ISBN 978-1628253825. [Google Scholar]
- Wang, Y. Applying the PDRI in Project Risk Management; The University of Texas at Austin: Austin, TX, USA, 2002. [Google Scholar]
- Anticona, P. Does BIM offer a better approach to guarantee a reliable, accurate, and precise Cost Estimate? PM World J. 2019, VIII, 1–28. [Google Scholar]
- Camilleri, E. Project Success: Critical Factors and Behaviours, 1st ed.; Gower Publishing: Burlington, VT, USA, 2011; ISBN 978-0566092282. [Google Scholar]
- García-Fornieles, J.M.; Fan, I.S.; Perez, A.; Wainwright, C.; Sehdev, K. A Work Breakdown Structure that Integrates Different Views in Aircraft Modification Projects. Concurr. Eng. 2003, 11, 47–54. [Google Scholar] [CrossRef] [Green Version]
- Kim, S.; Park, C.; Lee, S.; Son, J. Integrated cost and schedule control in the Korean construction industry based on a modified work-packaging model. Can. J. Civ. Eng. 2008, 35, 225–235. [Google Scholar] [CrossRef]
- Cerezo-Narváez, A.; Otero-Mateo, M.; Pastor-Fernández, A. Influence of scope management in construction industry projects. DYNA Manag. 2016, 4, 1–15. [Google Scholar]
- Ibrahim, Y.M.; Kaka, A.P.; Trucco, E.; Kagioglou, M.; Ghassan, A. Semi-automatic development of the work breakdown structure (WBS) for construction projects. In Proceedings of the 4th International Salford Centre for Research and Innovation (SCRI) Research Symposium, Salford, UK, 26–27 March 2007; Salford Centre for Research and Innovation (SCRI): Salford, UK, 2007; pp. 133–145. [Google Scholar]
- Ballesteros-Pérez, P.; Cerezo-Narváez, A.; Otero-Mateo, M.; Pastor-Fernández, A.; Zhang, J.; Vanhoucke, M. Forecasting the Project Duration Average and Standard Deviation from Deterministic Schedule Information. Appl. Sci. 2020, 10, 654. [Google Scholar] [CrossRef] [Green Version]
- Fageha, M.K.; Aibinu, A.A. Prioritising Project Scope Definition Elements in Public Building Projects. Australas. J. Constr. Econ. Build. 2014, 14, 18–33. [Google Scholar] [CrossRef] [Green Version]
- Chritamara, S.; Ogunlana, S.O.; Bach, N.L. Investigating the effect of initial scope establishment on the performance of a project through system dynamics modelling. Eng. Constr. Archit. Manag. 2001, 8, 381–392. [Google Scholar] [CrossRef]
- Gómez-Senent Martínez, E. El Proyecto. Diseño en Ingeniería; Servicio de Publicaciones de la Universidad Politécnica de Valencia UPV: Valencia, Spain, 1997; ISBN 978-8477214540. [Google Scholar]
- Wang, Y.-R.; Gibson, G.E., Jr. A study of preproject planning and project success using ANN and regression models. In Proceedings of the 25th International Symposium on Automation and Robotics in Construction, Vilnius, Lithuania, 26–29 June 2008; Vilnius Gediminas Technical University: Vilnius, Lithuania, 2008; pp. 688–696. [Google Scholar]
- Thaweejinda, J.; Methakullawat, N. Guideline for Clearly Definition Scope; Chulalongkorn University: Bangkok, Thailand, 2012. [Google Scholar]
- Kraus, W. Analysis and Cost Estimating. Cost Eng. J. 2008, 50, 3–4. [Google Scholar]
- Seidel Calazans, A.T.; Dias Kosloski, R.A. O gerenciamento da alteração de escopo na contratação externa de serviços de desenvolvimento/manutenção de software. In Proceedings of the 13th Argentine Symposium on Software Engineering (ASSE), La Plata, Argentina, 27–31 August 2012; Sociedad Argentina de Informática: La Plata, Argentina, 2012; pp. 75–90. [Google Scholar]
- Khan, A. Project Scope Management. Cost Eng. J. 2006, 48, 12–16. [Google Scholar]
- Stal-Le Cardinal, J.; Marle, F. Project: The just necessary structure to reach your goals. Int. J. Proj. Manag. 2006, 24, 226–233. [Google Scholar] [CrossRef]
- Sikdar, S.; Das, O. Goal based project scope determination approach. In Proceedings of the IEEE International Conference of Science and Technology for Humanity (TIC-STH), Toronto, ON, Canada, 26–27 September 2009; IEEE: Toronto, ON, Canada, 2009; pp. 415–420. [Google Scholar]
- Chrissis, M.B.; Konrad, M.; Shrum, S. CMMI for Development: A Guide to Process Integration and Product Improvement, 1st ed.; Editorial Centro De Estudios Ramón Areces: Madrid, Spain, 2012; ISBN 978-8499610788. [Google Scholar]
- Chua, D.K.; Godinot, M. Use of a WBS Matrix to Improve Interface Management in Projects. J. Constr. Eng. Manag. 2006, 132, 67–79. [Google Scholar] [CrossRef]
- Project Management Institute. Practice Standard for Work Breakdown Structures, 3rd ed.; Project Management Institute: Newtown Square, PA, USA, 2019; ISBN 978-1628256192. [Google Scholar]
- International Organization for Standardization. ISO 21500:2012. Guidance on Project Management; International Organization for Standardization: Geneva, Switzerland, 2012. [Google Scholar]
- López Paredes, A.; Pajares Gutierrez, J.; Iglesias Sanzo, M. Certificación IPMA-4LC. Manual de Preparación; Business Project Management Solutions & Technologies: Valladolid, Spain, 2013; ISBN 978-8461640324. [Google Scholar]
- Kerzner, H. Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 11th ed.; John Wiley & Sons: Hoboken, NJ, USA, 2013; ISBN 978-1118022276. [Google Scholar]
- Buchtik, L. Secrets to Mastering the WBS in Real World Projects, 2nd ed.; Project Management Institute: Newtown Square, PA, USA, 2013; ISBN 978-1628250336. [Google Scholar]
- Hendrickson, C.; Au, T. Project Management for Construction: Fundamental Concepts for Owners, Engineers, Architects, and Builders, 1st ed.; Prentice Hall: Upper Saddle River, NJ, USA, 1989; ISBN 978-0137312665. [Google Scholar]
- Engineering Advancement Association of Japan. A Guidebook of Project & Program Management for Enterprise Innovation, 3rd ed.; Project Management Association of Japan: Tokyo, Japan, 2017; ISBN 978-4908520204. [Google Scholar]
- AXELOS. Managing Successful Projects with PRINCE2; AXELOS: London, UK, 2017; ISBN 978-0113315338. [Google Scholar]
- The American Institute of Architects. Integrated Project Delivery: A Guide; The American Institute of Architects: Washington, DC, USA, 2007. [Google Scholar]
- Saidi, K.S.; Lytle, A.M.; Stone, W.C. Report of the NIST Workshop on Data Exchange Standards at the Construction Job Site. In Proceedings of the 20th International Symposium on Automation and Robotics in Construction (ISARC), Eindhoven, The Netherlands, 21–24 September 2003; International Association for Automation and Robotics in Construction (IAARC): Eindhoven, The Netherlands, 2003; pp. 617–622. [Google Scholar]
- Zhang, X.; Bakis, N.; Lukins, T.C.; Ibrahim, Y.M.; Wu, S.; Kagioglou, M.; Aouad, G.; Kaka, A.P.; Trucco, E. Automating progress measurement of construction projects. Autom. Constr. 2009, 18, 294–301. [Google Scholar] [CrossRef]
- Jawad, R.S.M.; Abdulkader, M.R.; Abang Ali, A.A. Variation Orders in Construction Projects. J. Eng. Appl. Sci. 2009, 4, 170–176. [Google Scholar]
- Ballesteros-Pérez, P.; Skitmore, M.; Pellicer, E.; Gutiérrez-Bahamondes, J.H. Improving the estimation of probability of bidder participation in procurement auctions. Int. J. Proj. Manag. 2016, 34, 158–172. [Google Scholar] [CrossRef] [Green Version]
- González Fernández de Valderrama, F. Mediciones y Presupuestos, 2nd ed.; Reverte: Barcelona, Spain, 2010; ISBN 978-8429132014. [Google Scholar]
- Lock, D. Project Management in Construction, 1st ed.; Routledge: Burlington, VT, USA, 2004; ISBN 978-1315602417. [Google Scholar]
- Makarfi Ibrahim, Y.; Kaka, A.; Aouad, G.; Kagioglou, M. Framework for a generic work breakdown structure for building projects. Constr. Innov. 2009, 9, 388–405. [Google Scholar] [CrossRef]
- Nouban, F.; Sadeghi, K.; Abazid, M. An overall guidance and proposition of a WBS template for construction planning of the template (jacket) platforms. Acad. Res. Int. 2017, 8, 37–56. [Google Scholar]
- Cha, H.S.; Lee, D.G. A case study of time/cost analysis for aged-housing renovation using a pre-made BIM database structure. KSCE J. Civ. Eng. 2015, 19, 841–852. [Google Scholar] [CrossRef]
- Jung, Y.; Woo, S. Flexible Work Breakdown Structure for Integrated Cost and Schedule Control. J. Constr. Eng. Manag. 2004, 130, 616–625. [Google Scholar] [CrossRef]
- Raz, T.; Globerson, S. Effective Sizing and Content Definition of Work Packages. Proj. Manag. J. 1998, 29, 17–23. [Google Scholar] [CrossRef]
- Taylor, M.D. How to Develop Work Breakdown Structures; Systems Management Services: Montreal, QC, Canada, 2009. [Google Scholar]
- Heerkens, G.R. Gestión de Proyectos; McGraw-Hill Interamericana: Madrid, Spain, 2002; ISBN 978-9701047729. [Google Scholar]
- Globerson, S.; Vardi, S.; Cohen, I. Identifying the Criteria Used for Establishing Work Package Size for Project WBS. J. Mod. Proj. Manag. 2016, 4, 64–69. [Google Scholar]
- Pavan, A.; Daniotti, B.; Re Cecconi, F.; Maltese, S.; Spagnolo, S.L.; Caffi, V.; Chiozzi, M.; Pasini, D. INNOVance: Italian BIM Database for Construction Process Management. In Computing in Civil and Building Engineering; American Society of Civil Engineers ASCE: Reston, VA, USA, 2014; pp. 641–648. [Google Scholar]
- Chang, A.S.-T.; Tsai, Y.-W. Engineering Information Classification System. J. Constr. Eng. Manag. 2003, 129, 454–460. [Google Scholar] [CrossRef]
- Rianty, M.; Latief, Y.; Riantini, L.S. Development of risk-based standardized WBS (Work Breakdown Structure) for quality planning of high rise building architectural works. MATEC Web Conf. 2018, 159, 01019. [Google Scholar] [CrossRef]
- Ramadhan, A.; Latief, Y.; Sagita, L. Development of risk-based standardized work breakdown structure for quality planning of airport construction project. J. Phys. Conf. Ser. 2019, 1360, 012005. [Google Scholar] [CrossRef]
- Lister, G. Mastering Project, Program, and Portfolio Management. Models for Structuring and Executing the Project Hierarchy; Pearson Education Limited: Upper Saddle River, NJ, USA, 2015; ISBN 978-0133839746. [Google Scholar]
- Jaber, H.; Marle, F.; Vidal, L.-A.; Didiez, L. Criticality and propagation analysis of impacts between project deliverables. Res. Eng. Des. 2018, 29, 87–106. [Google Scholar] [CrossRef]
- Büchmann-Slorup, R. Criticality in Location-Based Management of Construction; Technical University of Denmark: Lyngby, Denmark, 2012. [Google Scholar]
- Choi, O.-Y.; Kim, T.-H.; Kim, G.-H. A Study on Selection of Roof Waterproofing Method by analyzing Life Cycle Costing. J. Korean Inst. Build. Constr. 2008, 8, 127–134. [Google Scholar] [CrossRef]
- El-Haram, M.A.; Marenjak, S.; Horner, M.W. Development of a generic framework for collecting whole life cost data for the building industry. J. Qual. Maint. Eng. 2002, 8, 144–151. [Google Scholar] [CrossRef]
- Le, Y.; Ren, J.; Ning, Y.; He, Q.; Li, Y. Life Cycle Cost Integrative Management in Construction Engineering. In Proceedings of the First International Conference on Information Science and Engineering, Nanjing, China, 26–28 December 2009; IEEE: Nanjing, China, 2009; pp. 4367–4370. [Google Scholar]
- Schade, J. Life Cycle Cost Calculation Models for Buildings. In Proceedings of the 4th Nordic Conference on Construction Economics and Organisation: Development Processes in Construction Mangement, Luleå, Sweden, 14–15 June 2007; Swedish National Research and Development Programme for Construction: Luleå, Sweden, 2007; pp. 321–329. [Google Scholar]
- Bahaudin, A.Y.; Elias, E.M.; Dahalan, H.; Jamaluddin, R. Construction Cost Control: A Review of Practices in Malaysia. In Proceedings of the The 3rd International Conference on Technology and Operation Management (ICTOM), Bandung, Indonesia, 4–6 July 2012; Institute of Technology Bandung (ITB): Bandung, Indonesia, 2012; pp. 1–11. [Google Scholar]
- Lesniak, A.; Plebankiewicz, E.; Zima, K. Cost Calculation of Building Structures and Building Works in Polish Conditions. Eng. Manag. Res. 2012, 1, 72–81. [Google Scholar] [CrossRef] [Green Version]
- Koushki, P.A.; Al-Rashid, K.; Kartam, N. Delays and cost increases in the construction of private residential projects in Kuwait. Constr. Manag. Econ. 2005, 23, 285–294. [Google Scholar] [CrossRef]
- Derakhshanalavijeh, R.; Cardoso Teixeira, J.M. Cost overrun in construction projects in developing countries, gas-oil industry of Iran as a case study. J. Civ. Eng. Manag. 2016, 23, 125–136. [Google Scholar] [CrossRef] [Green Version]
- Lind, H.; Brunes, F. Explaining cost overruns in infrastructure projects: A new framework with applications to Sweden. Constr. Manag. Econ. 2015, 33, 554–568. [Google Scholar] [CrossRef]
- Cantarelli, C.C.; Molin, E.J.E.; Van Wee, B.; Flyvbjerg, B. Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases. Transp. Policy 2012, 22, 49–56. [Google Scholar] [CrossRef] [Green Version]
- Cantarelli, C.C.; Flyvbjerg, B.; Molin, E.J.E.; van Wee, B. Cost overruns in large-scale transportation infrastructure projects: Explanations and their theoretical embeddedness. Eur. J. Transp. Infrastruct. Res. 2010, 10, 5–18. [Google Scholar]
- Harrison, F.; Lock, D. Advanced Project Management; Gower Publishing: Burlington, VT, USA, 2017; ISBN 978-1315263328. [Google Scholar]
- Staub–French, S.; Fischer, M.; Kunz, J.; Ishii, K.; Paulson, B. A feature ontology to support construction cost estimating. Artif. Intell. Eng. Des. Anal. Manuf. 2003, 17, 133–154. [Google Scholar] [CrossRef] [Green Version]
- Lee, S.K.; Kim, K.R.; Yu, J.H. BIM and ontology-based approach for building cost estimation. Autom. Constr. 2014, 41, 96–105. [Google Scholar] [CrossRef]
- Ma, Z.; Wei, Z.; Zhang, X. Semi-automatic and specification-compliant cost estimation for tendering of building projects based on IFC data of design model. Autom. Constr. 2013, 30, 126–135. [Google Scholar] [CrossRef]
- Cooper, R.; Kaplan, R.S. Measure Costs Right: Make the Right Decision. Harv. Bus. Rev. 1988, 66, 96–103. [Google Scholar]
- Everaert, P.; Bruggeman, W.; Sarens, G.; Anderson, S.R.; Levant, Y. Cost modeling in logistics using time-driven ABC. Int. J. Phys. Distrib. Logist. Manag. 2008, 38, 172–191. [Google Scholar] [CrossRef]
- Kaplan, R.S.; Anderson, S.R. Time-Driven Activity- Based Costing. Harv. Bus. Rev. 2004, 82, 131–138. [Google Scholar] [CrossRef] [PubMed]
- International Federation of Consulting Engineers Which FIDIC Contract Should I Use? Available online: http://fidic.org/bookshop/about-bookshop/which-fidic-contract-should-i-use (accessed on 30 December 2019).
- Marsh, P. Contracting for Engineering and Construction Projects, 5th ed.; Routledge: New York, NY, USA, 2016; ISBN 978-0566082825. [Google Scholar]
- Hughes, W.; Champion, R.; Murdoch, J. Construction Contracts. Law and Management, 5th ed.; Routledge: London, UK, 2015; ISBN 978-1315695211. [Google Scholar]
- Ballesteros-Pérez, P.; González-Cruz, M.C.; Cañavate-Grimal, A. Mathematical relationships between scoring parameters in capped tendering. Int. J. Proj. Manag. 2012, 30, 850–862. [Google Scholar] [CrossRef]
- Ballesteros-Pérez, P.; del Campo-Hitschfeld, M.L.; Mora-Melià, D.; Domínguez, D. Modeling bidding competitiveness and position performance in multi-attribute construction auctions. Oper. Res. Perspect. 2015, 2, 24–35. [Google Scholar] [CrossRef] [Green Version]
- Ballesteros-Pérez, P.; González-Cruz, M.C.; Fernández-Diego, M.; Pellicer, E. Estimating future bidding performance of competitor bidders in capped tenders. J. Civ. Eng. Manag. 2014, 20, 702–713. [Google Scholar] [CrossRef] [Green Version]
- Council for Development and Housing of the Regional Government of Andalusia; University of Seville; School of Building Engineering of Seville; Official Association of Quantity Surveyors and Technical Architects of Seville Andalusian Construction Cost Base (BCCA). Available online: https://www.juntadeandalucia.es/organismos/fomentoinfraestructurasyordenaciondelterritorio/areas/vivienda-rehabilitacion/planes-instrumentos/paginas/vivienda-bcca.html (accessed on 30 December 2019).
- Construction Technology Institute of Catalonia (ITEC) BEDEC DataBase. Available online: https://metabase.itec.cat/vide/es/bedec (accessed on 30 December 2019).
- Council of Development Housing Territorial Planning and Tourism of the Regional Government of Extremadura Construction Pricing Base of the Regional Government of Extremadura. Available online: http://basepreciosconstruccion.gobex.es/ (accessed on 30 December 2019).
- Directorate General of Housing and Rehabilitation of the Community of Madrid Construction Database of the Community of Madrid. Available online: http://www.madrid.org/bdccm/index.html (accessed on 30 December 2019).
- CYPE Arquimedes. Available online: http://arquimedes.cype.es/ (accessed on 30 December 2019).
- PREOC Premeti. Available online: http://www.preoc.es/#!129000001 (accessed on 30 December 2019).
- PROSOFT Menfis. Available online: https://prosoft.es/productos/menfis (accessed on 30 December 2019).
- Magalhães, P.M.; Sousa, H. Information consistency on construction—Case study of correlation between classification systems for construction types. In Proceedings of the 10th European Conference on Product and Process Modelling (ECPPM), Vienna, Austria, 17–19 September 2014; European Association of Product and Process Modelling (EAPPM): Vienna, Austria; pp. 309–315. [Google Scholar]
- International Organization for Standardization. ISO TR 14177:1994. Classification of Information in the Construction Industry, 1st ed.; International Organization for Standardization: Geneva, Switzerland, 1994. [Google Scholar]
- Kang, L.S.; Paulson, B.C. Adaptability of information classification systems for civil works. J. Constr. Eng. Manag. 1997, 123, 410–426. [Google Scholar] [CrossRef]
- The European Council for Construction Economists. Code of Measurement for Cost Planning; CEEC: Paris, France, 2014. [Google Scholar]
- Deutsches Institut für Normung. DIN 276-1. Building Costs. Part 1: Building Construction; DIN: Berlin, Germany, 2008. [Google Scholar]
- Swedish Building Centre. BSAB 96. Systems and Applications, 1st ed.; Swedish Building Centre: Stockholm, Sweden, 2005; ISBN 978-9173339032. [Google Scholar]
- National Building Specification (NBS) UniClass 2015. Available online: https://www.thenbs.com/our-tools/uniclass-2015 (accessed on 30 December 2019).
- Construction 2000 Classification Committee. TALO 2000. Construction Classification; Building Information Foundation: Helsinki, Finland, 2000; ISBN 978-9516829480. [Google Scholar]
- Centre for Productivity in Construction (Cuneco). Development plan for the Danish Building Classification System (DBK) 2010–2012, 3rd ed.; Centre for Productivity in Construction (Cuneco): Copenhague, Denmark, 2010. [Google Scholar]
- International Construction Measurement Standards Coalition. ICMS: Global Consistency in Presenting Construction and Other Life Cycle Costs; International Construction Measurement Standards Coalition: London, UK, 2019; ISBN 978-1783213757. [Google Scholar]
- Stoy, C.; Wright, M. The CEEC Code for Cost Planning: Introduction and Practical Application. J. Cost Anal. Manag. 2007, 9, 37–54. [Google Scholar] [CrossRef]
- Construction Specifications Institute. Construction Specifications Practice Guide, 1st ed.; John Wiley & Sons: Hoboken, NJ, USA, 2011; ISBN 978-0470635209. [Google Scholar]
- Construction Specifications Institute. Masterformat 2018. Master List of Members and Titles for the Construction Industry, 2018th ed.; Construction Specifications Institute: Alexandria, VA, USA, 2018. [Google Scholar]
- Construction Specifications Institute. Uniformat. A Uniform Classification of Constructions Systems and Assemblies; Construction Specifications Institute: Alexandria, VA, USA, 2010; ISBN 978-0984535712. [Google Scholar]
- Construction Specifications Institute. OmniClass. A Strategy for Classifying the Built Environment; Construction Specifications Institute: Alexandria, VA, USA, 2019. [Google Scholar]
- International Organization for Standardization. ISO 12006-2: 2015. Building Construction. Organization of Information about Construction Works. Part 2: Framework for Classification of Information, 2nd ed.; International Organization for Standardization: Geneva, Switzerland, 2015. [Google Scholar]
- International Organization for Standardization. ISO 81346-12:2018. Industrial Systems, Installations and Equipment and Industrial Products. Structuring Principles and Reference Designations. Part 12: Construction Works and Building Services, 1st ed.; International Organization for Standardization: Geneva, Switzerland, 2018. [Google Scholar]
- Swedish Building Centre. Industry Practices for Application of CoClass in Software; Swedish Building Centre: Stockholm, Sweden, 2018. [Google Scholar]
- Centre for Productivity in Construction (Cuneco) Cuneco Classification System (CCS). Available online: https://ccs.molio.dk/ (accessed on 30 December 2019).
- International Organization for Standardization. ISO 12006-3: 2007. Building Construction. Organization of Information about Construction Works. Part 3: Framework for Object-Oriented Information, 1st ed.; International Organization for Standardization: Geneva, Switzerland, 2007. [Google Scholar]
- Liu, H.; Lu, M.; Al-Hussein, M. BIM-Based Integrated Framework for Detailed Cost Estimation and Schedule Planning of Construction Projects. In Proceedings of the 31st International Symposium on Automation and Robotics in Construction and Mining (ISARC), Sydney, Australia, 9–11 July 2014; International Association for Automation and Robotics in Construction (IAARC): Sydney, Australia, 2014; pp. 286–294. [Google Scholar]
- Park, I.J.; Jin, R.Z.; Yang, H.J.; Hyun, C.T. A support tool for cost and schedule integration by connecting PMIS & PgMIS. In Proceedings of the 2011 2nd International Conference on Engineering and Industries (ICEI), Jeju, Korea, 29 November–1 December 2011; IEEE: Jeju, Korea, 2011; pp. 142–146. [Google Scholar]
- Fan, S.-L.; Chong, H.-Y.; Hung, T.-W.; Wang, Y.-C. Cost-based scheduling method using object-oriented approach. Autom. Constr. 2016, 65, 65–77. [Google Scholar] [CrossRef] [Green Version]
- Lee, J.-H.; Lee, S.-W.; Kim, T.-Y. A Development of Unified and Consistent BIM Database for Integrated Use of BIM-based Quantities, Process, and Construction Costs in Civil Engineering. J. Korea Soc. Comput. Inf. 2019, 24, 127–137. [Google Scholar]
- Young-Bae, C.; Hyun-Soo, L. An Aplication Model to Ensure Practical Usage in Construction Management. Proc. Korean Inst. Constr. Eng. Manag. 2002, 11, 401–404. [Google Scholar]
- Yang, H.J.; Jin, R.Z.; Park, I.J.; Hyun, C.T. Development of a Support Tool for Cost and Schedule Integration Managment at Program Level. Int. J. Civ. Environ. Eng. 2012, 62, 790–797. [Google Scholar]
- Park, H.-T.; Lee, B.-H. EVMS Database System Implementation for interworking of WBS & CBS based management in Construction Works. J. Korea Acad. Coop. Soc. 2011, 12, 2851–2858. [Google Scholar]
- Teicholz, P.M. Current Needs for Cost Control Systems. In Project Controls: Needs and Solutions; Ibbs, C.W., Ashley, D.B., Eds.; American Society of Civil Engineers: Chicago, IL, USA, 1987; pp. 47–57. [Google Scholar]
- Rasdorf, W.J.; Abudayyeh, O.Y. Cost and Schedule Control Integration: Issues and Needs. J. Constr. Eng. Manag. 1991, 117, 486–502. [Google Scholar] [CrossRef] [Green Version]
- Cho, K.; Hong, T.; Hyun, C. Integrated schedule and cost model for repetitive construction process. J. Manag. Eng. 2010, 26, 78–88. [Google Scholar] [CrossRef]
- Villena Manzanares, F.; García Segura, T.; Ballesteros-Pérez, P.; Pellicer Armiñana, E. Influence of BIM in Construction Companies Innovation. In Proceedings of the 23rd International Congress on Project Management and Engineering, Malaga, Spain, 10–12 July 2019; AEIPRO (IPMA Spain): Malaga, Spain, 2019; pp. 524–533. [Google Scholar]
- Cavka, H.B.; Staub-French, S.; Pottinger, R. Evaluating the alignment of organizational and project contexts for BIM adoption: A case study of a large owner organization. Buildings 2015, 5, 1265–1300. [Google Scholar] [CrossRef]
- Terreno, S.; Asadi, S.; Anumba, C. An Exploration of Synergies between Lean Concepts and BIM in FM: A Review and Directions for Future Research. Buildings 2019, 9, 147. [Google Scholar] [CrossRef] [Green Version]
- Bensalah, M.; Elouadi, A.; Mharzi, H. Overview: The opportunity of BIM in railway. Smart Sustain. Built Environ. 2019, 8, 103–116. [Google Scholar] [CrossRef]
- Nam, J.-Y.; Jo, C.-W.; Park, S.-H. A Study on Applying Information Framework for BIM Based WBS -Focusing on Civil Construction-. J. Korea Acad. Coop. Soc. 2017, 18, 770–777. [Google Scholar]
- Subramani, T.; Sivakumar, P. Analysis Cost Overruns, Delays and Risk Involved in Construction Management Using Primavera. Int. J. Eng. Technol. 2018, 7, 160. [Google Scholar] [CrossRef] [Green Version]
- Aziz, A.; Kumar, S. Financial and work management analysis for residential construction: A case study. Int. J. Recent Technol. Eng. 2019, 7, 893–897. [Google Scholar]
- Sun, C.; Man, Q.; Wang, Y. Study on BIM-based construction project cost and schedule risk early warning. J. Intell. Fuzzy Syst. 2015, 29, 469–477. [Google Scholar] [CrossRef]
- Sattineni, A.; Bradford, R.H. Estimating with BIM: A Survey of US Construction Companies. In Proceedings of the 28th International Symposium on Automation and Robotics in Construction (ISARC), Seoul, Korea, 29 June–2 July 2011; International Association for Automation and Robotics in Construction (IAARC): Seoul, Korea, 2011; pp. 564–569. [Google Scholar]
- Ding, L.Y.; Zhou, Y.; Luo, H.B.; Wu, X.G. Using nD technology to develop an integrated construction management system for city rail transit construction. Autom. Constr. 2012, 21, 64–73. [Google Scholar] [CrossRef]
- Park, J.; Cai, H. WBS-based dynamic multi-dimensional BIM database for total construction as-built documentation. Autom. Constr. 2017, 77, 15–23. [Google Scholar] [CrossRef]
- Taner, M.T. Critical Success Factors for Six Sigma Implementation in Large-scale Turkish Construction Companies. Int. Rev. Manag. Mark. 2013, 3, 212–225. [Google Scholar]
- Pinto, J.K.; Prescott, J.E. Planning and Tactical Factors in the Project Implementation Process. J. Manag. Stud. 1990, 27, 305–327. [Google Scholar] [CrossRef]
- Shenhar, A.J.; Dvir, D.; Levy, O.; Maltz, A.C. Project success: A multidimensional strategic concept. Long Range Plan. 2001, 34, 699–725. [Google Scholar] [CrossRef]
- Kulatunga, U.; Amaratunga, D.; Haigh, R. Implementation of critical success factors in construction research and development process. Int. J. Eng. Sci. Technol. 2010, 2, 96–106. [Google Scholar] [CrossRef] [Green Version]
- Liberzon, V.; Shavyrina, V. Methods and Tools of Success Driven Project Management. Proj. Perspect. 2013, XXXV, 32–37. [Google Scholar]
- Fageha, M.K.; Aibinu, A.A. Managing Project Scope Definition to Improve Stakeholders’ Participation and Enhance Project Outcome. Procedia-Soc. Behav. Sci. 2013, 74, 154–164. [Google Scholar] [CrossRef] [Green Version]
- Baccarini, D. The Logical Framework Method for Defining Project Success. Proj. Manag. J. 1999, 30, 25–32. [Google Scholar] [CrossRef]
- Tasevska, F.; Damij, T.; Damij, N. Project planning practices based on enterprise resource planning systems in small and medium enterprises—A case study from the Republic of Macedonia. Int. J. Proj. Manag. 2014, 32, 529–539. [Google Scholar] [CrossRef]
- Kumar, D. Developing strategies and philosophies early for successful project implementation. Int. J. Proj. Manag. 1989, 7, 164–171. [Google Scholar] [CrossRef]
- Dvir, D.; Lipovetsky, S.; Shenhar, A.J.; Tishler, A. In search of project classification: A non-universal approach to project success factors. Res. Policy 1998, 27, 915–935. [Google Scholar] [CrossRef]
- Smith, S.D.; Beausang, P.; Moriarty, D.; Campbell, J.M. Subjectivity in data extraction: A study based on construction hazard identification. In Proceedings of the 24th Annual Conference of the Association of Researchers in Construction Management, (ARCOM), Cardiff, UK, 1–3 September 2008; Association of Researchers in Construction Management (ARCOM): Cardiff, UK, 2008; Volume 2, pp. 1065–1073. [Google Scholar]
- Vahed, A.M.; Gambatese, J.A.; Hendricks, M.T. Perceptions of the Influence of Personal Demographic Factors on the Safety Performance of Field Employees. In Construction Research Congress 2016; American Society of Civil Engineers: Reston, VA, USA, 2016; pp. 2936–2945. [Google Scholar]
- Pheng, L.S.; Chuan, Q.T. Environmental factors and work performance of project managers in the construction industry. Int. J. Proj. Manag. 2006, 24, 24–37. [Google Scholar] [CrossRef]
- Méxas, M.P.; Quelhas, O.L.G.; Costa, H.G. Prioritization of enterprise resource planning systems criteria: Focusing on construction industry. Int. J. Prod. Econ. 2012, 139, 340–350. [Google Scholar] [CrossRef]
- Ruthankoon, R.; Olu Ogunlana, S. Testing Herzberg’s two-factor theory in the Thai construction industry. Eng. Constr. Archit. Manag. 2003, 10, 333–341. [Google Scholar] [CrossRef]
- Jiang, Z.; Henneberg, S.C.; Naudé, P. Supplier relationship management in the construction industry: The effects of trust and dependence. J. Bus. Ind. Mark. 2011, 27, 3–15. [Google Scholar] [CrossRef]
- Kline, R.B. Principles and Practice of Structural Equation Modeling, 3rd ed.; The Guilford Press: New York, NY, USA, 2011; ISBN 978-1606238776. [Google Scholar]
- Kaiser, H.F. A second generation little jiffy. Psychometrika 1970, 35, 401–415. [Google Scholar] [CrossRef]
- Kaiser, M.O. Kaiser-Meyer-Olkin measure for identity correlation matrix. J. R. Stat. Soc. 1974, 52, 296–298. [Google Scholar]
- Bartlett, M.S. The Effect of Standardization on a chi square Approximation in Factor Analysis. Biometrika 1951, 38, 337–344. [Google Scholar]
- Cho, K.M.; Hong, T.H.; Hyun, C.T. Effect of project characteristics on project performance in construction projects based on structural equation model. Expert Syst. Appl. 2009, 36, 10461–10470. [Google Scholar] [CrossRef]
- Xiong, B.; Skitmore, M.; Xia, B.; Masrom, M.A.; Ye, K.; Bridge, A. Examining the influence of participant performance factors on contractor satisfaction: A structural equation model. Int. J. Proj. Manag. 2014, 32, 482–491. [Google Scholar] [CrossRef] [Green Version]
- Cronbach, L.J.; Schönemann, P.; McKie, D. Alpha Coefficients for Stratified-Parallel Tests. Educ. Psychol. Meas. 1965, 25, 291–312. [Google Scholar] [CrossRef]
- George, D.; Mallery, P. SPSS for Windows Step-by-Step: A Simple Guide and Reference, 7th ed.; Routledge: Abingdon, UK, 2006; ISBN 978-0205515851. [Google Scholar]
- Hair, J.F., Jr.; Black, W.C.; Babin, B.J.; Anderson, R.E. Multivariate Data Analysis, 7th ed.; Pearson Education Limited: Harlow, UK, 2014; ISBN 978-1292021904. [Google Scholar]
- Peterson, R.A.; Kim, Y. On the relationship between coefficient alpha and composite reliability. J. Appl. Psychol. 2013, 98, 194–198. [Google Scholar] [CrossRef] [PubMed]
- Ho, R. Handbook of Univariate and Multivariate Data Analysis and Interpretation with SPSS; Chapman& Hall/CRC: Boca Raton, FL, USA, 2006; ISBN 978-1420011111. [Google Scholar]
- Fornell, C.; Larcker, D.F. Evaluating Structural Equation Models with Unobservable Variables and Measurement Error. J. Mark. Res. 1981, 18, 39. [Google Scholar] [CrossRef]
- Washington, S.P.; Karlaftis, M.G.; Mannering, F. Statistical and Econometric Methods for Transportation Data Analysis, 2nd ed.; CRC Press: Boca Raton, FL, USA, 2010; ISBN 978-1420082852. [Google Scholar]
- Hooper, D.; Coughlan, J.; Mullen, M. Structural Equation Modelling: Guidelines for Determining Model Fit. Electron. J. Bus. Res. Methods 2008, 6, 53–60. [Google Scholar]
- Wheaton, B.; Muthen, B.; Alwin, D.F.; Summers, G.F. Assessing Reliability and Stability in Panel Models. Sociol. Methodol. 1977, 8, 84. [Google Scholar] [CrossRef]
- Jöreskog, K.G.; Sörbom, D. Recent Developments in Structural Equation Modeling. J. Mark. Res. 1982, 19, 404–416. [Google Scholar] [CrossRef]
- Steiger, J.H. Understanding the limitations of global fit assessment in structural equation modeling. Pers. Individ. Dif. 2007, 42, 893–898. [Google Scholar] [CrossRef]
- Hu, L.T.; Bentler, P.M. Cutoff criteria for fit indexes in covariance structure analysis: Conventional criteria versus new alternatives. Struct. Equ. Model. 1999, 6, 1–55. [Google Scholar] [CrossRef]
- Tabachnick, B.G.; Fidell, L.S. Using Multivariate Statistics, 5th ed.; Allyn & Bacon: Needham Heights, MA, USA, 2006; ISBN 978-0205459384. [Google Scholar]
- Bentler, P.M. Comparative fit indexes in structural models. Psychol. Bull. 1990, 107, 238–246. [Google Scholar] [CrossRef] [PubMed]
- Bentler, P.M.; Bonett, D.G. Significance tests and goodness of fit in the analysis of covariance structures. Psychol. Bull. 1980, 88, 588–606. [Google Scholar] [CrossRef]
- Byrne, B.M. Structural Equation Modeling with LISREL, PRELIS, and SIMPLIS: Basic Concepts, Applications, and Programming; Psychology Press: Road Hove, UK, 1998; ISBN 978-0805829242. [Google Scholar]
- Mulaik, S.A.; James, L.R.; Van Alstine, J.; Bennett, N.; Lind, S.; Stilwell, C.D. Evaluation of Goodness-of-Fit Indices for Structural Equation Models. Psychol. Bull. 1989, 105, 430–445. [Google Scholar] [CrossRef]
- Sobel, M.E. Asymptotic Confidence Intervals for Indirect Effects in Structural Equation Models. Sociol. Methodol. 1982, 13, 290. [Google Scholar] [CrossRef]
- Cerezo-Narváez, A.; Otero-Mateo, M.; Pastor-Fernández, A. From requirements agreement to changes integration: Keys not failing in construction projects. DYNA Ing. Ind. 2017, 92, 254. [Google Scholar]
- Cho, C.-S.; Gibson, G.E., Jr. Building Project Scope Definition Using Project Definition Rating Index. J. Archit. Eng. 2001, 7, 115–125. [Google Scholar] [CrossRef]
- Bingham, E.; Gibson, G.E. Infrastructure Project Scope Definition Using Project Definition Rating Index. J. Manag. Eng. 2017, 33, 04016037. [Google Scholar] [CrossRef]
- Kim, M.H.; Lee, E.B.; Choi, H.S. Detail Engineering Completion Rating Index System (DECRIS) for optimal initiation of construction works to improve contractors’ Schedule-Cost performance for offshore oil and Gas EPC projects. Sustainability 2018, 10, 2469. [Google Scholar] [CrossRef] [Green Version]
- Hansen, S.; Too, E.; Le, T. Retrospective look on front-end planning in the construction industry: A literature review of 30 years of research. Int. J. Constr. Supply Chain Manag. 2018, 8, 19–42. [Google Scholar]
- Desmond, C.L. Work Breakdown Structure. In Project Management for Telecommunications Managers; Kluwer Academic Publishers: Boston, MA, USA, 2012; pp. 71–72. ISBN 978-1402077289. [Google Scholar]
- Nayak, M.K.; Mohanty, S. Schedule Risk Analysis of ICT Infrastructure Projects. Int. J. Comput. Appl. 2012, 38, 1–5. [Google Scholar]
- Altahtooh, U.; Alaskar, T. Understanding Relationship between Milestone and Decision-Making in Project Management: A Qualitative Study among Project Managers in Saudi Arabia. Int. J. Bus. Manag. 2018, 13, 184. [Google Scholar] [CrossRef] [Green Version]
- Kim, H.-S.; Park, S.-M.; Kim, S.-G.; Han, S.-J.; Kang, L.-S. BIM Application and Construction Schedule Simulation for the Horizontal Work Area. Int. J. Civ. Environ. Eng. 2017, 11, 1581–1586. [Google Scholar]
- Lin, W.Y.; Huang, Y.H. Filtering of irrelevant clashes detected by BIM software using a hybrid method of rule-based reasoning and supervised machine learning. Appl. Sci. 2019, 9, 5324. [Google Scholar] [CrossRef] [Green Version]
- Su, L.; Cao, Y.; Chen, R. Research on WBS-based risk identification and the countermeasures for real estate projects’ entire course. In Proceedings of the 8th International Conference on Information Systems for Crisis Response and Management (ISCRAM), Harbin, China, 25–27 November 2011; IEEE: Harbin, China, 2011; pp. 223–226. [Google Scholar]
- Zou, Y.; Kiviniemi, A.; Jones, S.W.; Walsh, J. Risk Information Management for Bridges by Integrating Risk Breakdown Structure into 3D/4D BIM. KSCE J. Civ. Eng. 2019, 23, 467–480. [Google Scholar] [CrossRef]
- Hillson, D.; Grimaldi, S.; Rafele, C. Managing Project Risks Using a Cross Risk Breakdown Matrix. Risk Manag. 2006, 8, 61–76. [Google Scholar] [CrossRef]
- Mhetre, K.; Konnur, B.A.; Landage, A.B. Risk Management in Construction Industry. Int. J. Eng. Res. 2016, 5, 153–155. [Google Scholar]
- Navon, R.; Sacks, R. Assessing research issues in Automated Project Performance Control (APPC). Autom. Constr. 2007, 16, 474–484. [Google Scholar] [CrossRef]
- Sepasgozar, S.M.E.; Karimi, R.; Shirowzhan, S.; Mojtahedi, M.; Ebrahimzadeh, S.; McCarthy, D. Delay Causes and Emerging Digital Tools: A Novel Model of Delay Analysis, Including Integrated Project Delivery and PMBOK. Buildings 2019, 9, 191. [Google Scholar] [CrossRef] [Green Version]
- Palacios, J.L.; Gonzalez, V.; Alarcón, L.F. Selection of Third-Party Relationships in Construction. J. Constr. Eng. Manag. 2014, 140, B4013005. [Google Scholar] [CrossRef]
- Montes, M.V.; Ponce, M.E.; Falcón, R.M.; Ramírez-de-Arellano, A. Aproximación a la gestión económica integral de las obras por procesos productivos: Elaboración del modelo COP de control de costes de construcción. Inf. Constr. 2017, 69, 1–11. [Google Scholar] [CrossRef] [Green Version]
- International Organization for Standardization. ISO 21511:2018. Work Breakdown Structures for Project and Programme Management, 1st ed.; International Organization for Standardization: Geneva, Switzerland, 2018. [Google Scholar]
Standard | Value | Design | Change | Quality | Time | Resource | Supply | Cost | Risk | Delivery |
---|---|---|---|---|---|---|---|---|---|---|
ISO | X | X | X | X | X | X | ||||
IPMA | X | X | X | X | X | X | X | X | ||
PMI | X | X | X | X | X | X | X | |||
PMAJ | X | X | X | X | X | X | ||||
AXELOS | X | X | X | X | X | X |
Criterion: | Comment |
---|---|
Global Vision: | Integrate to simplify, prevent omissions, and allow global analysis of the deliverable |
Strategy: | Segregate to facilitate cross-referencing and save resources |
Homogeneity: | Share measurement units and measurement approaches |
Appraisal: | Be executed by a single trade to be paid once completed |
Equity: | Make the investment profitable avoiding construction units that are executed separately |
Analysis: | Meet aggregation criteria for cost analysis |
Normalization: | Facilitate searches and comparisons |
Chang and Tsai 2003 [54] | Jung and Woo 2004 [48] | Ibrahim et al. 2009 [45] | Rianty et al. 2018 [55] | Ramadhan et al. 2019 [56] | |||||
---|---|---|---|---|---|---|---|---|---|
1 | Type | 1 | Facility | 1 | Location | 1 | Name | 1 | Name |
2 | Life Cycle | 2 | Space | ||||||
3 | Element | 2 | Element | ||||||
4 | Section | 3 | Section | 2 | Section | 2 | Section | ||
3 | Area | ||||||||
4 | Sub-section | 3 | Sub-section | ||||||
5 | Aid | 4 | Aid | ||||||
3 | Product | 6 | Product | 5 | Product | ||||
4 | Function | 7 | Attribute | 6 | Work Unit | 5 | Work Unit | 4 | Work Unit |
5 | Task | 8 | Management | 6 | Activity | 5 | Activity | ||
6 | Resource | 7 | Resource | 6 | Resource |
ISO 12006-2 | ISO 81346-12 | OmniClass | CoClass | CCS | UniClass |
---|---|---|---|---|---|
Information | Information | Documents | Forms | ||
Products | Components | Products Materials | Components | Components | Products |
Agents | Disciplines Roles | Documents | Agents | ||
Aids | Tools | Equipment | Tools Equipment | ||
Management | Services | Documents | PM | ||
Processes | Phases | Documents | Phases | ||
Complexes | Complexes | Complexes | |||
Entities | By Functions By Forms | Entities | Entities | Entities Activities | |
Built Spaces | Spaces | By Functions By Forms | Spaces | Built Spaces User Spaces | Spaces Locations |
Elements | By Functions By Technics | Elements | By Functions By Technics | By Functions By Technics | Functions Systems |
Work Results | Work Results | Production | |||
Properties | Properties | Properties Landscape | Classes | Properties CAD |
Code | Edition | Ref | Scope | Organization | |
---|---|---|---|---|---|
First | Last | ||||
Masterformat | 1963 | 2018 | [103] | USA 1 | Construction Specifications Institute |
Uniformat | 1973 | 2010 | [104] | ||
OmniClass | 2006 | 2019 | [105] | ||
DIN 276-1 | 1993 | 2008 | [95] | Germany | Deutsches Institut für Normung |
BSAB | 1996 | 2005 | [96] | Sweden | Swedish Building Centre |
CoClass | 2015 | 2018 | [108] | ||
UniClass | 1997 | 2019 | [97] | UK 2 | Construction Project Information Committee |
TALO | 2000 | 2017 | [98] | Finland 3 | Building Information Foundation |
DBK | 2006 | 2010 | [99] | Denmark | Building Information Technology, Productivity, and Stands (Dansk Bygge Klassifikation) |
CCS | 2012 | 2017 | [109] | ||
CMCP | 2008 | 2014 | [94] | Europe | European Committee of Construction Economists(International coalition) |
ICMS | 2017 | 2019 | [100] | ||
ISO 12006-2 | 2001 | 2015 | [106] | World | International Organisation for Standardisation |
ISO 81346-12 | 2018 | 2018 | [107] |
Bin Variable | 1 | 2 | 3 | 4 | 5 |
---|---|---|---|---|---|
Age (in years) | <25 | 25–30 | 31–45 | 46–60 | >60 |
Company size (Staff size) | Freelance 0 | Micro 1–9 | Small 10–49 | Medium 50–249 | Large >250 |
Avg. project duration size (in months) | <4 | 4–12 | 13–24 | 25–48 | >48 |
Avg. project budget size (in €) | <100 k | 100 k–500 k | 500 k–1 M | 1 M–2 M | >2 M |
PM training (Highest level only) | – | Degree | Postgrad | Master | PhD |
Knowledge (ISO 21500/PMI PMBOK/IPMA ICB) | Poor | Fair | Average | Good | Excellent |
Experience in the construction industry (in years) | <1 | 1–5 | 6–10 | 11–20 | >20 |
PM certification (Highest recognition only) | – | CAPM IPMA-D | PMP IPMA-C | PGMP IPMA-B | PFMP IPMA-A |
Scope Design: | |
Q01 | Agreement on requirements |
Q02 | Scope definition |
Q03 | Deliverables definition (regarding specifications and acceptance criteria) |
Scope Development: | |
Q04 | Work breakdown |
Q05 | Work organization (prevention of tasks omission) |
Q06 | Identification of activities |
Project Success: | |
Q07 | Performance of project constraints (time, cost, quality, risks, resources) |
Q08 | Stakeholders’ satisfaction (clients, users, shareholders) |
Q09 | Project outcomes usability (products and/or services) |
Organization Success: | |
Q10 | Compliance with strategic objectives (alignment) |
Q11 | Market positioning (creation, expansion, and consolidation) |
Q12 | Profit generation (business) |
(a) | (b) | ||||
---|---|---|---|---|---|
Technical Roles | Number | Average | Managerial Roles | Number | Average |
Architects | 112 | 44.8% | Portfolio Managers | 48 | 19.2% |
Civil Engineers | 45 | 18.0% | Program Managers | 59 | 23.6% |
Industrial Engineers | 39 | 15.6% | Project Managers | 82 | 32.8% |
Quantity Surveyors | 54 | 21.6% | PM Team | 61 | 24.4% |
250 | 250 |
Item | Statistical Properties | CIT | CIM |
---|---|---|---|
n | Sample | 250 | 250 |
μ | Mean | 76.95% | 77.50% |
σ2 | Heterogeneity | 22.91% | 22.36% |
1-α | Confidence interval | 95.45% | 95.45% |
E | Statistical error | 02.97% | 02.93% |
Item | Question | CIT Sample | CIM Sample | ||
---|---|---|---|---|---|
μ | σ | μ | σ | ||
F1 | Scope Design: | 3.95 | 1.03 | 3.97 | 1.03 |
Q01 | Agreement on requirements | 4.47 | 0.71 | 4.36 | 0.71 |
Q02 | Scope definition | 3.93 | 0.88 | 3.90 | 0.88 |
Q03 | Deliverables definition (specifications and acceptance criteria) | 3.46 | 1.18 | 3.65 | 1.18 |
F2 | Scope Development: | 4.05 | 0.89 | 4.11 | 0.89 |
Q04 | Work breakdown | 4.00 | 0.88 | 4.11 | 0.88 |
Q05 | Work organization (prevention of tasks omission) | 4.14 | 0.89 | 4.20 | 0.89 |
Q06 | Identification of activities | 4.00 | 0.90 | 4.03 | 0.90 |
4.00 | 0.96 | 4.04 | 0.96 |
Item | Question | CIT Sample | CIM Sample | ||
---|---|---|---|---|---|
μ | σ | μ | σ | ||
C1 | Project Success: | 4.35 | 0.84 | 4.33 | 0.83 |
Q07 | Performance of project constr. (time, cost, quality, risks, resources) | 4.23 | 0.87 | 4.16 | 0.84 |
Q08 | Stakeholders’ satisfaction (clients, users, shareholders) | 4.24 | 0.89 | 4.24 | 0.84 |
Q09 | Project outcomes usability (products and/or services) | 4.60 | 0.70 | 4.58 | 0.75 |
C2 | Organization Success: | 3.96 | 1.00 | 3.99 | 1.01 |
Q10 | Compliance with strategic objectives (alignment) | 3.91 | 0.98 | 3.93 | 0.94 |
Q11 | Market positioning (creation, expansion, and consolidation) | 4.04 | 0.98 | 4.02 | 1.01 |
Q12 | Profit generation (business) | 3.92 | 1.04 | 4.02 | 1.07 |
4.16 | 0.94 | 4.16 | 0.94 |
Hypotheses | Positive Influence | ||
---|---|---|---|
H1 | (F1) Scope Design | → | (F2) Scope Development |
H2 | → | (C1) Project Success | |
H3 | → | (C2) Organization Success | |
H4 | (F2) Scope Development | → | (C1) Project Success |
H5 | → | (C2) Organization Success | |
H6 | (C1) Project Success | → | (C2) Organization Success |
Items | Principal Components | |||
---|---|---|---|---|
F1 | F2 | |||
CIT | CIM | CIT | CIM | |
Q01 | 0.798 a | 0.853 a | ||
Q02 | 0.824 | 0.832 | ||
Q03 | 0.532 | 0.744 | ||
Q04 | 0.766 a | 0.856 a | ||
Q05 | 0.742 | 0.829 | ||
Q06 | 0.762 | 0.819 |
Items | Principal Components | |||
---|---|---|---|---|
C1 | C2 | |||
CIT | CIM | CIT | CIM | |
Q07 | 0.820 a | 0.812 a | ||
Q08 | 0.831 | 0.822 | ||
Q09 | 0.709 | 0.763 | ||
Q10 | 0.807 a | 0.806 a | ||
Q11 | 0.872 | 0.872 | ||
Q12 | 0.866 | 0.829 |
Questions | Variance Explained | KMO Test | Bartlett Test | |||
---|---|---|---|---|---|---|
CIT | CIM | CIT | CIM | CIT | CIM | |
Q01–Q06 | 82.51% | 87.37% | 0.771 | 0.868 | 283.81 (15,*) | 557.51 (15,*) |
Q07–Q12 | 87.64% | 87.12% | 0.766 | 0.793 | 448.07 (15,*) | 464.29 (15,*) |
Variables | All (12) | F1 | F2 | C1 | C2 | |||||
---|---|---|---|---|---|---|---|---|---|---|
CIT | CIM | CIT | CIM | CIT | CIM | CIT | CIM | CIT | CIM | |
Cα | 0.831 | 0.890 | 0.599 | 0.717 | 0.627 | 0.782 | 0.696 | 0.716 | 0.805 | 0.783 |
CR | 0.864 | 0.910 | 0.768 | 0.852 | 0.801 | 0.873 | 0.831 | 0.841 | 0.885 | 0.874 |
Items | SRWs | SMCs | ||||
---|---|---|---|---|---|---|
F1 | F2 | |||||
CIT | CIM | CIT | CIM | CIT | CIM | |
Q01 | 0.626 | 0.769 | 0.492 | 0.591 | ||
Q02 | 0.642 | 0.708 | 0.512 | 0.602 | ||
Q03 | 0.423 | 0.634 | 0.279 | 0.501 | ||
Q04 | 0.613 | 0.762 | 0.476 | 0.581 | ||
Q05 | 0.607 | 0.718 | 0.469 | 0.515 | ||
Q06 | 0.575 | 0.737 | 0.431 | 0.544 |
Items | SRWs | SMCs | ||||
---|---|---|---|---|---|---|
C1 | C2 | |||||
CIT | CIM | CIT | CIM | CIT | CIM | |
Q07 | 0.726 | 0.711 | 0.527 | 0.603 | ||
Q08 | 0.738 | 0.796 | 0.544 | 0.586 | ||
Q09 | 0.525 | 0.722 | 0.275 | 0.506 | ||
Q10 | 0.684 | 0.631 | 0.468 | 0.622 | ||
Q11 | 0.781 | 0.697 | 0.611 | 0.734 | ||
Q12 | 0.826 | 0.709 | 0.582 | 0.604 |
Variable | F1 | F2 | C1 | C2 | ||||
---|---|---|---|---|---|---|---|---|
CIT | CIM | CIT | CIM | CIT | CIM | CIT | CIM | |
AVE | 0.533 | 0.658 | 0.573 | 0.697 | 0.622 | 0.639 | 0.721 | 0.699 |
Type | Measure | Criteria | Reference | Index | Status | |
---|---|---|---|---|---|---|
CIT | CIM | |||||
AFM | χ2/DF | <5.00 | [162] | 1.915 | 1.915 | Ok |
p-value | <0.05 | [163] | 0.00003 | 0.00015 | Ok | |
RMSEA | <0.08 | [164] | 0.064 | 0.061 | Ok | |
SRMR | <0.08 | [165] | 0.053 | 0.045 | Ok | |
GFI | >0.90 | [166] | 0.939 | 0.943 | Ok | |
IFM | CFI | >0.90 | [167] | 0.942 | 0.964 | Ok |
NFI | >0.90 | [168] | 0.893 | 0.928 | Ok | |
NNFI | >0.80 | [169] | 0.920 | 0.950 | Ok | |
PFM | PNFI | >0.50 | [170] | 0.906 | 0.916 | Ok |
PGFI | >0.50 | [170] | 0.901 | 0.907 | Ok |
Project Criteria (C1) | Business Criteria (C2) | ||||
---|---|---|---|---|---|
Paths | Indirect Effects | Paths | Indirect Effects | ||
CIT | CIM | CIT | CIM | ||
F1-F2-C1 | 0.294 | 0.390 | F1-F2-C1-C2 | 0.256 | 0.312 |
F1-C1-C2 | 0.165 | 0.181 | |||
F2-C1-C2 | 0.161 | 0.197 |
Scope Development (F2) | Project Success (C1) | Organization Success (C2) | ||||||
---|---|---|---|---|---|---|---|---|
Paths | Direct Effects | Paths | Direct Effects | Paths | Direct Effects | |||
CIT | CIM | CIT | CIM | CIT | CIM | |||
F1-F2 | 0.924 | 0.906 | F1-C1 | 0.822 | 0.985 | F1-C2 | 0.533 | 0.755 |
F2-C1 | 0.702 | 0.889 | F2-C2 | 0.511 | 0.752 | |||
C1-C2 | 0.941 | 0.917 |
© 2020 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).
Share and Cite
Cerezo-Narváez, A.; Pastor-Fernández, A.; Otero-Mateo, M.; Ballesteros-Pérez, P. Integration of Cost and Work Breakdown Structures in the Management of Construction Projects. Appl. Sci. 2020, 10, 1386. https://doi.org/10.3390/app10041386
Cerezo-Narváez A, Pastor-Fernández A, Otero-Mateo M, Ballesteros-Pérez P. Integration of Cost and Work Breakdown Structures in the Management of Construction Projects. Applied Sciences. 2020; 10(4):1386. https://doi.org/10.3390/app10041386
Chicago/Turabian StyleCerezo-Narváez, Alberto, Andrés Pastor-Fernández, Manuel Otero-Mateo, and Pablo Ballesteros-Pérez. 2020. "Integration of Cost and Work Breakdown Structures in the Management of Construction Projects" Applied Sciences 10, no. 4: 1386. https://doi.org/10.3390/app10041386
APA StyleCerezo-Narváez, A., Pastor-Fernández, A., Otero-Mateo, M., & Ballesteros-Pérez, P. (2020). Integration of Cost and Work Breakdown Structures in the Management of Construction Projects. Applied Sciences, 10(4), 1386. https://doi.org/10.3390/app10041386